Neighborhood Meeting No.2 Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid -Day Bus Parking Facility. Contract No . 2013-BT-1 • March 20, 2013. March 20th Presentation. Project Status Update: Traffic Signal Update: Sound Wall Design Concepts
E N D
Neighborhood Meeting No.2Golden Gate Bridge, Highway and Transportation District’sSan Francisco Mid-Day Bus Parking Facility Contract No. 2013-BT-1 • March 20, 2013
March 20th Presentation • Project Status • Update: Traffic Signal • Update: Sound Wall Design Concepts • Update: Modular Units and Security Fencing • Update: Landscaping Planting Concepts • Next Steps
New Traffic Signal and Pavement Delineation at Perry and 3rd Streets
Variation on Selected OptionAlt. Sound Wall Option 2 – “Stripe Pattern”
Project Schedule • Comments: April 1, 2013 • Complete Design Documents – estimated May 2013 • Award Construction Contract – estimated July 2013 • Complete Construction – estimated January 2014 • Start Bus Parking – February 2014