1 / 19

Selected Topics in Management Information Systems [MOIS470] Fall 2004 Nahed Amin MS Project

Selected Topics in Management Information Systems [MOIS470] Fall 2004 Nahed Amin MS Project. Introduction. What’s Project Management? Project management is a matter of keeping scope , schedule and resources in balance Scope: the range of tasks required to accomplish project goals

aleda
Download Presentation

Selected Topics in Management Information Systems [MOIS470] Fall 2004 Nahed Amin MS Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Selected Topics in Management Information Systems [MOIS470] Fall 2004 Nahed Amin MS Project

  2. Introduction • What’s Project Management? • Project management is a matter of keeping scope,scheduleand resourcesin balance • Scope: the range of tasks required to accomplish project goals • Schedule: the time and sequence of each task, as well as the total project duration • Resources: the people and/or equipment that perform or facilitate project tasks

  3. Steps for Managing a Project • Project Definition: • Decide on the goals to be accomplished • Identify the major tasks • Agree on the available resources • Determine the schedule’s limit • Project Plan: • Identify all project tasks and who will do them • Get work and time estimates for tasks • Determine task dependencies • Enter task and project constraints

  4. Steps for Managing a Project • Tracking: • Track project progress comparing actual to original • Review resources, scope, and schedule factors • Identify problems that could knock off schedule • Analyze resource requirements over project • Make midstream changes to reach goals sooner • Project Close: • Compare original plan to actual one • Analyze problems for future improvements • Archive the project file

  5. Getting Started • Set clear project goals, scope and assumptions • Start a new project file • Enter a project start or finish date • Enter project goals, scope and assumptions • Save project

  6. MS Project Building Blocks • Tasks: • Actual work needed to be accomplished to meet project goals can be broken into tasks • The scope of a project consists of all its tasks • Resources: • The amount of resources can affect the project scope and schedule • Assignments: • Assigning resources to work on a task directly affects the time required to complete a task, and indirectly the total project time

  7. 1. Tasks • Break project into tasks, phases, and milestones: • Tasks: A concrete step required to meet project goal. It represents actual work to be done in the project • Phases: Consists of a group of related tasks. A phase represents a major step in the project • Milestones: Tasks that require no actual work. But just to indicate the beginning or end of a phase. Milestones are interim goals used to track the progress of the project

  8. 1. Tasks • Create a task list: • Include only tasks critical to project’s completion • Add detailed enough tasks so that the time to complete each one is short compared to overall project’s length • Remember tasks that occur repetitively, such as weekly meetings, status reporting, and anticipated revision work

  9. 1. Tasks • Enter tasks • Estimate task length: • Base estimates on: • Others’ experience • Your experience • Past records • Enter every task duration only, not its start or finish date

  10. 1. Tasks • Ensure to perform a logical, well-ordered task list • Add milestones • Order & group related tasks in tasks’ list. A straight list of tasks doesn’t indicate when one phase ends and another begins. The most common two grouping criteria: • Tasks belonging to the same process • Tasks to be completed in the same time period • Summing up summary tasks • Outline task list

  11. 1. Tasks • Link tasks: • Power of linking: • Let MS Project calculate all dates: every task start and finish dates, project finish date • See instantly how changes in start, finish, and duration of a task affect related tasks and whole schedule • Determine the best task sequence: • Identify dependencies of start or finish dates of a task on another one • A task that must start or finish before another task is called a predecessor task • A task that depends on start or finish of another task is called a successor task

  12. 1. Tasks • Link tasks: • Types of links: • Finish-to-start (FS) • Start-to-start (SS) • Finish-to-finish (FF) • Start-to-finish (SF)

  13. 1. Tasks • Link tasks: • Create links between tasks – avoid entering start or finish dates • Overlap or delay tasks: • Lag time • Lead time

  14. 1. Tasks • Add task’s constraints: • Constrain a task if: • The constraint reflects an actual time constraint in real world • The project will be penalized for not starting or finishing by a specific date • Types of constraints: • As Soon As Possible (ASAP) Finish no Later Than (FNLT) • As Late As Possible (ALAP) Start No Later Than (SNLT) • Finish no earlier than (FNET) Must Finish On (MFO) • Start No Earlier Than (SNET) Must Start On (MSO) • Enter constraints

  15. 2. Resources • Determine resource needs • Create a resource list: • A resource list includes: • The name of the resource • The maximum amount of time per day a resource is available to work • Enter the resource list

  16. 2. Resources • Determine the working times calendars: • There are two types of working times calendars: • A base calendar to store the planned working and non-working days and hours for a group of resources • A resource calendar containing the work schedule for only one individual resource • Modify the project calendar or create a working times calendar

  17. 3. Assignments • Assign resources to tasks: • Assigning resources to tasks provide several benefits: • The schedule mirrors actual circumstances more accurately • Responsibilities can be assigned for tasks • Workload is monitored to make adjustments in case any resource is overloaded • Pillars of task scheduling: work, duration, resources: • Work: amount of effort, measured in time units put into a task by a resource. The total work for a task is the sum of all these time units • Duration: amount of time between start & finish dates for a task • Resources: people, equipment, office space, etc • Assign one or more resources to each task

  18. Schedule’s Evaluation & Adjustment • Ensure the plan is accurate and complete • Review project goals, scope, assumptions • Add or delete tasks • Refine task-duration estimates • Check project finish date • Determine if constraints are necessary • Identify & correct obvious errors

  19. Plan’s Streamlining • Fine-tune schedule by making trade-offs among scope, resources, time; the three main factors that shape a project • Focus on: • shortening the schedule • Using resources as efficiently as possible

More Related