1 / 18

Contract No . 2013-BT-1 • March 20, 2013

Neighborhood Meeting No.2 Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid -Day Bus Parking Facility. Contract No . 2013-BT-1 • March 20, 2013. March 20th Presentation. Project Status Update: Traffic Signal Update: Sound Wall Design Concepts

amadis
Download Presentation

Contract No . 2013-BT-1 • March 20, 2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Neighborhood Meeting No.2Golden Gate Bridge, Highway and Transportation District’sSan Francisco Mid-Day Bus Parking Facility Contract No. 2013-BT-1 • March 20, 2013

  2. March 20th Presentation • Project Status • Update: Traffic Signal • Update: Sound Wall Design Concepts • Update: Modular Units and Security Fencing • Update: Landscaping Planting Concepts • Next Steps

  3. Proposed Site Plan

  4. Bus Ingress at Perry and 4th Streets

  5. Bus Egress at Perry and 3rd Streets

  6. New Traffic Signal and Pavement Delineation at Perry and 3rd Streets

  7. Existing Midblock Crosswalk Downtown San Francisco

  8. UpdatedSound Wall Elevations and Sections

  9. Selected OptionSound Wall Option 1 – “Diagonal Pattern”

  10. Variation on Selected OptionAlt. Sound Wall Option 2 – “Stripe Pattern”

  11. Sound Wall Steel Closure Plates – “Diagonal Pattern”

  12. Sound Wall Steel Closure Plates – “Stripe Pattern”

  13. Modular Units/Security FencingOriginal Concept

  14. Modular Units/Security FencingUpdated Concept

  15. Landscape Planting

  16. Landscape Planting

  17. Project Schedule • Comments: April 1, 2013 • Complete Design Documents – estimated May 2013 • Award Construction Contract – estimated July 2013 • Complete Construction – estimated January 2014 • Start Bus Parking – February 2014

  18. Q&A

More Related