340 likes | 597 Views
2. How Do TRO Applications Arise in Construction? . Alleged Public Approval Process ViolationsProcedural or substantive requirements for permits, zoning, etc. Alleged Environmental Law Violations and Environmental Impacts. 3. How Do TRO Applications Arise in Construction? . Historic PreservationNative American SitesCommunity and Neighborhood OppositionTraffic, noise and blight.
E N D
1. 1
2. 2 How Do TRO Applications Arise in Construction? Alleged Public Approval Process Violations
Procedural or substantive requirements for permits, zoning, etc.
Alleged Environmental Law Violations and Environmental Impacts
3. 3 How Do TRO Applications Arise in Construction? Historic Preservation
Native American Sites
Community and Neighborhood Opposition
Traffic, noise and blight
4. 4 How Do TRO Applications Arise in Construction? Alleged Violations of Public Contracting Requirements
Competitive bidding laws and other special requirements for awards of public construction contracts
Public owner directs that a contractor perform out-of-scope (cardinal change)
5. 5 How Do TRO Applications Arise in Construction? Alleged Violations of Public Contracting Requirements (cont’d)
Public owner terminates a contractor and engages a replacement contractor without competitive bidding
Prime contractor seeks to replace a subcontractor
6. 6 How Do TRO Applications Arise in Construction? Consumer fraud, unlicensed contracting and unfair competition
Safety issues
Abandonment and/or removal of work
Infringement of intellectual property rights
7. 7 How Do TRO Applications Arise in Construction? Violations of labor laws and/or union agreements
Revocations of licenses, pre-qualifications, or building or other permits
Spoliation of evidence
Misuse of or absconding with funds
8. 8 Logistical and Strategic Issues Regarding Emergent Relief What Relief Is Potentially Available?
Administrative remedies
Jurisdictional issues
ADR
Gathering Information
Client documents
Public records
Discovery
Don’t Forget the Bond!
9. 9 HYPOTHETICAL A competitively bid bridge project
Owner: City of New Hope
Contractor: Go-To Contractors
City-funded with State matching
Contract
Time is of the essence
Termination for default
Arbitration clause
10. 10 HYPOTHETICAL Performance
Delays
Defects
Directive to accelerate
Deck failure
Termination
Notice
Locked out of site, including own trailer
Arbitration demand
Completion contract with Reliable Contractors
11. 11 ISSUES 1 AND 2
Impact of Arbitration Clause on Availability of Emergency Relief
What Emergency Relief Might Be Available?
12. 12 MORE HYPOTHETICAL Go-To files suit in federal court
Seeks a TRO to prevent the City from proceeding with replacement contract with Reliable
Seeks writ of mandate to regain access to its trailer
Seeks a TRO to protect all project records
13. 13 ISSUE 1
14. 14 Issue 1 Argument Arbitrability is question for courts
Here have a party to suit who is not party in arbitration
Majority: courts have jurisdiction for preliminary relief despite arbitration clause
Courts have power to preserve status quo pending arbitration
15. 15 Issue 1 Opposition Strong federal policy favoring arbitration
FAA mandates arbitration of issues subject to agreement to arbitrate
“Substantive” rights for arbitrators to decide
Court intervention improper when entangled with merits of underlying dispute
Non-party (i.e. replacement contractor) to arbitration clause is simply a red-herring
16. 16 Issue 1 Rebuttal Arbitration clause is not a waiver of compatible remedies
Injunctive relief from court and arbitration are not incompatible
Without preliminary relief from court, arbitration will be “hollow formality”
17. 17 Issue 1 Sur-Rebuttal Claims for injunctive relief not excepted from agreement to arbitrate
Filing of arbitration demand changes the game
The requested TRO effectively passes upon the merits
18. 18 ISSUE 2
19. 19 Issue 2 Argument FRCP 65 authorizes injunctions and TRO’s
State law permits injunction to challenge award of public contracts
Standards are met:
Likelihood of success on merits
Balance of hardships
Public interest
20. 20 Issue 2 Argument: Likelihood of Success Statutory duty to competitively bid contracts
Contract was terminated and new contract awarded
No exception to competitive bidding
No “emergency”
21. 21 Issue 2 - Argument:Balance of Hardships and Public Interest
Greater hardship to terminated contractor
Public interest in protecting taxpayer funds and integrity of public contracting
22. 22 Issue 2 - Opposition:Irreparable Injury
No “immediate and irreparable” injury here
Go-To’s potential harm strictly financial
23. 23 Issue 2 Opposition:Likelihood of Success Termination of “contract” v. “right to proceed”
Contract contemplates City of New Hope’s “right to proceed” without competitive bidding
“Emergency” exception to competitive bidding requirements
24. 24 Issue 2 - Opposition:Balance of Hardships and Public Interest
Greater hardship to City of New Hope
Public interest favors timely and safe completion of significant transportation project
25. 25 Issue 2 - Rebuttal Importance of competitive bidding
Seriousness of injury to contractor and public
Loss of ability to compete for public contract is irreparable harm
Ambiguity re nature of termination to be construed against owner
Disguised “emergency”
26. 26 Issue 2 Sur-Rebuttal Go-To has adequate remedy at law
Lack of proof of improper termination
Competitive bidding impracticable when “time is of the essence”
27. 27 ISSUE 3
28. 28 MORE HYPOTHETICAL Go-To requests expedited discovery
Physical evidence re deck failure
Spoliation of project documents
Propriety of termination
City moves to dismiss all claims
arbitration clause
City opposes TRO
City opposes discovery request
29. 29 ISSUE 3
30. 30 Issue 3 Argument Request for injunctive relief makes expedited discovery “particularly appropriate”
Notaro standard is met
“Reasonableness” standard is met
“Good cause” exists
The discovery is appropriately tailored
31. 31 Issue 3 Opposition Go-To’s burden of proof
Failure to satisfy criteria for granting of expedited discovery
Notaro, “reasonableness” and “good cause” standards
Failure to tailor discovery request to injunctive relief
Availability and scope of discovery are for arbitrators to determine
32. 32 Issue 3 Rebuttal Discovery is reasonably related to the injunction proceedings
Discovery is necessary to preserve status quo
Discovery is necessary to prevent irreparable harm
33. 33 Issue 3 Sur-Rebuttal Discovery request improperly encompasses merits of dispute
Failure to demonstrate arbitration-related discovery inadequate
34. 34 RULINGS