An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. G0 Project Coordinator Report Joe Grames • “Big Picture” Schedule • Preparations • Polarized Source • Injector • Accelerator • Hall C • Accelerator Plans for 687 MeV Run

  2. Scope of Work Firm Pre-G0 Schedule Today – Jan. 26, Winter Shutdown Tasks Jan. 27 – Feb. 5, Restore & G0 Setup for 687 MeV & 362 MeV Feb. 6 – March 14, Physics Program for Hall B & A Firm G0 Running Schedule Mar. 15 – Apr. 2, Commissioning Period (following long down) Apr. 3 - Apr. 29, High Q2 Run (687 MeV) (3-halls, all polarized) Tentative G0 Running Schedule Jul. 21 - Sep. 1, Low Q2 Run (362 MeV) (1-pass, 1-linac, 2-halls) Sep. 22 - Dec. 22, High Q2 Run (687 MeV)

  3. Polarized Electron Source Layout Photocathode Gun 2 Anodized Superlattice P > 80% @ 780 nm QE ~ 0.5-1.0 % Ibeam ~ 80 mA Laser Ti:Sapphire (780 nm) f ~ 499 MHz Parity Quality Laser Setup G0 Helicity Sequence Pockels cell alignment IA intensity FB Rotatable ½-waveplate Insertable ½-waveplate

  4. Superlattice Polarization & Gun2 Lifetime Polarization ~86% Lifetime ~130 C A = 20 mA B = 5 mA C = 80 mA ~10 C/day

  5. Laser Table Layout for 3 Halls High Polarization (courtesy, J. Hansknecht)

  6. Injector Matching X-BPM (mm) Y-BPM (mm) without X-PZT (Source) 1C-Line 1C-Line with X-BPM (mm) Y-BPM (mm) Y-PZT (Source) 1C-Line 1C-Line • HC position differences are generated at the source. • “Matching” the beam emittance to the accelerator acceptance realizes damping, • Well matched beam => position differences reduced. • Poorly matched beam => reduced damping (or even growth). • Accelerator matching (linacs & arcs) routinely demonstrated. • Injector matching has been arduous, long (~2 year) process.

  7. Superlattice Photocathode for Parity Experiment G0 requirements => <2 ppm <40 nm

  8. Injector HC Position Feedback Helicity Magnets • HM (electron beam) replace • PZT (laser beam) • 4 magnets => • position (x,y) & angle (x’,y’) • linear over desired region • independent • electrically Isolated • orbit correction in each state • corrleated charge asymmetry 100x better than PZT • resolution 100 nm => 10 nm (at 5 MeV)

  9. PZTBooster Concept Matching • “Standard” injector matching process • Time consuming (1 shift + 2 days + 1 shift) • 30 Hz PZT at source yields small signal • Helicity Magnets in new “Optics Mode” • Synchronous with 30 Hz BPM acquisition system • Mimic small signal to deliver large signal • Goal: • Streamline injector matching • Improve accuracy of result • Allow for rapid confirmation • Direct comparison between Accelerator & Physics results for damping and response matrix for feedback.

  10. Hall C • Acclerator resources are largely allocated to the accelerator for the winter shutdown, with the exception of: • Install Moller kicker to allow high current polarimetry • Accelerator resources re-allocated in February for final 3C line work: • move Moller quad => low energy polarimetry • arrange quadruplet optics +> spot size (halo?) control • install shielded beam pipe => HKS stray field independence • install Halo & G0 girders w/ improved mating to G0 spectrometer

  11. 687 MeV Run • Jan 2 – Jan 16 : Source & Laser Table setup • Jan 17 – Jan 21 : G0 Laser Table setup • Jan 22 – Jan 26 : Machine checkout & PSS Certifications • Jan 27 – Feb 5 : Machine restoration & G0 Tasks • (9) - 56 MeV Injector Restore (Dec.’05) • (1) – PQB source checkout 100 keV, possibly higher • (6) – Setup T=5.0 MeV & 36.6 MeV injector & “lock-in” • (1) – Injector Match Part 1 (PZT acquisition) • (2) – 5-pass machine beam checkout @ 650 MeV/pass • (1) – Machine repair on DAY • (2) – 1-pass 687 MeV to BSY & ½-pass 362 MeV => SAVE • (1) - Injector Match Part 2 to BSY 687 MeV => SAVE • (2) – Full PQB, Source to BSY • (2) – 5-pass machine setup 738 MeV/pass • Feb 6 – Mar 14 : Physics Program resumes (B 6th and A 24th) • Mar 15 - Apr 29 : G0 (commissioning & production) at 650 MeV/pass Efforts shift to “hot checkout”, commissioning plans & safe operations.