10 likes | 290 Views
BLUE – DESIGN RED - EXECUTION. Duration in month. 2017. 2016. 2014. 2015. 2013. 2012. 2011. 2010. TASK NAME. 31.8.17. 1.9.10. Red Line project. 84. 21.9.11. 21.10.12. 3.10.10. Launching shafts for TBM tunnels . 25. 16.4.14. 31.3.13. 9.12.10. TBM Tunnels. 41. 1.6.12.
E N D
BLUE – DESIGN RED - EXECUTION Duration in month 2017 2016 2014 2015 2013 2012 2011 2010 TASK NAME 31.8.17 1.9.10 Red Line project 84 21.9.11 21.10.12 3.10.10 Launching shafts for TBM tunnels 25 16.4.14 31.3.13 9.12.10 TBM Tunnels 41 1.6.12 1.10.14 9.12.10 46 NATM Tunnels 31.7.16 1.3.12 1.9.10 48 Underground Section: Stations and Boxes 1.7.12 1.10.15 1.9.10 70 At level sections 30.6.16 1.7.12 1.9.10 61 System and Rolling stocks 31.10.13 3.2.13 9 Operation and Maintenance tender 15.3.14 17.2.16 65 1.9.10 Rolling stocks 31.8.17 1.5.15 28 Testing and commissioning 1.5.15 31.5.16 Start of south end testing 13 1.5.16 31.8.17 Start of the underground Section testing 16