1 / 15

TIGER PROGRAM Lessons Learned

TIGER PROGRAM Lessons Learned. Great PA/NJ Regional Trail Projects Presentation to the Circuit Coalition May 15, 2014 Chris Stanford, P.E., PTOE, PMP Michael Baker Jr., Inc. Introduction/Background. PEC sponsored effort to improve “the process” Baker involved with 4 Tiger projects

alec
Download Presentation

TIGER PROGRAM Lessons Learned

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TIGER PROGRAM Lessons Learned Great PA/NJ Regional Trail Projects Presentation to the Circuit Coalition May 15, 2014 Chris Stanford, P.E., PTOE, PMP Michael Baker Jr., Inc.

  2. Introduction/Background • PEC sponsored effort to improve “the process” • Baker involved with 4 Tiger projects • Transportation Investment Generating Economic Recovery (TIGER) grant program • $17.2 Million in funding for 7 projects in Philadelphia

  3. Projects • Schuylkill River Trail • Shawmont Ave to Montgomery County line • Walnut Street Gateway • CSX Pedestrian Bridge • Boardwalk from Locust St. to South St. • Bartram’s Garden • East Coast Greenway • 58th St. Connector from Bartram’s Garden to Cobbs Creek Trail • Delaware Ave./Allegheny Ave. to Lewis St.

  4. Time Analysis Typical PennDOT Project Development Process: • Categorical Clearance Evaluation (CEE) Scoping Field View • Safety Review Approval • Preliminary Engineering • CEE Approval • Final Design Engineering • Final Plans, Specifications & Estimate (PS&E) • Bid Letting

  5. Time Analysis • Environmental Clearance Duration (CEE SFV to CEE approval) • Average = 1.8 years • Overall Design Duration (CEE SFV to Let Date) • Average = 3.2 years • Factors Affecting Schedule • Acquisition of Federal / State Funds • Environmental Clearance • PennDOT Review/Approval process • Completion of Railroad Agreements

  6. Acquisition of Federal/State Funds (i.e. TAP or PennDOT Multimodal) • Positive – Supply 70% -100% Construction funding • Negative – Federal Highway oversight, Federal requirements - Requires PennDOT Requirements and Approvals - 30% match or all pre-construction costs

  7. Environmental Clearance Historic / Cultural Resource Reviews • Identify potential historic/cultural resources early • (i.e. parks, historic properties/ structures over 50 years old, etc.) Recommendations: • Use CRGIS (crgis.state.pa.org) to identify resources in area • Identify in RFP • Gather required data and provide to PennDOT prior to SFV meeting

  8. Railroad Agreements Issue: Can delay construction by several months due to required railroad agreements Recommendation: • Start coordination early in process (after SFV meeting) • Utilize PUC staff

  9. Lessons Learned - City Specific Recommendations • Curb Line Changes - City Plan Change and curb stakes • Sidewalk Bicycling Ordinance – submission/approval by PCPC & DOS • Curb Extensions – DOS requires geometry and grading plans Recommendations: • Include above in Scope of Work

  10. Traffic Signals Issue: Scope of improvements changed late in design process. ADA requirements changed scope late in the process Recommendations: • Early field meeting with PennDOT, City design, maintenance and construction staff to determine improvements • Identify ADA improvements earlier in process

  11. Overlapping/Adjacent Projects Issue: PennDOT resurfacing projects and adjacent private projects result in redesign and extra coordination Recommendations: • Identify adjacent projects and work out work limits prior to construction, if possible • Contact the City, Municipalities and/or PennDOT to identify resurfacing and private projects in the area

  12. City / PennDOT Coordination Issue: Separate plan submissions / separate review comments. Recommendations: • Combined meetings / conference calls with PennDOT and City reviewers • Consolidated review comments

  13. Project Management Recommendations • Scope of work • Scope contracts in separate parts (i.e. preliminary and final design) • Environmental • Include scope for Cultural / Historic research in RFP or use PennDOT open end contacts • Consultant selection • Include PennDOT prequalification as a selection criteria • Funding • Use 15%-25% of estimated construction cost for req’d design funding • Consider a contingency fund • Inflation of construction costs • For grants/funding request, add 1%-3% yearly inflation for construction costs

  14. Project Management Recommendations • Surveying • Include $10K-25K per mile for field survey work • Construction Management/Construction Inspection costs • Include 10%-17% for CM/CI in cost estimates • Construction phase services • Include construction phase services in design contract • Railroad and PUC coordination • Include considerable design and construction costs for projects crossing RR tracks

  15. Conclusion • TIGER, TAP, Multimodal projects will have a tremendous positive impact on regional trail network • Recommendations are designed to streamline and improve the project development process Contact Info: Chris Stanford cstanford@mbakercorp.com 215-442-5333

More Related