110 likes | 231 Views
ggonzale:. ggonzale:. Herschel PACS Instrument Qualification Review Review Objectives and Organisation. G.Crone/G.Pilbratt Herschel/Planck Project. Instruments Review Cycles in Perspective. Spacecraft ITT SRR PDR CDR …
E N D
ggonzale: ggonzale: Herschel PACS Instrument Qualification ReviewReview ObjectivesandOrganisation G.Crone/G.Pilbratt Herschel/Planck Project PACS IQR - SCI-PT/33202
Instruments Review Cycles in Perspective Spacecraft ITT SRR PDR CDR … Phase B Phase C/D Launch Instruments: ISVR IIDR IBDR IHDR IQR … IFAR 1999 2000 2001 2002 2003 2004 2005 2006 2007 PACS IQR - SCI-PT/33202
From Qualification to Flight Acceptance • CQM at module (EQM) level : Delivery (DRB) Test readiness (TRR) Test review (PTR) 2005 After CQM System Campaign hold a Instrument Status Review • FM at instrument level: ILT TRR ILTs ILT Test review prior to warm-up (PTR) 2005 To decide on need for further tests or to terminate & deliver • FM at module (PLM) and system level: Delivery (DRB) Test readiness (TRR) Test review (PTR) 2006 In preparation of FAR Instrument Status Review PACS IQR - SCI-PT/33202
Herschel Status • Herschel Payload Module CDR completed in July and Space Segment CDR completed in October with official close-out end 2004 • Herschel EQM - Ready for Herschel CQM Focal Plane Units. • All Herschel Instruments: HIFI, PACS and SPIRE have successfully completed CQM Instrument Level Tests. • All instruments delivered and in ASED OTN. (N.B. SPIRE to be returned 17th January) • Instrument testing to commence April 2005 • Instrument FM program underway – Baseline delivery Nov 2005 PACS IQR - SCI-PT/33202
Herschel EQM PACS IQR - SCI-PT/33202
Herschel PFM status • All units passed CDR, manufacturing well underway • Optical bench delivered • HTT delivered, most cryo-components, instrumentation, MLI integrated • HOT delivered instrumentation, cryo-components and MLI mounted. Tank integrated on framework. Both fully integrated • Cylinder thermal shields delivered-Others completed • CVV cylinder delivered-Upper and lower bulk head imminent. • Integration to be completed by May 2005; first cool-down with MTD instrument prior to shipment to ESTEC for STM campaign PACS IQR - SCI-PT/33202
Instrument Qualification Review - Objectives Ref: IQR Proceedings - v2 Aug 26, 2004 - SCI-PT/27108 • Confirmation of instrument CQM hardware/software qualification • Completion of instrument design verification • Assessment of performance and compliance with sci. reqs • Identification and confirmation of improvements for FM • Completion of OBSW design and demonstration of functionality • Confirmation of EGSE design and demonstration of functionality • Confirmation of instrument operability - User Manual PACS IQR - SCI-PT/33202
IQR - Proceedings Data Package – complete delivery at K.O. [PACS] • Documents as identified in SCI-PT/27108 • Presentations as given during the K.O. meeting Review of Data Package [Board] • Discrepancies and open issues raised as RIDs • RIDs issued up to one week before co-location Answersto RIDs [PACS] • Provided, discussed and resolved at co-location Board Report = Result of the three items above [Board] PACS IQR - SCI-PT/33202
IQR Timeline K.O. Meeting and Data Pack today Preliminary feedback 18 Jan 2005 Issue of RIDs 02 Feb 2005 Co-location 10-11 Feb 2005 Issue of Board Report 25 Feb 2005 PACS IQR - SCI-PT/33202
Review Board / Representatives of third parties Herschel/Planck Project (ESTEC) G. Crone (chair) G. Pilbratt (co-chair) A. Heske (secretary) P. Estaria J. Rautakoski F. Pedersen T. van der Laan Industry Representative G. Doubrovik (Alcatel) SPIRE Representative B. Swinyard (RAL) Funding Agency Representatives M. Falvella (ASI) K. Mercier (CNES) K. Proetel (DLR) H. Schroeven-Deceuninck (Prodex) Experts D. Schink (Astrium) B. Collaudin (Alcatel) G. Coe (ESTEC) F. Marliani (ESTEC) PACS IQR - SCI-PT/33202
PACS IQR K.O. - Agenda 09:00 Welcome MPE 09:05 Review Organization and Objectives ESA 09:15 Introduction – IHDR close-out and docs MPE 09:45 Instrument Qualification Status and plans for PFM MPE Mechanical, Thermal, Electrical I/Fs and EMC, Optical 11:45 PhFPU Qualification and plans for PFM CEA 12:15 Ge:Ga detector arrays Qualification MPE with Coffee Break at 11:00 12:45 Lunch 13:45 On-Board Software and UM MPE 14:15 EGSE, I-EGSE and MIB MPE 14:25 CQM/AVM ILT Results MPE 15:30 PA/QA Status MPE 15:40 Management and Schedule MPE 15:55 Critical Items and next steps MPE 16:15 Lessons learnt from CQM Integration in Industry MPE 16:30 Questions and Clarifications All 17:00 First Impressions and Feedback ESA with Coffee Break at 15:15 PACS IQR - SCI-PT/33202