Project Management Chapter 17
Build A A Done Build B B Done Build C C Done Build D Ship JAN FEB MAR APR MAY JUN On time! Projects Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.
Project Management • How is it different? • Limited time frame • Narrow focus, specific objectives • Less bureaucratic • Why is it used? • Special needs • Pressures for new or improves products or services
Project Management • What are the Key Metrics • Time • Cost • Performance objectives • What are the Key Success Factors? • Top-down commitment • Having a capable project manager • Having time to plan • Careful tracking and control • Good communications
Project Management • What are the Major Administrative Issues? • Executive responsibilities • Project selection • Project manager selection • Organizational structure • Organizational alternatives • Manage within functional unit • Assign a coordinator • Use a matrix organization with a project leader
Project Management • What are the tools? • Work breakdown structure • Network diagram • Gantt charts • Risk management
Summary of Key Decisions • Deciding which projects to implement • Selecting a project manager • Selecting a project team • Planning and designing the project • Managing and controlling project resources • Deciding if and when a project should be terminated
Project Manager Responsible for: Work Quality Human Resources Time Communications Costs
Feasibility Planning Concept Execution Termination Project Life Cycle Management
Gantt Chart Planning and Scheduling
PERT and CPM Networks PERT: Program Evaluation and Review Technique CPM: Critical Path Method • Graphically displays project activities • Estimates how long the project will take • Indicates most critical activities • Show where delays will not affect project
The Network Diagram • Network (precedence) diagram – diagram of project activities that shows sequential relationships by the use of arrows and nodes. • Activity-on-arrow (AOA) – a network diagram convention in which arrows designate activities. • Activity-on-node (AON) – a network diagram convention in which nodes designate activities. • Activities – steps in the project that consume resources and/or time. • Events – the starting and finishing of activities, designated by nodes in the AOA convention.
The Network Diagram (cont’d) • Path • Sequence of activities that leads from the starting node to the finishing node • Critical path • The longest path; determines expected project duration • Critical activities • Activities on the critical path • Slack • Allowable slippage for path; the difference the length of path and the length of critical path
a b c a c b a c a c Dummy activity b b d Network Conventions for PERT and CPM Networks (AOA)
Orderfurniture 4 Furnituresetup 2 Locatefacilities Remodel 1 5 6 Move in Interview Hire andtrain 3 Project Network
6 weeks 4 3 weeks 2 8 weeks 11 weeks 1 5 6 1 week 4 weeks 9 weeks 3 Example
Example Solution Critical Path
Computing Algorithm • Network activities • ES: earliest start • EF: earliest finish • LS: latest start • LF: latest finish • Used to determine • Expected project duration • Slack time • Critical path
Project Management Software • Computer aided design (CAD) • Groupware (Lotus Notes) • CA Super Project • Harvard Total Manager • MS Project • Sure Track Project Manager • Time Line
Advantages of PM Software • Imposes a methodology • Provides logical planning structure • Enhances team communication • Flag constraint violations • Automatic report formats • Multiple levels of reports • Enables what-if scenarios • Generates various chart types
Summary • Projects are a unique set of activities • Projects go through life cycles • PERT and CPM are two common techniques • Network diagrams • Project management software available
Build A A Done Build B B Done Build C C Done Build D Ship JAN FEB MAR APR MAY JUN On time! Advantages of Gantt Charts and Networks • Forces managers to organize • Provides graphic display of activities • Identifies • Critical activities • Slack activities
4 2 1 5 6 3 Limitations of Networks • Important activities may be omitted • Precedence relationships may not be correct • Estimates may include a fudge factor 142 weeks
Ethical Issues • Temptation to understate costs • Withhold information • Misleading status reports • Falsifying records • Comprising workers’ safety • Approving substandard work
Homework Problem Do problem 5 (part a only) on p. 819. While thesolution is given in the following slides, be sure that you take the time to try to solve this problem prior to looking at the solution.
LF EF LS ES 26 18 21 13 2 21 13 10 8 28 20 5 26 19 12 1 31 24 11 4 28 21 19 12 26 19 7 0 0 0 11 3 25 25 31 31 9 6 25 25 10 10 10 10 20 20 20 20 16 16 16 16 5a. 5 26 18 7 Key 4 9 2 12 4 28 21 11 4 8 2 3 4 7 19 12 6 10 5 6 4