1 / 235

Installation, Commissioning & Test Run HT

Comprehensive guide for installation, commissioning, and test run of Daikin Altherma HT + Flex Type units. Includes precautions, circuit information, field settings, and operational guidelines.

annehoward
Download Presentation

Installation, Commissioning & Test Run HT

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Installation, Commissioning & Test Run HT Training Course Daikin Altherma HT + Flex Type (S-HTF01-004)

  2. Installation, Commissioning & Test run (1) • Installation precautions • Service space • Refrigerant circuit • Water circuit • Field wiring • Remote controller • How to use • Operations • Field settings

  3. Installation, Commissioning & Test run (2) • Pre-operation checks • Final checks • Test run • Flow charts

  4. Installation precautions

  5. Installation precautions Outdoor Unit

  6. Handling outdoor unit Grips are foreseen to lift the unit

  7. Strong wind On places exposed to strong wind (5 m/s or more)

  8. Drain work • Prepare water drainage around the foundation • If water drainage is not possible, put unit on concrete blocks, etc with a height of at least 150mm • In places exposed to frequently snow, elevate foundation as high as possible • If installed on a building frame, install waterproof plate within 150mm of underside unit or use drain kit

  9. Cold climates • Install outdoor unit with suction side facing the wall • Never install with suction side directly to wind • If necessary, install baffle plate on air discharge side of outdoor unit • Make sure heat exchanger coil is not affected by the snow

  10. Prevention falling over (if necessary)

  11. Precaution foundation Screw foundation bolts until their length are 20mm from foundation surface

  12. Removing transportating stay The yellow transportation stay installed over the compressor leg for protecting the unit during transport must be removed If unit is operating with transportation stay attached, abnormal vibration or noise may be generated

  13. Precautions on knockout holes

  14. Holes prevention To prevent rusting To prevent entering foreign objects After knocking out the knock-out, it is recommended to apply paint to the edge and the surrounding end surfaces to prevent rusting

  15. Installation precautions Indoor Unit

  16. Installation precautions indoor unit • Indoor unit should not be installed in sound sensitive rooms (living room, bedroom, …) • Indoor unit should not be installed in rooms with a humidity over 85% (bathroom, …) • Frost free • Strong foundation • Dust free • Nothing placed on top of unit • No possible water damage in case of leak

  17. Final installation position 2 lifting supports are delivered in the accessory bag

  18. Leveling feet

  19. Water pipes Use different knockout holes for refrigerant pipes

  20. Knock out holes

  21. Position water filter standard filter

  22. Manometer (AB-model)

  23. Sound insulation (1) Insulate knock out holes Drop sound plates on both sides to the ground

  24. Sound insulation (2) Install the sound bottom plate

  25. Sound insulation parts (3) Install top panel (sound insulation + drain purpose) Stick insulation (see accessory bag) to the top decoration panel

  26. Leveling feet

  27. Installation precautions DHW tank EKHTS

  28. Installation precautions tank EKHTS • A drain device should be installed on the cold water connection on DHW tank • It is not allowed to add any kind of glycol to the water circuit • In cases where during longer periods of time there is no consumption of hot water, the equipment must be flushed with fresh water before usage • Immediatly after installation, the DHW tank must be flushed with fresh water. This procedure must be repeated at least once a day the first 5 consecutive days after installation

  29. Handling DHW tank

  30. Installation precautions DHW tank EKHWP

  31. Installation precautions tank EKHWP • Ground load-bearing capacity of 1050 kg/m² • Not be exposed to direct sunlight • Protected from frost • Suitable water treatment may be required (corrosive water?) • Service space: 200mm

  32. Service space

  33. Required space installation – Oudoor unit

  34. Servicing space - Stacked installation

  35. Servicing space - Multiple-row installation

  36. Required space installation – Indoor unit

  37. Required space installation – Tank EKHTS

  38. Required space installation –Tank EKHWP Distance to the walls: 200mm

  39. Refrigerant circuit

  40. Pipe directions – Outdoor unit 4 refrigerant pipe directions possible

  41. Refrigerant pipes AA-model 2 refrigerant pipe directions possible 2 water pipe directions possible direction pipes deliverd with indoor unit

  42. Refrigerant pipes AB-model

  43. ATTENTION!!!!

  44. ATTENTION!!!

  45. ATTENTION!!!

  46. Leak test and vacuum drying • Use a 2-stage vacuum pump with a non-return valve which can evacuate to a gauge pressure of -100.7kPa • Connect the vacuum pump to both service port of gas stop valve and liquid stop valve to increase efficiency • Make sure gas stop valve and liquid stop valve are firmly closed before performing the leak test or vacuum drying

  47. Leak test • Vacuum leak test • Evacuate the system from the liquid and gas piping to -100 kPa • Turn off vacuum pump and check pressure for at least 1 minute • Pressure leak test • Break the vacuum by pressurizing with nitrogen gas to a minimum gauge pressure of 0.2 MPa (Never higher than 4.0MPa) • Tests for leaks by applying bubble test solution to all piping connections • Do not use soap water -> soap contains salt and ammonia -> can freeze and/or lead to corrosion • Discharge all nitrogen gas

  48. Vacuum drying • Evacuate the system for at least 2 hours to a target vacuum of -100 kPa • Check that, with vacuum pump off, target vacuum is maintained for at least 1 hour • In case of moisture (failing of 2 above steps), break vacuum by pressurizing xith nitrogen gas to a gauge pressure of 0.05MPa and repeat above steps 1 to 2 • Open stop valves After opening stop valve, it is possible that pressure in refrigerant piping does not rise. This might be caused by e.g. closed state of expansion valve in outdoor circuit, but does not present any problem for correct operation of unit

  49. Charging refrigerant R410A Factory charge: 4,5 kg Additional charge ONLY required when >10 m Complete recharging

  50. Charging refrigerant • Charge refrigerant R410A in liquid state to the liquid pipe • Before charging, check whether the refrigerant cylinder has a syphon attached or not and position the cylinder accordingly to figure below:

More Related