380 likes | 633 Views
Innovative Approaches for Managing Stormwater Runoff: Constructed Wetlands. March 4, 2009 32 nd Annual Airport Conference Hershey, PA. Project Background. Kim Minkel, NFTA. Buffalo Niagara International Airport. 110 daily flights, 25 gates 96” Avg. snow fall ~330,000 gallons glycol
E N D
Innovative Approaches for Managing Stormwater Runoff: Constructed Wetlands March 4, 2009 32nd Annual Airport Conference Hershey, PA
Project Background Kim Minkel, NFTA
Buffalo Niagara International Airport • 110 daily flights, 25 gates • 96” Avg. snow fall • ~330,000 gallons glycol • 1.2 MGD stormwater runoff
Deicing operations and practices • Deicing at the gates. • Storm sewer design. • Parallel system routes storm and glycol water. • Glycol storage before discharging to a POTW. • Glycol capture by GRV’s 45-48%.
Environmental Concerns • 1994 - SPDES permit • 30 mg/L BOD5 and 500 mg/L glycol limit • Frequent permit exceeded • 1995 - Vacuum sweeping • 3/1998 - The Citizen Alliance Group targets NYSDEC • 4/1998 NYSDEC issues Order on Consent - Comply by 2/99
Over the next 4 years… • ~$13.1 million spent • deicing controls, • storage and • treatment • Permit limits still exceeded • Neighbor complaints • Town prohibits discharge
Concerns • Point source limit applying to a non-point source operation – Permit modification • It’s not working –treat everything or reduce use? • Large volumes – how do you treat this cost effectively? • How do you pay for this?
Action Items • Modify permit – stream impact • Treatment Alternatives (non-point source) • Eliminate (reduce) glycol • Open SPDES permit • 2004 – Generic RFP issued • Petition for funding
Alternatives considered • Dedicated sewer line to POTW • Anaerobic/aerobic onsite treatment • Membrane bioreactors • Recycling • Infratek systems • Reed bed subsurface wetland • Centralized deicing recycling
Subsurface engineered wetland • Advantage – • Lowest 20 year combined capital and operating cost • Effective treatment for stormwater • Totally Green process • Disadvantage – • Space constraints • Public acceptance (Will it work?)
Go for it! • 2005 - RFP for a Treatability Study and Conceptual design • 2006 - Awarded to Jacques Whitford/NAWE/Urban • Treatability study showing >95% reduction in BOD • 2007- Design phase completed
Stormwater ManagementImpacts GARRET A. MEAL, P.E., URBAN ENGINEERING
URBAN ENGINEERS Buffalo Engineering firm with 10 offices 475 staff along the East Coast Extensive airport and civil transportation experience NY and local environmental permitting experience
Existing Infrastructure • Storm System • Extensive Storm Network • Stormwater Vault (3+ MG) • Outfall • Glycol Containment • Major pipes • Glycol storage tanks • Snow melt pad • Sanitary sewer pump station
Objectives • Treat Glycol Concentrate • Treat Glycol Contaminated Storm • Maintain Runoff Control • Reduce or Control Deicing costs
What needs to be treated? • Concentrate – 100% • Simple • Common Pumped Discharge to sanitary • Replace pumps, discharge to WTS
What needs to be treated? • Storm • Would require 15 Million Gallons storage for 10 yr storm • 25 Million Gallons for 100 yr storm • First Flush
Stormwater Management • Existing Design – Detention • Design Storm • Proposed Design for WTS Influent
Stormwater Management Strategies • Divert upstream areas directly to wetlands, where possible • Utilize wetlands for storm detention • Utilize glycol infrastructure year round • Design additional pumping capacity • Evaluate emergency overflows • Surface storage of severe storms
Conclusions • Storm Water Management Plan • Know what you are handling • How will you capture and hold water for treatment • Evaluate Resources – Can primary use be modified
Glycol Treatment Scott Wallace, JW NAWE
Treatment Objectives • Provide treatment of contained deicing fluid • Design system for integration into airfield • Integrate system into existing stormwater management
Why Wetlands? • Subsurface flow constructed wetlands do not pose a bird-aircraft strike hazard (BASH) • More stable than mechanical treatment systems • Biggest challenge is oxygen transfer into subsurface flow beds!
Subsurface Bed Cross Section Mulch Layer Influent Line Water Level Air Line Drain Line
Glycol Treatment • Glycols are readily degradable by bacteria
Cells are designed for a total load of 10,000 pounds of oxygen demand per day The equivalent to 50,000 people Process Sizing and Layout
Conclusions • System operation scales to glycol usage • In this case, the design had to handle variable flows and concentrations from at gate deicing • The design provides flexible operations • Winter = glycol treatment • Summer = storm storage
Lessons Learned • Communicate early and often • Never forget your key mission • Every airport is different • Design with flexibility in mind • Listen to your stormwater engineer