TGP Outages August & September 2013. Customer Webex July 25 th , 2013. Agenda. Review of Upcoming Outages August & September Q&A. Disclaimers.
E N D
TGP OutagesAugust & September 2013 Customer Webex July 25th, 2013
Agenda • Review of Upcoming Outages • August & September • Q&A
Disclaimers • Anticipated Impacts are estimates. Actual nominations, market demand, weather and pipeline conditions, etc. will determine if, and through what level, restrictions become necessary. • Unless otherwise stated, all scheduled dates represent gas days as defined in the Tennessee Gas Pipeline tariff to mean a period of twenty-four consecutive hours, beginning and ending at 9:00 a.m. (Central Clock Time).
Disclaimers • Scheduled dates are subject to change. • Projects may be added, altered, delayed or cancelled. • TGP will provide notice of such additions or changes via PASSKEY postings. • Dates as posted on PASSKEY should be deemed correct in the event of conflicts between PASSKEY posted dates and dates within this presentation.
Color Key for Maps • Green • No Impact Anticipated • Yellow • Restrictions are possible, but not likely • With extended duration, restrictions could be necessary from time to time • (M) denotes that meter(s) may be impacted, refer to EBB posting • Red • Restrictions are probable
Div 5 & 6 –August Outages Hydrotest 40-3 to 41-3 (7/8/2013-8/27/2013) ILI Pigging MLV 823-1 to 827-1 (8/6/2013)(M) Class change 511-1 to 512-1 (7/15/2013-8/7/2013) Hot Tap (M) 8-1 to 9-1 (7/26/2013-7/27/2013) ILI Pigging 4-3 to 9-3S (8/6/2013-8/8/2013) Cleaning Pig 409A-1101 to 409A-1102 (8/20/2013-8/21/2013) Unit Maintenance Sta. 409A (8/14/2013-8/21/2013) ESD Test Sta. 409 ESD (8/6/2013-8/7/2013) Sta. 409A ESD (8/8/2013-8/9/2013
2013 Outages – Offshore Outages Sta. 523 - Station & Line Tie-ins (7/24/2013-8/10/2013)(M) Sta. 523 (36") Line outage - SAM Sale Outage (6/22/2013-8/10/2013)(M) 507F-100 (Grand Chenier) -- SAM Sale Outage (7/22/2013-7/31/2013) (M) Sta 523 – Unit Outage (4/11/2013-8/10/2013)
Div 8 & 9 – August Outages Hydrotest109-3 to 110-3 (6/15/2013-8/15/2013) Rosehill Class Change 558 to 860 (Line 2 & 3) (7/15/2013-11/1/2013) Anomaly Remediation 72-1 to 77-1A (7/8/2013-8/16/2013) Bi-Directional Operation Sta 555 (5/29/2013-8/13/2013) Station MaintenanceSta. 843 (8/30/2013) Purchase Power Upgrade Sta. 834 (7/15/2013-7/29/2013) Station MaintenanceSta. 834 (8/7/2013)
Div 10(200 Line) – August Outages Anomaly Remediation 200-4 to 219-4 (11/16/2011-12/31/2013) 205-2 to 206-2 (8/15/2012-10/31/2013) 207-2 to 208-2(8/15/2013-10/31/2013) 208-2 to 209-2 (3/7/2012-8/15/2013) Station 219 Maintenance ESD (8/15/2013) Pipe Replacement MLV 204-4 (8/5/2013-10/11/2013) MLV 212-4(8/5/2013-10/11/2013) Hydrotest MLV 200-1A to 201-1 (7/18/2013-9/4/2013) MLV 203-1 to 204-1 (8/5/2013-10/11/2013) MLV 208-3 to 212-3 (8/2/2013-12/19/2013) 213-3 to 214-3 (8/5/2013-10/11/2013)
Div 10(200 Line) – August Outages Station Maintenance Sta 267 (8/27/2013-8/28/2013) Unit Maintenance Sta 266A (8/13/2013-8/16/2013) Sta 266A (8/19/2013-8/23/2013) Anomaly Remediation 268A-101.1 to 268A-103 (Fitchburg) (7/15/2013-8/16/2013) 267-1 to 270C-101 (Beverly Salem) (8/12/2013-8/23/2013) 270B-101.1 to 270B-103 (Concord) -(6/17/2013-8/2/2013) Anomaly Remediation 256-3A to 257-3 (8/26/2013-8/30/2013)
