An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Bailey HallDuct Bank Relocation ProjectOverview & Status May 19th, 2004

  2. Scope of Project • Drivers • Objective - re-establish in-service communications facilities in a re-routed duct bank behind Bailey Hall due to a State construction project. • To minimize impact – working pairs were audited and consolidated to the beginning of all 100 pair counts. • New pathway: • approximately 400’-450’ in length. • Two new pass-through manholes in the new route. • Copper media consists of an 1800 pair and two 1500 pair “mirror image” or “clock “ cables and a 300 pair copper cable.

  3. Scope of Project • Background and goals (Cont.) • Scope: • Installing and splicing an equivalent pair or strand count in the new pathway. • Re-establish service in a simultaneous method to reduce down time of each facility. • Both ends copper/fiber sections spliced concurrently. • Fiber work includes placing trunk fiber consolidating several hybrid cables. • Restricted construction schedule project and work will continue around the clock tentatively staring at 5pm on Friday, July 9th. • Clearing old ducts of existing copper and fiber. • Coordinated with CIT personnel during splicing as the cables contain groups of working voice and point-to-point circuits. • Whenever troubles are recognized on working pairs, they will be repaired before moving on to the next group.

  4. Buildings Effected

  5. Time frame of Project • Project is slated for the weekend starting Friday, July 9th after normal business hours. • Minimal impact to users by scheduling the major work during maintenance hours. • Intermittent disruption in service and will not be during normal Monday - Friday business hours.

  6. Schedule of Project

  7. Stakeholders • Identification of Stakeholders. • SRM, DDDH, CUFF • Facilities and building owners. • Cornell Police, Life Safety • Verification of scheduled events – Video Conferncing, CIT Labs • Special circuits – alarms, chilled water • CIT Divisions – I&D, BIS, CSM, DLS, S&O, Finance • NCS – Voice Eng, Network Eng, Operations Support, Field Services, Infrastructure Engineering • Campus Life, Alumni Affairs, Libraries, Day Hall • All Network Admins as well as Telecom Coordinators for the effected buildings.

  8. Communication Plan

  9. Communications Plan • Content of Stakeholder Communications: • Why it is occurring • When it will happen (with schedule of what to expect) • How long it will take • What areas are effected • Forum date • URL for Web-site • Who to contact mdr23@cornell.edu or 254.2766

  10. Contingency Plan • Contingency Plan - If a catastrophic event occurs, the cut-over would be rescheduled to another weekend once the stakeholders are notified and agree to the time frame adjustment.

  11. Wrap Up • Other Issues or Questions?