August 19, 2013. All Experimenters’ Meeting. Machine Status. Proton Source Commissioning and Studies 8/13-8/14 : Linac & Booster Maintenance Period Main Injector MI30 vacuum Work continues to resolve the high gas load at MI308 MI back-fed from Master Sub-Station
E N D
August 19, 2013 All Experimenters’Meeting
Machine Status • Proton Source Commissioning and Studies • 8/13-8/14: Linac & Booster Maintenance Period • Main Injector • MI30 vacuum • Work continues to resolve the high gas load at MI308 • MI back-fed from Master Sub-Station • KRS T85 work complete, but still using Feeder 45 for MI conventional • Need to schedule a 20 minute MI conventional power outage to remove the back-feed from Master Sub-Station after tunnel work. • SY120 • Neutrino Muon • G2 NM1 berm pipe progressing • Mtest • MC6 magnet replacement
MI 307 to 309 Section 1 Section 2 Section 3
Section 3 • Stable • Holding vacuum • No further work
Section 2 • Contamination • Bellows • Pirani Gauge • Samples sent for testing • Section 2 removed • Cleaning elements and building a new section in parallel • Leak check and reinstall
Section 1 • RGA Scan completed Friday • Did not reveal anything conclusive • Additional baseline scans this morning • Downstream end put under vacuum (not including collimator) • Heated bellows for 30 seconds • Ion pump tripped off. • Section 1 contaminated • Collimator beam pipe will be cleaned in place • Remainder of section replaced.
Neutrino Muon • G2 NM1 Berm Pipe Progress • Status – Welding third set of pipes in enclosure M. Geelhoed 8/16/2013
August 2013 DRAFT
Shutdown 2012 Schedules and Links: Schedule can be accessed from the Operations Home Page - Schedules -> Operations Schedule Direct link to schedule - http://www-ad.fnal.gov/ops/schedule.html