West Onslow Beach/ Topsail Beach Coastal Storm Damage Reduction Project

West Onslow Beach/ Topsail Beach Coastal Storm Damage Reduction Project. Town of Topsail Beach Board of Commissioners Brief July 9, 2014. Presented by U.S. Army Corps of Engineers Wilmington District. OVERVIEW. Project Update: Current Status Process to get to a Federal Project: Steps

aiko-hull
Download Presentation

West Onslow Beach/ Topsail Beach Coastal Storm Damage Reduction Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. West Onslow Beach/Topsail BeachCoastal Storm Damage Reduction Project Town of Topsail Beach Board of Commissioners Brief July 9, 2014 Presented by U.S. Army Corps of EngineersWilmington District

  2. OVERVIEW • Project Update: Current Status • Process to get to a Federal Project: Steps • Project History: How did we get where we are? • Project Description and Cost: What will the Federal Project achieve? • Fiscal Overview: How much have we spent and on what? • Project Authorization – FINALLY! • The Path to Construction

  3. PROJECT UPDATE • General Reevaluation Report defining the project was approved in final form in 2009 • Preconstruction, Engineering and Design Phase of Work: preliminary design documentation completed • Project is ready for preparation of construction documents once real estate acquisition has been completed • Project authorization received in 2014

  4. PROCESS TO GET TO A FEDERAL PROJECT • Request from a local entity and, in most cases, Congressional study authority • Cost-shared study completion to identify Federal interest in a potential project • Cost-shared preconstruction, engineering and design for preparation of project plans and specifications • Project authorization (can occur at any time after study completion) • Construction appropriation/Project Partnership Agreement Execution • Real Estate Acquisition • Construction Contract Award

  5. WOB/TOPSAIL BEACH PROJECT HISTORY • 4 Congressional study resolutions were used to undertake the original Feasibility Study that recommended a project at Topsail Beach. Feasibility Report was completed in 1990. • Project was authorized in Water Resources Development Act of 1992 • Design activities were completed in 1992; Town decided not to sign the Project Cooperation Agreement • Request was received to re-look at a Federal project in late 1990s, and General Reevaluation Report (GRR) was completed between 2001-2009 • Design activities for modified project were initiated in 2010 and preliminary design was completed in 2014 • Locally Preferred project was authorized in WRRDA 2014

  6. UPDATEDAUTHORIZED PROJECT

  7. UPDATEDAUTHORIZED PROJECT Project life: 50 years Initial construction cost: $39.4M ($25.6M Fed/$13.8M Non-Fed) Renourishment cost/life: $265.5M ($132.8M Fed/$132.8M non-Fed) 23,200 feet long Dune and Berm

  8. FINANCIAL SUMMARY PROJECT PHASE FEDERAL NON-FEDERAL TOTAL COST Feasibility Report (1990) $963,000 $963,000 Project Design $346,200 $115,400 $461,600 GRR (2001-2009) 75/25 cost share $2,025,750 $675,250 $2,701,000 50/50 cost share $ 499,000$499,000 $ 998,000 $2,524,750 $1,174,250 $3,699,000 Project Design $685,500 $228,500 $914,000 TOTALS: $4,519,450 $1,518,150 $6,037,600 Available funds remaining: $25k (coordination, budget process, PPA dev) Additional funds required for Econ Update: $60k ($45 Fed/$15 non-Fed)

  9. PROJECT AUTHORIZATION AT LAST: Water Resources Reform and Development Act of 2014

  10. THE PATH TO CONSTRUCTION • Complete economic/project cost update • Request and receive construction funds • Develop and execute a Project Partnership Agreement • Obtain Real Estate • Finalize construction bid documents • Award construction contract and initiate construction

  11. QUESTIONS? • BOTTOM LINE: • 13 years to study, design and authorize a project • Over $4.5M Fed and $1.5 Non-Fed funds invested to date • Over $150M Fed funding share once construction has initiated • Project authorization allows us finally to request funds for construction • Federal Project life: 50 years • Federal Non-Fed Total • Initial construction cost: $25.6M $13.8M $39.4M • Renourishment cost/life: $132.8M $132.8M $265.6M • TOTAL: $158.4M $146.6M $305M