1 / 18

Experiences and Lessons Learned Electrification Indaba by Wolsey Barnard Executive Manager: INEP 15 March 2012

Experiences and Lessons Learned Electrification Indaba by Wolsey Barnard Executive Manager: INEP 15 March 2012. Introduction. Electrification programme in country has two distinctive periods – prior 2001 and post 2001; Prior 2001 - industry “number” chasing era;

aldon
Download Presentation

Experiences and Lessons Learned Electrification Indaba by Wolsey Barnard Executive Manager: INEP 15 March 2012

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Experiences and Lessons Learned Electrification Indaba by Wolsey Barnard Executive Manager: INEP 15 March 2012

  2. Introduction • Electrification programme in country has two distinctive periods – prior 2001 and post 2001; • Prior 2001 - industry “number” chasing era; • Post 2001 – “integrated” era, ensure processes are aligned with different Government policies; • This Indaba is 10 years into the 2nd era; • Good time to recap and asked seriously what was the “Experiences and Lessons learned” in this period.

  3. Connections between 1994 and 2011

  4. Enabling circumstances for effective electrification progammes

  5. Requirements for effective electrification • Following environment/circumstances is required to have an effective electrification programme: • Stable and effective electricity distribution industry; • Correct customer numbers and mix; • Integrated electrification planning and monitoring unit/agency; • Ring-fenced capital subsidy system for electrification; • Long-term transparent subsidy system; • Good project management systems need to be in place; • Effective financial and technical monitor systems to be in places as a key component of any electrification programme; • Required national/regional technical standards while projects need to be monitored against these standards;

  6. Requirements for effective electrification (…2) • Following environment/circumstances is required to have an effective electrification programme (continue): • Sufficient number of consulting engineers and contractors that are available to partake on a continuous basis in the electrification projects; • All stakeholders and role-players need to understand the electrification policy/rules; • Multi-year funding must be available for projects; • Pre-paid meters the most effective revenue collection method for electrification customers; • Common/standardization of technology from network designs to vending and IT platforms; • Electrification customers have to make a financial contribution to ensure responsibly for service/infrastructure.

  7. Misconception regarding electrification • Following misconception exist regarding electrification: • Electrification is only an electricity industry challenge – it is a social challenge; • Every new research breakthrough will result in new electrification product/implementation method; • Pilot projects will solve electrification problems - very few pilot projects are suitable for mass roll-out; • Electrification does not make commercial sense – at the most it can be a break even venture: • Recover connection costs via tariffs - consumption levels of rural costumers so low that it is impossible to recover capital and operations cost from the tariffs alone; • In most instances not even possible to recover operation costs to supply a rural customer;

  8. Misconception regarding electrification (cont..) • Following misconception exist regarding electrification projects (continue): • Metering technology can solve financial viability of electrification projects – non of the current metering solution (pre-paid meters, smart meters etc) can fulfil such a roll; • Electrification are completed with the switch-on ceremony - most electrification projects are designed to address only current needs and does not take into consideration (1) increase demand as customers financial position improving or (2) other economic activities emerged as a result of the upliftment/development of a community due to electrification. • Renewable energy technology systems requires no maintenance – need service providers and community responsible to take ownership of asset.

  9. Challenges in current electrification progamme

  10. Challenges Municipalities and Eskom • Slow delivery of electrification projects by Municipalities and certain Eskom regions. • Lack of skills within Municipalities – technical and project management. • Majority of Municipalities are not performing as required - internal procurement processes takes too long, even up to 7 months to appoint the consultants and just as long to complete the appointment of the contractors. • Eskom internal project management systems and ‘red type’ is slowing down delivery in certain regions. • Lack of implementation of FBE. • Consulting engineers and contactors not geographically spread according to backlogs in country. • Municipalities do not have purchase bargaining power. Non-grid programme • Slow roll-out of non-grid connections due to negative political perceptions and practical short comings. • Current non-grid systems not addressing basic electricity needs of customers – does not address heating and cooking needs. • Non-grid service providers struggle to exist financially due to small customer base and rural location. • Regulations promulgated recently increase non-grid installation costs dramatically.

  11. Challenges (...2) Electricity industry • Shortcomings in EDI are starting to have a very negative effect on the delivery of new connections. • Municipalities use electrification funds to do upgrading of existing networks. • Due to the nature of EDI, different electrification technical standards are implemented by Municipalities and Eskom. Funding and cost of connections • More and more connections done in rural areas – connections costs increase sharply and subsidy level have to be increased accordingly. • Electrification fund allocated in next 3 years will not increase annually above CPI - connection costs on average have increased annually by 12% over last 3 years. • Pressure is increasing on fund - received 4.2 times more applications from municipalities than what was available for 2012/13 financial year. Last 6 years INEP received 50% of the funding as projected in 2003/4 to address backlogs. • Annual budgetary process force projects to be planned and designed on an annual basis and not on a multi-year (project completion) basis. • High energisation/switch-on cost charged by Eskom. Municipalities have to pay up front , not as previously over 10 to 15 yrs period. • No soft loans or grants nationally or internationally available for normal grid extension, except if grid is renewable feed. • Difference in National and Local Government financial years.

  12. Challenges (...3) INEP • Planning, Monitoring and evaluation of electrification programme limited due to lack of resources – funding and HR; • Limited national planning capacity within INEP – Eskom Distribution and Transmission expansion and planning is dictating electrification roll-out. • INEP resources are stretched, since more and more operational involved in municipal projects. General • EIA and land clam process that took sometimes more than two years to resolve; • Late delivery of housing projects. • Sharp increase in hard ware cost (transformers, switch gear, cables) – increase in base metals prices. • Corruption staring to became a serious issue. • Local manufactures cannot compete with low cost imported equipment

  13. Thank you

  14. Current estimated backlogs

More Related