150 likes | 266 Views
LHC Sync. Light Monitors Status and Plans. 05 Feb 2014 Emittance Meeting (~= BI-TB Jan 2014) F.Roncarolo A.Goldblatt , G.Trad , E.Bravin , S.Mazzoni , W.Andreazza , G.Shneider,M.Wendt , N.Chritin. Overview. BSRTM Design Option A: original design with ceramic pieces
E N D
LHC Sync. Light Monitors Status and Plans 05 Feb 2014 Emittance Meeting (~= BI-TB Jan 2014) F.RoncaroloA.Goldblatt, G.Trad, E.Bravin, S.Mazzoni, W.Andreazza, G.Shneider,M.Wendt, N.Chritin
Overview • BSRTM Design • Option A: original design with ceramic pieces • Option B (BASELINE): Longer mirror, support behind RF screen, all metal • Optics • Low wavelength optics • Interferometer (B1 only) • New calibration line (B1 only) • Change tank support from ‘chair’ to 3 pillars (B1 only?) • New light shielding • SW • New functionalities to cope with new optics layout • Filter wheels pneumatic IN-OUT • Interferometer • Possible request of tomography meas. (ABP) fastest and synchronized camera acquisition • Discussion on Digital Cameras
New Calibration Line BSRTR B1 ECR circulating System (BSRTR = BTVSI modified) in production expected delivery: March Scheduled installation: March Components outside vacuum to be ordered, not critical, will be installed fall 2014
BSRTM Option A (ceramic) Mirror holder components (except springs) made in ceramic 2 systems in fabrication Expected delivery Keep as backup solution
BSRTM Option B For both option A and B, see BI-TB Oct 2013 for details on RF studies • BASELINE Option • ECR submitted • 2 systems in fabrication • Expected Delivery: February • Schedule • RF tests in the LAB? • To TE-VSC for testing: 15 March • Installation: April ?
Tank Support Proposal: change B2 immediately, to free space for halo monitor Decision: change B1 support from ‘chair’ to 3 pillars (existing) to free space on optical table
New mirrors • 2 mirrors compatible with option B, coating visible : arrived, backup solution • 3 mirrors with coating in the UV (down to 230nm) for option A + 3 for Option B • Expected delivery end of February • Can be the bottleneck for scheduling
https://espace.cern.ch/be-dep-bi-tb/Lists/Calendar/Attachments/840/LHC%20PROPOSAL.pptxhttps://espace.cern.ch/be-dep-bi-tb/Lists/Calendar/Attachments/840/LHC%20PROPOSAL.pptx https://dfs.cern.ch/dfs//Departments/AB/Groups/BI/Sections/PM/Projects/LHC/BSR/Docs-Litterature-Publications/BSRTWG/2013-09-10/BSRT_WakefieldAnalysis.pptx