Div 10(300 Line) – August Outages Station 319 NEUP (8/15/2013-10/25/2013) Station 323A NEUP Station (8/5/2013-10/7/2013) Station 313 MPP Station (8/12/2013-8/30/2013) NEUP Tie-Ins 322-2 (8/20/2013-8/30/2013) 325-2 (8/15/2013-8/21/2013) Station MaintenanceSta 303 – MPP (8/5/2013-8/10/2013) 317-1 - Pig installation (8/19/2013-8/29/2013) Station 321 NEUP (7/15/2013-8/5/2013) Maintenance Pigs321-1 to 325-1 (8/30/2013)
Div 5 & 6 –September Outages Maintenance Pig Carthage Line (9/17/2013) (M) Station 40 Maintenance(9/2/2013-9/20/2013) ILI Pigging MLV823-1 to 827-1 (9/10/2013)(M) ILI Pigging MLV507G-100 to 507G-109 (9/25/2013)(M) ILI Pigging 409A-1101 to 409A-1102 (9/24 /2013-9/26/2013)
Div 8 & 9 – September Outages ILI Pig110-2 to 114-2S (9/1/2013-9/2/2013) (M) Rosehill Class Change 558 to 860 (Line 2 & 3) (7/15/2013-11/1/2013) Anomaly Remediation 69-2 to 78-2 (9/23/2013-10/17/2013) Pressure test 63-4 to 64-4 (9/1/2013-9/30/2013) (M)
Div 10(200 Line) – September Outages Anomaly Remediation 219-2 to 307-1 (9/1/2013 - 12/1/2013) 219-3 to 307-2 (9/1/2013 - 12/1/2013) Anomaly Remediation 200-4 to 219-4 (11/16/2011-12/31/2013) 205-2 to 206-2 (8/15/2012-10/31/2013) 207-2 to 208-2(8/15/2013-10/31/2013) 211-1 to 212-1(9/1/2013-9/15/2013) 211-2 to 212-2(9/15/2013-9/30/2013) Station 219 Maintenance MPP (9/8/2013-9/27/2013) Pipe Replacement MLV 204-4 (8/5/2013-10/11/2013) MLV 212-4(8/5/2013-10/11/2013) Station 209 Maintenance MPP (9/4/2013-11/8/2013) Hydrotest MLV 200-1A to 201-1 (7/18/2013-9/4/2013) MLV 203-1 to 204-1 (8/5/2013-10/11/2013) MLV 208-3 to 212-3 (8/2/2013-12/19/2013) 213-3 to 214-3 (8/5/2013-10/11/2013)
Div 10(200 Line) – September Outages Station Maintenance Sta. 264 (9/30- 10/4) Unit Maintenance Sta. 241 (9/9/2013-9/13/2013) Sta. 261 (9/5/2013 - 9/13/2013) Sta. 261 (9/16/2013 - 9/20/2013) Sta. 261 (9/3/2013 - 9/4/2013) Sta. 261 (9/30/2013- 10/4/2013) Sta. 264 (9/23/2013- 9/24/2013) Sta. 264 (9/25/2013- 9/26/2013) ESD Sta 230C (9/17/2013) Sta 237 (9/24/2013) Sta266A (9/17/2013 - 9/18/2013) ILI pigging 261B-101.1 to 261B-102 (Springfield) (9/24/2013-9/25/2013) Class Change 230B-200 Niagara Spur Loop Line (9/16/2013-10/7/2013) Line lowering 260A-100 (Northampton) (M) (9/3/2013-9/5/2013) Anomaly Remediation 248-2 to 249-2 (9/16/2013-10/5/2013) 258-1 to 259-1 (9/3/2013-9/13/2013)
Div 10(300 Line) – September Outages Meter Station Upgrade Meter 020207 (Mahwah) (9/2/2013-9/5/2013) Station 319 NEUP (8/15/2013-10/25/2013) Station 323A NEUP Station (8/5/2013-10/7/2013) Maintenance Pigs319-1 to 321-1 (9/15/2013) 319-1 to 321-1 (9/20/2013) 321-1 to 325-1 (9/30/2013) NEUP Tie-Ins Sta. 321 (9/16/2013-9/30/2013) 327-2(9/15/2013-9/21/2013)
We welcome your feedback/questions • Suggestions for improvements to this meeting • Are the meetings beneficial? • Is additional information needed? • Questions after the meeting? • Other? • Email to one of the following: • Your scheduler • PASSKEY Portal