An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TCC2/TDC2 LS1 Consolidation Plans On behalf of the TDC2/TCC2 WG team http://cern.ch/tcc2tdc2WG

  2. TCC2 Targets Target Box BAC TBIU Monitor TBID Monitor Mobile shielding motor Switchs Patch Panel Fan Courtesy of D. Grenier (EN-STI)

  3. Cabling campaign • Replace irradiated cables, avoid unnecessary cable length if possible, eliminate cable with PVC if possible • Cable campaign foreseen end 2013 for 4 months • Only signal and control cables (not DC cables) between patch RAL and Patch RX • 700 cables = 100 km in TCC2/TDC2 for the time being • End user to fill a DIC if additionnal request In discussion TCT: Top cable tray, AA: Almost All, R: Rest, Part: Partial.

  4. Air handling unit and cooling circuit • Leaking valve replacement foreseen in LS1 • North Area AHU consolidation planned for 2017 and cooling station for 2021 • AHU’s upgrade (add humidity control, make controls reliable) • Increase efficiency of air ventilation: at present the TDC2 tunnel is a dead-end and no clear air flow is set in the extremity toward TT20 (test in progress).

  5. List of activities for LS1: Magnet refurbishment • New cooling connection for all magnets • Global replacement of EPDM/Kevlar water hoses and gaskets in TDC2 / TCC2 • Y-shape fitting replacement by welded parts • Interlock: Thermometer and Manometer contacts get corroded, triggering inconsistent machine stops; • Insulation of cables is cracked in the patch panels, the magnet safety system could malfunction • Interlock systems will need consolidation in the future. A more modern system should be defined and implemented at the same time.

  6. Vacuum upgrade • Replace of damaged vacuum chambers and bellows • Replacement of ion pumps which are not or are poorly working at present. Change of ion pumps’ cables and connectors. • Increase of the number of pumps whenever possible and replacement of some ion pumps by new-generation NEG cartridges to accelerate recovery after air venting. • Beam line protection system in critical areas Courtesy of P. Chiggiato

  7. Lighting system and LV network • Lights upgrade (rad hard lights to be developed) • LV cabinet to be refurbished and moved away from targets and TAX areas

  8. Civil engineering • General infrastructure consolidation • Maintain drain network • Roof and floor cracks to be cured • Remove PVC hoses

  9. Beam line upgrade • Re-alignment of all secondarylines (neverdonesince installation mid seventies) • New PU-jacks for supportingbeamelements

  10. Courtesy of R. Losito

  11. TCSC

  12. Use of TruView

  13. Beam monitors • A lot of beam monitors are corroded and must bechecked. • BE-BI linkpersonbeingdefined

  14. Organization: review by equipment or infrastructure

  15. Organization: review by areas