LULA GREEN ROADUNION, SOUTH CAROLINA Jerry A. Brannon, Sr. ,PE Union County Engineer
Project Description • Project Length – 2.8 Miles • Dirt and stone – 2.5 Miles • Asphalt - 0.3 Miles • Ditches & shoulders - 5.6 Miles • Crossline Pipe - 76 Feet 18 “ • Rip Rap - As Needed • Macadam Stone - 2.5 Miles • Bituminous Surface - 2.5 Miles
Project Description • Re-grade 5.6 Miles of shoulders and ditches • Re-grade and reshape 2.3 miles of road bed • Spread, shape and compact macadam stone • Clean existing pipe • Place new cross line pipes • Install erosion control
Project Description • Phase II – Install 18’ bituminous surface treatment Total Project cost estimated at $125,000 Addition funds anticipated from CTC and Union County Forces providing most of labor