ERCOT PMO Update

ERCOT PMO Update. Robert Connell Director Program Management August Board of Directors Aug 16, 2005 (Through 7/31/05). 2005 YTD Project Performance. Third Quarter Results (to 7/31). Project Process Improvements In 2005. 3 completed, 24 YTD 23 in Initiation 21 in Planning

alafferty
Download Presentation

ERCOT PMO Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ERCOT PMO Update Robert Connell Director Program Management August Board of Directors Aug 16, 2005 (Through 7/31/05)

  2. 2005 YTD Project Performance Third Quarter Results (to 7/31) Project Process Improvements In 2005 • 3 completed, 24 YTD • 23 in Initiation • 21 in Planning • 35 in Execution • Instituting Managed Time Periods • Expand on Project Metrics – EVM • Establishing Risk Management Methodology Project Performance Project Activity

  3. Major ERCOT Projects Summary

  4. Large Capital Projects Information in August SO – PR50142 – Network Model Management System/Environment   Project over $3M in the Planning Phase Inform F&A on planning efforts Will request Board approval prior to beginning execution SO – PR40090 Operator Training Simulator (OTS) Project Components: SO-40090-1 OTS Center (Building modification) $100K to $500K (planning and execution in 2005) Moving from planning to execution on 8/15/05 SO-40090-2 OTS System (Hardware and software) $100K to $500K (2005 Planning) Over $3M (2006 execution) RO – PR50007 – Enhancement to FasTrak Project over $1M asking to move forward in purchasing software/move to execution Inform F&A and Board on efforts Presenting for Board approval to move forward Large Project Update

  5. Projects Completed 3rd Quarter • Projects Completed in July • PR-50001_01 Ancillary Services Reporting • PR-40075_01 Lodestar Enhancements for PRR-350 and PRR 471 • PR-50033_01 MV90 Software Purchase

  6. PR-50001_01 Ancillary Services • Scope of PR-50001_01 Ancillary Services The scope of this PUCT project includes Ad-hoc reporting capability against an Ancillary Services (AS) Market “subject area”. • Features and Deliverables: • includes AS Requests, AS Bids, and AS Deployments • includes prompts for Hour Ending, QSE name, and CM Zone; the ability to create custom prompts/filters was also included. • Current Activity • This completes the first of four subprojects for the PUCT: • 50001_01 Ancillary Services • 50001_02 Price Spike Analysis • 50001_03 Replacement Reserves Market Ad Hoc Reporting • 50001_04 Ad Hoc Access to QSE Down-Balancing Compliance Report Data • The three remaining sub projects of 50001 are scheduled to complete by 12/31/05. Planning 1 Months Execution 3 Months 4/4/05-7/8/05 3/1/05-4/4/05

  7. Lodestar Enhancement SIRs • Scope of PR-40075_01 Lodestar EnhancementSIRs: • PRR-471 NIDR to IDR Default Profile Scaling • PRR350 Smoothing Algorithm • Features and Deliverables: • PRR-471 NIDR to IDR Default Profiling: • Scaled the IDR default profile based on the load of the last NIDR readings to reduce load variance • PRR350 Smoothing Algorithm: • The QSE Project Managers directed ERCOT to remove DC tie import values before performing the smoothing algorithm; after the schedule has been smoothed, DC tie import values will be added back to the smoothed values for use in the Uncontrolled Resource charge type • Current Activity • The other part of the parent project is PRR488 Weather Determination which will be completed under PR-40075_02. Planning 4 Months Execution 9 Months 10/01/2004 – 07/01/2005 06/01/2004 - 09/30/2004

  8. MV90 Software Purchase • Scope of PR-50033_01 MV90 Software Purchase: • The scope of this project was to purchase the MV90xi version software supported by the following: • Current version of software, MV90 v5.0 becomes obsolete and unsupported by the vendor in May, 2007 • The software vendor is offering incentive pricing to its’ customers to make it attractive to upgrade to the new software prior to May, 2007 • Incentive pricing is being offered in a tiered-approach, with costs escalating over time – purchasing the software prior to 6/30/2005 will save ERCOT $110,000. • Features and Deliverables: • Purchased copy of the MV90xi versioned software. • Current Activity • The other part of the parent project is to implement the MV90xi versioned software which will be completed under PR-50033_02. Planning 1 week Execution 8 weeks 05/16/2005 – 07/31/2005 05/09/2005 - 05/13/2005