40 likes | 202 Views
Subsystem Mgrs F2F Meeting Calorimeter Subsystem. 15 June 2005 J. Eric Grove Naval Research Lab grove@ssd5.nrl.navy.mil. CAL Status. Completed final CPTs and calibrations on FM 111 – FM 118 Completed ATDPs and PreShip Reviews on FM 111 – FM 118. Shipped to SLAC FM 108 – FM 114
E N D
Subsystem Mgrs F2F MeetingCalorimeter Subsystem 15 June 2005 J. Eric Grove Naval Research Lab grove@ssd5.nrl.navy.mil J Eric Grove
CAL Status • Completed final CPTs and calibrations on FM 111 – FM 118 • Completed ATDPs and PreShip Reviews on FM 111 – FM 118. • Shipped to SLAC FM 108 – FM 114 • Post-ship testing in progress for FM 111 – FM 114 • Preparing FM 115 – FM 118 for shipment on 23 June. • Assembly and Test of Module 119 • PEM assembled and tested • AFEE boards installed and soldered • TEM/TPS safe-to-mate in progress J Eric Grove
Assembly and Test Completion Started ] This month ] Previously J Eric Grove
CAL Module Milestones Deliveries or Ready to Ship Shipped 6/6/05 Shipped 6/13/05 Ship 6/23/05 J Eric Grove