King Fahd University of Petroleum& Minerals. Project Quality Management CEM515 Professor Abdulaziz A. Bubshait STD. MOHAMMED AL-SAQAR ID. 270101. Problem description. Delay in the adoption of the samples provided by the contractor for the elements that use the terms
E N D
King Fahd University of Petroleum& Minerals Project Quality ManagementCEM515 Professor Abdulaziz A. Bubshait STD. MOHAMMED AL-SAQAR ID. 270101
Problem description Delay in the adoption of the samples provided by the contractor for the elements that use the terms .”“best kinds” or “equal
Effects Delay on close-out date of the project . Rework. Reject of work.
FLOW CHART Installation of aluminum Contractor Supply aluminum Sample consultant approval START Yes No Owner approval No Fix aluminum Yes Start installation of aluminum Finish aluminum Sample
PROCESS MAP CONTRACTUR Supply aluminum Sample Fixaluminum Approval Sample CONSULTANT Final approval OWNER
Solution --use more than one type of specifications that used in the projects --Narrowing of differences on the interpretation of the specifications. --Early meetings between the contractor , consultant and owner representative for the identification and selection of items enough time before its implementation.