1 / 45

Project Introduction

Project Introduction. New high-tech classroom and lab facility Area : 30,000sq.ft. Function To provide a home for innovative courses that take a team based approach to problem solving and design. Inhabitants of building should feel a part of surrounding environ.

Download Presentation

Project Introduction

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Introduction • New high-tech classroom and lab facility • Area : 30,000sq.ft. • Function • To provide a home for innovative courses that take a team based approach to problem solving and design. • Inhabitants of building should feel a part of surrounding environ. • Create a work environment that stresses collaborative achievement.

  2. Project Constraints • Constrained site- limited by palm grove, existing buildings and sea • Budget - 5.5 million • Completed by 9/30/12 • Hurricane zone • Hot, humid climatic conditions; high heat loads • Structural system must withstand high winds and possible flooding • Floor height restrictions

  3. Site Context - Seaside, Florida Seaside Florida provides a rich and colorful oceanfront community with a unique architectural sophistication. City/ Campus Plan Hybrid Building, Steven Holl

  4. Existing Site Plan

  5. Design Concept 1 • Special architectural features • High heat load on east side • Solid auditorium structure • Inefficient floor plans

  6. Design Concept 2 • Meets height requirements • Limited cranage space • Compact but awkward floor plans

  7. Design Concept 3 • Light steel structure over flood protected “Core” Business • Inflexible architecture layout • Excessive use of concrete

  8. Architecture View of Building from road

  9. Site Plan

  10. South Elevation South-east Axon First Floor Plan

  11. West Elevation Second Floor Plan

  12. North Elevation Third Floor Plan

  13. East Elevation Section Through Auditorium

  14. Area Analysis Entry Perspective

  15. Interior Space Model First Floor View from Sea

  16. Interior Space Model Second Floor

  17. Interior Space Model Third Floor

  18. Iterative Processes Problem: Design for 3rd floor office wing, elevated slab • Wayfinding problems caused by numerous corridors • Quality of space corrupted by low ceiling heights • Elevated slab raises several constructability issues • Prohibitive complexity for architectural and structural design

  19. Iterative Processes Solution: Swap second and third floors entirely Large Classrooms Offices Auditorium • Walls to hide main Beams in • Large classrooms placed under • large open steel truss roofing • Simplified architectural design • Organized architectural design, faculty offices with exterior view

  20. Iterative Processes Leveraging Aesthetic and Functional Concerns • Architect prefers tighter spacing of structural elements to improve asymmetric balance • Glazed corner important to design concept • Large shear walls block a great deal of window wall on North elevation

  21. Structural System • Gravity loads • DL = 150 psf • LL = 50-100 psf • Wind load 120 psf • ASCE 7-95 • Preliminary system

  22. Office Wing • Shear wall system • Foundation • 9 ‘ Flat slab perimeter beam

  23. Flat Plate in SAP 2000

  24. Structural Model

  25. Gravity System • Beams • Cast in place 9”x12” (2.0%) • Columns • Custom precast 18”x18” (3%) / 20”x20” (3.5%) • Auditorium precast 26”x16” (1.5%) • Interior cast in Place 18”x18” (2%)

  26. Auditorium • Retaining wall / slab • Precast columns • Glass corners • Roof ?

  27. Lateral System Auditorium • Higher wind pressure • Shear wall connection • Ringbeam

  28. Integrated Solution • Hidden steel beams W24x450 (90%) • Larger shear walls • Reduced cantilever

  29. Structural Model

  30. Wind Deflection

  31. Cost Breakdown - $ 5,600,000

  32. Schedule - Start Date 1 May 2011Finish Date 25 Apr 2012

  33. Equipment Crane - Link Belt Hydraulic Truck Crane - HTC 11100 Backhoe Loader - Caterpillar 426C

  34. Comparison: Fenestration System

  35. Comparison: Column Construction Precast Cast-in-place

  36. 1 Aug 2011

  37. 12 Oct 2011

  38. 3 Nov 2011

  39. Opportunities for Off-site Fabrication • Copper roof • Auditorium Roof Truss • Precast concrete columns • Curtain wall and cladding frame

  40. Design Analysis • Location a factor in team dynamics • Tight design process between engineer and architect • Design process monitored by construction management

  41. Collaborative Successes Strong integration of structure and architecture Friendly relationship, friendly struggles Programmatic goals achieved through iterative design process Collaborative Inadequacies Lack of shared product model Creation of numerous design models, several for each discipline Difficulties with communicating key structural concerns Group Assessment

  42. Using Technology Collaborative Means Heavy use of web based technologies • NetMeeting • Email • Discussion Forums • Group web space • Technology cannot offset lack of communication • Learning new technologies requires time overhead and may not produce desired results

  43. Lessons learned • Everyone should use compatible technology • Shared product model saves time and increases efficiency across disciplines • Team should follow protocols for developing and sharing information • Greater understanding of other disciplines needs • If technology is used properly, time and effort are saved for the entire team

More Related