1 / 7

DRMS “ Bringing Our Service To The Customer”

Presented to: Lorna B. Estep, SES, Deputy Director for Supply , Directorate of Logistics, Headquarters Air Force Materiel Command Steven G. Schmidt, SES, Deputy Center Director , NASA Dryden Research Center, Edwards ARB November 2007. DRMS “ Bringing Our Service To The Customer”.

albert
Download Presentation

DRMS “ Bringing Our Service To The Customer”

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Presented to: Lorna B. Estep, SES, Deputy Director for Supply, Directorate of Logistics, Headquarters Air Force Materiel Command Steven G. Schmidt, SES, Deputy Center Director, NASA Dryden Research Center, Edwards ARB November 2007 DRMS “Bringing Our Service To The Customer”

  2. SR-71, Disposal Operations Multi-Service, Agency & Contractor Involvement Edwards Air Force Base Marine Corp Logistics Base Defense Logistics Agency NASA Air Force Materiel Command Defense Reut & Mktg Service NASA Drain/Purge Contract MCLB Security Scrap Venture AFMC Roll-Off Contract Tri-Rinse Shredder APCD/DTSC permits MCLB Safety Hw Contractor AFMC Support Team MCLB Environmental SV Roll-Off Contractor Tri-Rinse Fuel Contractor DRMS SR-71 Team Coordinating Disposition Efforts DEMAN Contractor

  3. SR-71, Disposal Plan In Progress Nov 07 May 07 Jun 07 Jul 07 Aug 07 Sep 07 Oct 07 Dec 07 AFMC/A4SM (SR-71 Project officer) and DRMS Program Manager conducted apreliminary site visit 21 May – 21 June. AFMC/DRMS teamed to initiate disposal action for NON Sensitive “H” conditioned support equipment. DRMS contractor mutilated on site, witnessed by DRMS and removed 192,000 lbs of residue. AFMC/DRMS staff on site segregating SR-71 parts by disposal method/process Continue improving disposal process Identified, segregated and consolidate electronic equipment, components, test sets, and circuit cards for shipment on DEMAN task orders. Successfully shipped 132,760 lbs to date. Final DEMAN task order for approx. 25,000 lbs scheduled for shipment Nov 10th AFMC/DRMS/SV workforce on site to uncrate, segregate and stage property eligible for shredding Tri-Rinse Shredding start date Sept 29th Identified asbestos containing property, segregated and place on disposal contract for ultimate destruction (burial) A total of 229,520 lbs of asbestos shipped in (44) Roll-off containers. Receipt, off-load & actual burial witnessed and Certified/Verified by CORs Identified end items with hazardous constituents, i.e. gas cylinders, support equipment containing fluids. AFMC fundedNASA contractor to drain/purge on site. Utilized Tri-Rinse shear and shredding process to dispose of end items as scrap

  4. SR-71, Disposal Plan Mutilation Process In Action Shear with 17K lbs pressure Large shredder crane feed Small shredder manually feed All (3) operating simultaneously

  5. SR-71, Asbestos Disposal Plan Complete CORs observed receipt/off-load Asbestos loaded for departure CORs Witness Burial Process Certified/verified destruction by burial

  6. SR-71, Disposal Plan Challenge & Solution • Challenge - During the first hour of full operations the main shredder experienced a hydraulic leak • The loss of hydraulic pressure immediately shut down the entire system. • One of the hydraulic hoses separated from the coupling and resulted in the release of approx 10-15 gallons of hydraulic fluid • Solution - The spill was immediately isolated, contained, and cleaned up by the Tri-Rinse staff in accordance with the provisions of their contract • The spilled hydraulic fluid was contained on the rubber containment mats under the shredder and with the addition of absorbent and absorbent pillows • The contaminated absorbent was place on a DRMS HW disposal contract & removed

  7. SR-71, Disposal Plan Challenge & Solution • Challenge - During the shredding process we experienced a fire that was caused by hot metal mixed with the shredded wooden boxes, crates & packing materials • Smoke was immediately detected by the operator and a DRMS employee monitoring the operation • Attempts by the SR-71 team to distinguish the smoldering content with fire extinguishers failed • The Fire Department was immediately called and extinguished the fire • Solution – We placed a spotter with a water hose to observe the shredding process and continuously wet down the content as it enters the roll-off

More Related