Department Of Energy. National Power Corporation. National Electrification Administration. Consultation with SPUG DUs on Power Supply Agreement (PSA). PROGRAM. Invocation Recognition of Participants Opening Remarks Messages DOE NPC-SPUG Mindanao NEA Overview PSA Template Timeline
E N D
Department Of Energy National Power Corporation National Electrification Administration Consultation with SPUG DUs on Power Supply Agreement (PSA)
PROGRAM • Invocation • Recognition of Participants • Opening Remarks • Messages • DOE • NPC-SPUG Mindanao • NEA • Overview • PSA Template • Timeline • Closing Remarks
Execution of PSA between NPC and DUs • Relationship should be made legal and binding • Enhance system reliability • Firm up subsidy allocation for OPEX and CAPEX
DOE Remarks • “professionalize” the electric industry • On-going PhP 0.30/kwh reduction and 3% prompt payment discount should have a legal basis • PSALM-NPC separation of books: must immediately implement transfer of books • SPUG as residual of NPC • SPUG is being subsidized by the mainland grid revenues and UC-ME • COA is already looking at SPUG operations especially on the rate reduction and PPD since these are taxpayers money
SPUG Existing Areas • 105 plants in 86 areas nationwide • 77 island grids and 9 isolated grids • 44 DUs covered • 23 in Luzon • 10 in Visayas • 11 in Mindanao • 13 DUs with signed PSA with NPC that will expire 2012-2013 • 9 DUs with signed PSA with NPP
Status of PSA with DUs in Luzon • Areas - 41 • Number of DUs – 23 • Areas per DU: • DUs with PSA with NPC in # Areas– 9 in 11 areas • DUs with PSA with NPPs in # Areas- 7 in 7 areas
Status of PSA with DUs in Visayas • Areas - 24 • Number of DUs – 10 • Areas per DU: • DUs with PSA with NPC in # Areas– 1 in 1 area • DUs with PSA with NPPs in # Areas- 1 in 1 area
Status of PSA with DUs in Mindanao • Areas - 21 • Number of DUs – 11 • Areas per DU: • DUs with PSA with NPC in # Areas– 3 in 5 areas • DUs with PSA with NPPs in # Areas- 1 in 1 area
Power Supply Agreement • The Parties to the PSA are NPC (NPC-SPUG) and DU (Off-taker) • Scope • Contract Demand and Energy • Full service (base load, peaking) • Tariff • Penalties • Assignability
TIMELINE • Distribution of Draft PSA to DUs 23 Jan 2009 • Consultation • Luzon 27 Jan 2009 • Visayas and Mindanao 29 Jan 2009 • Presentation to DU’s Board of Directors nlt 07 Feb 2009 • Submission of Revisions to NPC nlt 13 Feb 2009 SPUG Fax (02) 9213319 or 9213230 or em at crvborlaza@napocor.gov.ph rlabergas@napocor.gov.ph
TIMELINE • NP Board Meeting week of 16 Feb 2009 • PSA Template • UC-ME application to ERC • Prompt Payment Discount Confirmation of the DUs Board of Directors nlt 28 Feb 2009 • Submission of signed PSA of ECs to SPUG 28 Feb 2009 Signing of PSA by NPC and DUS week of 02 March 2009 (venue – NPC Central Office) • SPUG website: www.spug.ph