LULA GREEN ROAD UNION, SOUTH CAROLINA

LULA GREEN ROAD UNION, SOUTH CAROLINA. Jerry A. Brannon, Sr. ,PE Union County Engineer. Project Description. Project Length – 2.8 Miles Dirt and stone – 2.5 Miles Asphalt - 0.3 Miles Ditches & shoulders - 5.6 Miles Crossline Pipe - 76 Feet 18 “ Rip Rap - As Needed

amara
Download Presentation

LULA GREEN ROAD UNION, SOUTH CAROLINA

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LULA GREEN ROADUNION, SOUTH CAROLINA Jerry A. Brannon, Sr. ,PE Union County Engineer

  2. Project Description • Project Length – 2.8 Miles • Dirt and stone – 2.5 Miles • Asphalt - 0.3 Miles • Ditches & shoulders - 5.6 Miles • Crossline Pipe - 76 Feet 18 “ • Rip Rap - As Needed • Macadam Stone - 2.5 Miles • Bituminous Surface - 2.5 Miles

  3. Project Description • Re-grade 5.6 Miles of shoulders and ditches • Re-grade and reshape 2.3 miles of road bed • Spread, shape and compact macadam stone • Clean existing pipe • Place new cross line pipes • Install erosion control

  4. Project Description • Phase II – Install 18’ bituminous surface treatment Total Project cost estimated at $125,000 Addition funds anticipated from CTC and Union County Forces providing most of labor