1 / 9

EMGT 501 HW #3 10.3-5 10.4-5 Due Day: Sep 27

EMGT 501 HW #3 10.3-5 10.4-5 Due Day: Sep 27. 10.3-5. You are given the following information about a project consisting of six activities:. (a) Construct the project network for this project.

alicia
Download Presentation

EMGT 501 HW #3 10.3-5 10.4-5 Due Day: Sep 27

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EMGT 501 HW #3 10.3-5 10.4-5 Due Day: Sep 27

  2. 10.3-5. You are given the following information about a project consisting of six activities: (a) Construct the project network for this project. (b) Find the earliest times, latest times, and slack for each activity. Which of the paths is a critical path? (c) If all other activities take the estimated amount of time, what is the maximum duration of activity D without delaying the completion of the project?

  3. Start 0 10.3-5 a) A 5 B 1 4 2 E 6 D C 3 F Finish 0

  4. b) Critical Path: Start A E F Finish Length = 14 months c) 6 (=2+4) months

  5. 10.4-5 Sharon Lowe, vice president for marketing for the Electronic Toys Company, is about to begin a project to design an advertising campaign for a new line of toys. She wants the project completed within 57 days in time to launch the advertising campaign at the beginning of the Christmas season. Sharon has identified the six activities (labeled A, B, …, F) needed to execute this project. Considering the order in which these activities need to occur, she also has constructed the following project network. A C E F START FINISH B D

  6. Using the PERT three-estimate approach, Sharon has obtained the following estimates of the duration of each activity. Optimistic Most Likely Pessimistic Activity Estimate Estimate Estimate A 12 days 12 days 12 days B 15 days 21 days 39 days C 12 days 15 days 18 days D 18 days 27 days 36 days E 12 days 18 days 24 days F 2 days 5 days 14 days (a) Find the estimate of the mean and variance of the duration of each activity. (b) Find the mean critical path.

  7. (c) Use the mean critical path to find the approximate probability that the advertising campaign will be ready to launch within 57 days. (d) Now consider the other path through the project network. Find the approximate probability that this path will be completed within 57 days. (e) Since these paths do not overlap, a better estimate of the probability that the project will finish within 57 days can be obtained as follows. The project will finish within 57 days if both paths are completed within 57 days. Therefore, the approximate probability that the project will finish within 57 days is the product of the probabilities found in parts (c) and (d). Perform this calculation. What does this answer say about the accuracy of the standard procedure used in part (c)?

  8. 10.4-5 a) Activity A 12 0 B 23 16 C 15 1 D 27 9 E 18 4 F 6 4 b)

  9. (from the Normal table) (from the Normal table)

More Related