1 / 7

FTS Testing: Introduction

FTS Testing: Introduction. Chris Boone Test Readiness Review January 29, 2003. What We Know. Acceptance tests by ABB Bomem --Functionality --Resolution, stability Acceptance/verification tests at the subsystem level for some components. Science Team Testing (FTS).

Download Presentation

FTS Testing: Introduction

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FTS Testing: Introduction Chris Boone Test Readiness Review January 29, 2003

  2. What We Know • Acceptance tests by ABB Bomem --Functionality --Resolution, stability • Acceptance/verification tests at the subsystem level for some components

  3. Science Team Testing (FTS) • Instrument level testing of those components descoped by ABB Bomem due to compressed test schedule (imagers, suntracker). • Characterization of instrument behaviour under various conditions (particularly with changing instrument and detector temperature). • Keep in mind potential impacts on instrument performance from shock tests and any changes made by ABB Bomem since previous tests.

  4. “Resolved” Issues • Power Supply jumper wire --Easily resolved, no anticipated impact. • Improper capacitor induced instability in the InSb channel --Change capacitor. At UoT Monitor output for continued instability and for possible new problems arising from the change in electronics.

  5. “Resolved” Issues (continued) • Corner cube coating causes fatal polarization problems for the backup metrology laser for some temperatures. --Swap in uncoated corner cubes. ABB BomemMeasure modulation efficiency, at DFL or at UoT. If at UoT, equipment, personnel, procedure required. UoTSet aside time in test schedule.

  6. Lesson Learned • Detector Contamination --severely impacts performance. --decontamination event(s) may be required, may interrupt FTS test schedule. --schedule major (or contamination-sensitive) tests early or shortly after decontamination. • Contamination of passive cooler could limit the achievable detector temperature.

  7. Major Gaps in Our Knowledge • Performance of passive cooler • Characterization of the suntracker • Imager (all aspects) • Instrumental Line Shape • Performance above 3000 cm-1

More Related