An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The „Energy in minds!“ - project in the energy region Weiz-Gleisdorf

  2. Energy region Weiz-Gleisdorf Weiz 17 communities 38 500 inhabitants Gleisdorf

  3. Project Partner in Austria Coordination of the energy region Weiz-Gleisdorf: W.E.I.Z. Research organisation: AEE INTEC Institut for sustainable technologies Utility: Feistritzwerke STEWEAG GmbH

  4. Research/Innovation • Information campaign • Public energy day • Innovative PV-systems • Bio-fuelled co-generation • High efficient retrofit • Establish wood-pellet infrastructure • Dissemination

  5. Demonstration • Innovativ solar thermal systems 80 solar-comby-systems in private households (10 – 20m²) 8 large-scale-systems f. resident.buildings or tourism.comp. • Innovative PV-systems 25 PV-Systems in private households with about 3 kWp • Improve district heating system 15 local district heating systems with about 150 kWhth, using woodchips or pellets • 1.000 Energy checks for buildings

  6. Demonstration High efficient retrofit 7000 m² residential-buildings 2500 m² public-buildings 1000 m² office-buildings • New low-energy buildings 4500 m² residential-buildings with passivhouse-standard • Communal energy management • Establish wood-pellet infrastructure 110 pellet boilers with 10 to 30 kW • Establish bio-fuel infrastructure

  7. DEM: for example: Plant oil-infrastructure • Two new fuel stations • Training course for garage owners and mechanics • Installation of an show room • Adaption of 30 vehicles to use plant oil

  8. Solar thermal systems Since June 2005 we installed 1331,9m² = 67 solar plants (one family houses)

  9. Pellet burners Since June 2005 we installed 886 kW= 56 pellet burners (one family houses)

  10. New buildings (one family houses) Since June 2005 we supported 2214 m² of new buildings.

  11. Retrofits - one family houses Since June 2005 we supported 2327m² of retrofits. Energy characteristic: 58 kWh/m²a Energy characteristic: 258 kWh/m²a

  12. Retrofits - one family houses Measurements Roof: 40 cm heat insulation Outer walls: 12 cm insulation Windows: U-value 1,1 W/m²K Heating system: solar thermal system 20m², wood boiler, storage tank 1000l

  13. Retrofits - one family houses Energy characteristic: 54 kWh/m²a Energy characteristic: 205 kWh/m²a

  14. PV-plants PV-Power: 4.700 Wp Low energy-building in massive construction < 12 kWh/m² heating PV-power: 3.040 Wp 16m² therm. Collector 12 kWh/m² heating

  15. District heating systems • 7 plants finished – 820 kWth

  16. Communal energy management Streetlights • in 4 communities, installationion of energy saving streetlights • - using new lamp-technology, reduction of operatingvoltage

  17. Online Energy-consulting

  18. Bio-fuel „plant oil“ • 8 vehicles adaped to bio fuel and in operation • 2 filling stations will be finished in July 2008 • 1 trasportable show-element to present the technology in the region

  19. Bio-fuel co-generation plants 1 plant running, 2 plants under construction - Electric Power: 8 kW – grid-connected - Thermal output: 18 kW – for heating office-building - Overall efficiency: aprox. 91%

  20. Monitoring for Energy in minds!° - projects

  21. Buildings monitoring

  22. Buildings

  23. Buildings Energy demand: Before: 157 kWh/m²a After: 24 kWh/m²a Energy costs: Before: 30.450 €/year After: 4.190 €/year

  24. Solar Thermal System and Pellet Boiler – Family Hausmann, Gleisdorf 19.5 m² 1,250 litres storage tank Domestic hot water is generated by a flat plate heat exchanger 10 kW pellet boiler for auxiliary heating

  25. Monitoring Solar Thermal System and Pellet Boiler – Family Hausmann, Gleisdorf House energy demand of 43 kWh/m²a for 150 m² living area The 19.5 m² solar thermal collector area was architectural integrated in the building’s south facade

  26. Solar Thermal System and pellet boiler – Family Wolf, Gleisdorf 15 m² 1,000 litres storage tank 10 kW pellet boiler for auxiliary heating

  27. Monitoring PV plants

  28. Monitoring PV-Plants – web-based