1 / 22

HiRadMat Project team: WG2 report

Detailed overview of activities completed & planned at HiRadMat project, including removal of cooling pipes, cable trays, lighting, vacuum pipes, MTR shielding, and more. Lessons learned and ongoing tasks discussed.

almaguer
Download Presentation

HiRadMat Project team: WG2 report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HiRadMat Project team: WG2 report Agenda Last TS debriefing Lessons learned PR532 monitoring system for remote control Activities planned for Xmas shutdown (first part) Horn removal: plan

  2. Activitiescompleted in the last TS • Cooling pipes dismantling in TJ7 (+TNC) (CERAP) • Cleaning of TJ7 wall and floor (CERAP + RP) • Cable trays in TJ7 (Ineo) • Removal of old lighting and new temporary one in TNC (Ineo, Dino + FSU) • Vacuum pipe removal in TNC (FSU) • MTR shielding dismantling (Altead) • Scaffolding installation in TJ7 (Ouvaroff) • TJ7 structure modification for EN-EL (Ineo)

  3. TJ7 cooling pipes + cleaning + cable trays • Old contaminated pipes were fully disposed of and moved to TT4 (will be cut by Endel in W44) • Floor decontaminated (DG-SCR) • Old cable tray removed (Spie) • 3 new Cable trays installed (Ineo) • Liaison cable tray on the roof of TJ7 installed (Ineo) • Cable trays repairs in TA7 (Ineo)

  4. New temporary lighting • Old lighting was fully disposed of. • New temporary system set up..

  5. DN 250 vacuum pipes • DN 250 Vacuum pipes removed • 18 supports to be dismounted • End temporarily closed • Flange to be installed (like the horizontal one  Dino + Victor)

  6. MTR blockhouse removal MTR magnets + shielding in TCC6 May 2010 October 2010 TCC6 is now ready for primary beam installation during Xmas shutdown!

  7. MTR blockhouse removal MTR magnets + shielding in TCC6 July 2010 May 2010 September 2010 • In 4 Technical stops, more than 600 tons were removed • Beam line and tables: 5 tons • Cast iron blocks: 530 tons • 2 MTR’s magnets: 50 tons • Mobile shielding structure: 15 tons • Without damaging the neighboring TI2 line (but partially removal necessary in July) October 2010

  8. MTR blockhouse removal T1 block inventory liste des blocs stockes dans TCC 6 et TT 61. TTC 6 Ø  842 = 3 Ø  844 = 5 Ø  882 = 3 Ø  884 = 37 Ø  1682 = 2 Ø  1684 = 30 TT 61 Ø  842 = 1 Ø  882 = 1 Ø  884 = 3 Ø  1682 = 9 Ø  1684 = 14

  9. Scaffolding installation in TJ7 • All scaffoldings were installed

  10. TJ7 structure modification for EN-EL • Modification completed • Empty fire fighters cupboard removed • DN 250 vacuum pipe dismounted in the corner

  11. Activities in progress in the last TS and to becontinued • « Cremaillere » cleaning: tool installed • PR 532: 2 motions ready (translation + direction) • TNC air ducts • T1 target dismantling • Cable trays in TNC • Miscellaneous works to be done in TNC

  12. Cremaillere cleaning device • Device installed and successfully tested manually • Will be driven by crane PR532 once operational

  13. Crane PR532 repair • Not possible to move it with elevator • Operational along 2 directions • Load test still to be made • Highest priority for next accesses!

  14. Air duct dismantling • 150 m long air duct to be removed. • Contaminated dust inside and above • Removal test carried out  to be dismantled 2 part by 2 parts (internal link discovered) • New supporting framework manufactured • Lesson learnt: junction between parts must be quickly and easily dismountable  to be included in technical spec. for new air ducts. • Currently about 21 parts were removed (out of 50)

  15. T1 removal 30 T1 removal 300 Blindage mobile 20 300 3000 5000 175 Blindage fixe • 5 step dismantling procedure • Dedicated Lead-shielded container • No need to remove TI2 line • Similar operation in 2005  2 mSv • ISR 6 as long-term storage • Target Monitors (TBID, TBIU) and head removed on 20.10.2010 BAC Potence Moniteur 45 Débit de dose en uSv/h en Mars 2010 Courtesy of D. Grenier

  16. T1 removal T1 removal

  17. TNC Cable trays • Only the consoles were installed waiting for the painting works during Xmas shutdown • 4 ladders up to Irradiation area then 2 up to the end of TNC. • 3 yellow supports in the way and some welded consoles to be removed.

  18. Miscellaneous work to be done in TNC • Cover holes in TNC & TJ7 • Fix Red phone • Remove and rebuild new barrack

  19. Lessons learnt • Transport passage through TJ7 is very difficult during the working hours and time consuming  to be done during the night • Electrical installation in TJ7 to be quickly upgraded: no sufficient 230V plugs  new LV cabinet to be installed asap (Alexandre) • RP safety consumables (shoes covers, Ti-vet, gloves) in shortage  get a larger stock available in BA7 (Nadine, Dino) • Lack of room in TT4 in order to store waste (air ducts for instance)  ISR3 as backup solution • Lack of trailers in order to move air ducts to TT4  Logistics to be improved • Absence of ENDEL  a cleaning company must be present at each TS to intervene quickly if needed. TJ7 floor decontamination was done by DG-SCR. • Alara principle must be applied at the design stage: the difficulties we faced to disconnect air ducts in TNC call a new design and fast release connections. • 2 elevator failures during last TS  foresee plan B

  20. PR532 monitoring system for remote control New tools available • PR532 remotely controlled (operated from TA7)  monitoring system to be installed (TAN like system) • Order must be launched now • New automatic hook ready Courtesy of J-L Grenard

  21. Xmas shutdown: first part • 2 weeks available before Xmas: • Remove horn  2 days • Remove air ducts  3 days (or nights) • General cleaning  3 days • Painting  2 days (or nights) • T9 modification  5 days • 2 weeks of Xmas break: air duct modification in TJ7 (tbc)

  22. Horn removal: plan Stripline: 200 to 400 uSv/h. Downstream part:1300 uSv/h.  Idea: Removal sequence similar to the reflector one (not use the crane) Remove 3 marble plates and cast iron blocks (Transport) Rough cleaning (Endel) Cut stripline and services (FSU) Remove stripline and horn with 2 elevators (Transport) Final cleaning. (Endel)

More Related