S-RAMP Standardization Timeline. March 17 – August 2: Prepare Committee Specification Draft August 3 – September 3: Public Review of Draft (30 days) September 4 – October 2: Resolve comments from public review period
E N D
S-RAMP Standardization Timeline • March 17 – August 2: Prepare Committee Specification Draft • August 3 – September 3: Public Review of Draft (30 days) • September 4 – October 2: Resolve comments from public review period • October 3 – October 18: Public review draft with comments posted for 15 day public review cycle • October 19: Committee Specification Draft goes to a vote for approval • October 22 – December 17: Committee Specification Draft, if approved, is submitted as a Candidate OASIS Standard to TC Admin and undergoes a 60 day public review