Phase-I Up-gradationMedical Colleges-13 • Thiruvanthapuram • Salem • Bangalore • Hyderabad • Tirupati • Kolkatta • Lucknow
Jammu Srinagar Ranchi Varanasi Ahmadabad Mumbai
FUND COMPONENT GOI Component : Rs. 100 cr. State Government : Rs. 20 cr. For IMS (BHU) – MHRD has additionally contributed Rs. 20 cr. For SVIMS Tirupati – Central Govt. Rs. 60 cr. ; rest of Rs. 60 cr. From TTD Trust. Civil work at 10 sites (except Mumbai, Ahmedabad, Tirupati). Procurement of Equipment in all 13 sites
Status -PMSSY Projects under execution- Middle stage of completion
Project Cost -Civil Cost - Rs. 44.66 Cr (Revised - Rs.49.23 Cr) - Med. Eqp Cost - Rs. 45.34 Cr - Total cost - Rs. 90 Cr No. of Beds- 253 Total built up area & No. of floors - SS Block - 15010 Sqm (Basement + G+5) - Nursing College - 675 Sqm( G+1) - MLT Block. - 920 Sqm( G+1)
Issues • Clearance from AAI to be expedited • Faculty and Manpower to be recruited
Project Cost - Civil Cost - Rs. 79.31 Cr (Revised – Rs.84.70Cr) - Med. Eqpt Cost - Rs. 10.69Cr - Total cost - Rs.90.00 Cr No. of Beds - Super Speciality Block - 319 - Trauma Care Centre - 122 Total built up area & No. of floors - SS Block - 26,459Sqm (G+4) - Trauma Care Centre - 4,593 Sqm (G+2)
Issues • Procurement of low end equipment by State Government • Grant of environmental clearance from TNPCB and Power Connection from TNEB • Additional Fund Rs 1.378 Cr from State Government • Faculty and manpower to be recruited
Project Cost - Civil Cost - Rs. 49.86 Cr (Revised Rs.56.16 Cr) - Med. Eqp Cost - Rs. 40.14 Cr - Total cost - Rs.90.00 Cr No. of Beds- 203 Total built up area & No. of floors - SS Block - 14,626 Sqm (G+5) - Nursing College & Hostel - 06,964 Sqm (G+3)
Issues • Additional Fund Rs 1.10 Cr to be provided by State Government • Faculty and Manpower to be recruited
Status - Hyderabad (Speciality ) Physical progress -80% Expected Completion - March’10
NIMS, HYDERABAD • NIMS to establish substation and take action on supply of electricity to 11 KV substation already constructed by HSCC. Land issue of NIMS with State Electricity board to be resolved. • Areas like Operation theatres, Diagnostic facilities etc. where major medical equipment are to be installed can be finished after installation of medical equipment. Institute to take action on procurement of medical equipment . • Effluent treatment plant work also to be taken up • Action on municipal water supply connection. • GOI balance fund expected is about Rs. 7 cr. after construction component of Rs. 83 crore. This may be utilized in procurement of office furniture & furnishing. Work of medical equipment and gases manifold may be taken by institute. • In a initial planning conventional operation theatres were envisaged. NIMS desired to have 2 to 3 modular OT which may kindly be identified so as to finish balance OT’s.
Up-gradation of SVIMS, Tirupathi • Project Consultant : SVIMS. & HLL • Medical Equipments : Rs. 55.00Cr • Consultancy cost : Rs.5 .00 Cr • Total : Rs.60.00 Cr • Fund released for Procurement of : Rs. 39.55 Cr. • Equipments : • Expected Date of completion : April, 2010
Issues • No issue
Status of the Project- SGPGIMS, Lucknow Physical progress -85% Expected Completion - March’10
Issues • Intervention with Govt. of UP for release of fund of Rs. 3.51 crore for neonatal ward without which the building can not be functional • Neonatal Ward is the Integral part of Building Without completion of Extension work, Facility of Maternity Unit, Pediatric Unit and part OT will remain not fully functional. • SGPGI to take up road work in front of building. • Faculty and Manpower to be recruited
IssuesOther Equipment and services- Lucknow • Tender documents for CSSD, Kitchen & pendent have been prepared and submitted to institute on 31.12.09. • Draft agreement submitted to institute in line of IFD circular on which SGPGI has reservations. • Institute has to form committee as per there guidelines. • Institute wants complete procurement with tendering, delivery and installation in 3 months which is not practical. • Institute had initially agreed consultancy fee of 7% which now they want to reduce to 2%. Consultancy fee for medical equipment may be 2% but for services etc. it should be 7%. • If require institute may take up this work directly as for other component.
Status of the Project- Kolkata Block % progress PDC OPD 70% March’10 Academic 60% Sept’10
Issues • Written confirmation for funding gap of Rs. 12 cr from State Govt. is yet to receive.
Issues- Jammu • Removal of Burmi • Installation of STP • Installation of 33/11KV Sub-Station • Intimate firmed up cost • Faculty and manpower recruitment
Up-gradation of Srinagar Medical College • Project Consultant : CPWD • Civil Construction Cost : Rs.40.00 Cr. • (220 bedded Trauma Centre) • Medical Equipments : Rs. 50.00 Cr • Consultancy : Rs. 10.00 Cr • Total : Rs.100 Cr • Award of Civil Work : April, 08 • Completion Date as per contract : March, 2010 • Expected Date of completion : August, 2010
Issues • Acquisition of land from Carpet Factory • Branches of Chinar Tree to be cut • Fund for laying 11KVA electric line to be • Firmed up cost to be intimated
Up-gradation of IMS, BHU • Project Consultant : CPWD • Civil Construction Cost : Rs.75.00Cr • (334 bedded Trauma Centre) • Medical Equipments : Rs.35.00Cr • Consultancy : Rs. 10.00 Cr • Total : Rs.120.00 Cr (HRD –Rs. 20 Cr.) • Start of Civil Work : Apr, 2009 • Expected Date of completion : Jul, 2010
Issues • HRD needs to give commitment to bear additional expenditure of Rs 27.00 Cr
Up-gradation of RIMS, Ranchi • Project Consultant : CPWD • Civil Construction Cost : Rs.45.00 Cr. • (240 bedded SSB + Cancer Centre) • Medical Equipments : Rs.45.00 Cr • Consultancy : Rs. 10.00 Cr • Total : Rs.100.00 Cr • Start of Civil Work : Sep 09 • Expected Date of completion : Dec 10
Issues • State Government would need to facilitate road permit for supply and installation of high end equipment • Shifting of overhead electric lines and pole
Up-gradation of Grants Med.College Mumbai • Project Consultant : State Govt. & HLL • Medical Equipments : Rs. 88.85 Cr • Civil Construction Cost : Rs.1.15 Cr • Consultancy : Rs. 10.00 Cr • Total : Rs.100.00 Cr. • Fund released for procurement of :Rs.57.36 Cr. • equipments • Expected Date of completion : April, 2010
Issues • Medical College authorities require to co-ordinate with HLL and equipment supplier for proper installation of high end equipments
Up-gradation of BJ Medical College Ahmadabad • Project Consultant : State Govt. & HLL • Medical Equipments : Rs. 82.00 Cr • Civil Construction Cost : Rs.8.00 Cr • Consultancy : Rs. 10.00 Cr • Total : Rs.100.00 Cr • Funds released for Procurement of : Rs. 36.79 Cr. • Equipments : • Expected Date of completion : April, 2010.
Issues • Fund utilisation certificate for Nursing College