1 / 11

The FREIA Test Program

The FREIA Test Program. Roger Ruber for the Uppsala Accelerator Group & FREIA 20-21 November 2013, Uppsala ESS-FREIA Spoke Cavity Testing Review and Planning Meeting. Responsibility for ESS Accelerator. Contribution to the technical design & construction effort

ashby
Download Presentation

The FREIA Test Program

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The FREIA Test Program Roger Ruber for the Uppsala Accelerator Group & FREIA 20-21 November 2013, Uppsala ESS-FREIA Spoke Cavity Testing Review and Planning Meeting

  2. Responsibility for ESS Accelerator • Contribution to the technical design & construction effort • design concept spoke accelerating cavity power source • design concept radio-frequency (RF) power distribution • survey test stand infrastructure and requirements • study of upgrade scenarios RF systems for ESS power upgrade • Development power station for spoke cavities • soak test with water cooled load, then accelerating cavity, incl. controls • collaboration with industry to develop vacuum tube and solid-state based prototypes • System test, power station withspoke cavity and cryostat-module • fully dressed prototype cavity (in test cryostat) • complete prototype module (2 spoke cavities) • Acceptance test cryostat-modules(proposal submitted) • for all final modules before installation ESS-FREIA Spoke Cavity Testing - Roger Ruber - Proposed Test Program

  3. What (doesthismean)? Criteriatojudge the test results • Efficiency • toreduceelectricitycosts • reusecoolingwater • Stability • relative fast responseto perturbations • predictabilityof the system • requirestestingof extreme conditions • Reliability • slow variations such as drift and agingthataffectparameters • abrupt failureofsomething • requires long-term soaktesting ESS-FREIA Spoke Cavity Testing - Roger Ruber - Proposed Test Program

  4. … for the sub-systems … • RF power station & RF distribution • achieverequiredperformance: 14 Hz, 2.9+tfillms, power-to-beam+overheadkWpeak • stable long term operation • safe handling ofreflections, sparking, interlocks and faults • LLRF and controls • RF control (1% amplitude, 1ophase) • compensationLorentz detuning&microphonics • Spokecavity • achieverequiredperformance: Eacc, Q0, f0, losses • stable long term operation • Spokecryo-module • as for singlecavity • no undesirablecouplingbetweencavities • achievecryogenicrequirements: cool down, losses ESS-FREIA Spoke Cavity Testing - Roger Ruber - Proposed Test Program

  5. How ? SpokeCavity LLRF Helium Liquefier RF Power Station • General idea • commission and test infrastructurebeforearrivalsub-systems • new facility, so must commissionequipmenttoguarantee proper operation • personnelshouldhavetimetofamiliarizewithequipment • commission and test each equipment before combining • limitedtimelinetowardsarrivalofcavity • limitedlearningcurvetowardsprototypecryo-moduletesting • Will be first major test for FREIA & ESS (of a whole accelerator section) • critical for decision towards cavity series production • critical for decision towards RF & LLRF component design and procurement Cryo-module HNOSS HorizontalCryostat 2K pumps today ESS-FREIA Spoke Cavity Testing - Roger Ruber - Proposed Test Program

  6. Cryogenics & Cryostat Helium Liquefier • Helium and Nitrogen Cryogenics: contract with Linde • factory test (cold box & controls): January • delivery & installation: February-March • commissioning & acceptance test (by Linde): March-April • HNOSS Cryostat and Transfer Lines: contracts with ACS and Cryo Diffusion • factory test (LN2): April • delivery & installation: May-June • commissioning (by UU and ACS): Summer • Sub-atmospheric pumps: tender launched last week • delivery & installation: May-June • commissioning: Summer HNOSS HorizontalCryostat 2K pumps today ESS-FREIA Spoke Cavity Testing - Roger Ruber - Proposed Test Program

  7. RF Power Station and Distribution Tetrode • Tetrodebased: contractwithElectrosys • factory test tetrodes (Thales, Thonon): thisweek • factory test (Electrosys): • delivery & installation: January-February • commissioning and acceptance test (by Electrosys): February-March • Solid-statebased:Siemensdevelopment • on loanto Uppsala, expecteddelivery: February • RF Distrbution • circulator and loadsordered • tender ofremaining parts now under preparation Solid State today ESS-FREIA Spoke Cavity Testing - Roger Ruber - Proposed Test Program

  8. Controls and Monitoring • Safety • radiationmonitoring • personnel& equipmentsafety interlocks • Equipment controls • basecontrolsincluded in contracts (Cryo Diffusion, Electrosys, Linde) • overall integration by Uppsala (EPICS based), workingwithequipmentmanufacturers • Data acquisition and monitoring • RF measurements (amplitude, phase) • infrastructure & environmentmonitoring (temperature, pressure & humidity) • … any special experiments … • LLRF • under development at Lund, updated as testingprogresses… LLRF today ESS-FREIA Spoke Cavity Testing - Roger Ruber - Proposed Test Program

  9. Single “Double Spoke” Cavity Onlyafter all other systems havebeensuccessfullycommissioned Then… • installcavityintocryostat • tooling under design by ACS • connectcavity vacuum pumping • alwayskeeppumpingifpossible… • connecttocryogenics, RF etc. • connection & functionality test • RF couplers, tuners and instrumentation Note thatthiswill be the firsttime (for cavity, cryostat and team) Expect extra time for • connections • cool down, RF conditioning, testing… ESS-FREIA Spoke Cavity Testing - Roger Ruber - Proposed Test Program

  10. Spoke Cryo-module Wehaveoneyearto test the firstspokecavity • should make optimum useto do it careful • exhaustivetesting for efficiency, stability and reliability • do it carefully and learnhowtooperateequipment and assembly • polish anyissues • toprepare for order of series production • arrivalofprototypecryo-module Prototypespokecryo-module • repeat the singlecavityexperience • test cryostatbehaviour • search for anycorrelation and interactions betweencavities • polish anyissues and learntoinstall/test/remove • prepare for series testingofcryo-modules ESS-FREIA Spoke Cavity Testing - Roger Ruber - Proposed Test Program

  11. Summary • Further discussions during this meeting • We have ideas on the testing but want to discuss with you for your input and experience • Onsetto a commonlyagreed test program Thanks toyou all ! http://blog.qatestlab.com/2011/04/01/how-to-involve-non-functional-testing-in-your-project/ ESS-FREIA Spoke Cavity Testing - Roger Ruber - Proposed Test Program

More Related