1 / 25

Environment, Safety and Health

Environment, Safety and Health. Steve Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting March 29, 2012. Outline. Baseline Scope, Staffing Progress since February 2011 Recommendation Status Accelerator Readiness Reviews Project Safety Record Risks Issues Summary. ESH Scope.

ashlyn
Download Presentation

Environment, Safety and Health

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Environment, Safety and Health Steve Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting March 29, 2012

  2. Outline • Baseline • Scope, Staffing • Progress since February 2011 • Recommendation Status • Accelerator Readiness Reviews • Project Safety Record • Risks • Issues • Summary

  3. ESH Scope • ESH Support for: • Design & Procurement • Conventional Facilities • Accelerator Systems • Experimental Systems • Construction • Ring Building • LOB’s • BORE’s • Pre Ops & Operations • Experimental Facilities • Experimental Reviews • Equipment installation • Authorization Basis & Commissioning • Safety Assessment Documents • Accelerator Safety Envelopes - Instrument, Readiness Reviews, ARR’s P-1 Storage Ring RF Building transmitters Support Building Utilities

  4. ESH Program Responsibilities • Safety system configuration control • Self-assessment • Risk assessment • Interlock testing • (radiation and laser) • Tier I inspections • Compliance audits • Readiness Reviews • Construction Safety • Conduct of Operations • Authorization Basis • Experiment safety review • Work planning support • Emergency planning • Environmental management • Hazardous waste management • Industrial hygiene • Industrial safety • Radiation safety • ESH Facility & Equipment Design

  5. Environment, Safety and Health Organization Environment, Safety and Health Manager – S. Hoey Deputy – A. Ackerman Laboratory Support*** Radiation Control F. Flannigan S.Townsend S. Walker F. Zafonte Industrial Hygiene C. Weilandics Environmental Compliance D. Bauer Readiness Review R. Travis ESH Operations** Manager A. Ackerman ESH Design, Construction & Commissioning Manager S. Hoey ESH Coordinator L. Stiegler G. Wilson Radiation Physics P. K. Job COMMITTEES ALARA Committee Beam line Review Committee EMS/OHSAS Committee ES&H Committee ES&H Improvement Committee Interlock Working Group Review Committee PS Directorate Safety Committee Instrument Readiness Review Committee ESH Engineer B. Heneveld Health Physics W. R. Casey Safety Officer B. Chmiel Authorization Basis N. Gmur Safety Engineer T. McDonald Construction* T. Anschutz R. Chilakala *Decrease one FTE coincides with construction downsizing ** Decrease two FTE retirement and re-org QA function Readiness Evaluation B. Heneveld *** Staffing increase to support commissioning

  6. Progress - ESH Operations • Significant increase lab, assembly, and office space • 725 – NSLS – 162,156 ft2 (Exp floor = 123,644 ft2) • 726 – NSLS - Mechanical Tech Support 3519 ft2 • 727 – NSLS – Mech/Magnet Measurement 3519 ft2 • 729 - NSLS Source Development Lab – 8018 ft2 • 902/905 – Magnet test and assembly, vacuum – 22,690 ft2 • 703 – Experimental Facilities Division, 9 new labs – 7,360 ft2 • 945 – Vacuum lab – 4,068 ft2 • 832 – RF development, magnetic measurement – 7,895 ft2 • 820 – Front Ends Diagnostics – 5,700 ft2 • 740, 746 & 747 – Ring Building - 400,000 ft2 • Risk well understood & Controlled – lab work, mechanical Assembly, chemicals, haz waste etc. • Work processes covered by Project Safety Review and/or Enhanced Work Permits • Experienced ESH Operations Staff being utilized for installation and commissioning • Lessons learned from these operations being applied to ring building installations. NSLS NSLS-II

  7. Progress - Area Monitoring • Required area monitors (2) are installed at Linac and are ready for commissioning • Area monitors for Booster and storage ring are ordered and are arriving (16 on hand at this point) • Remainder of 55 are scheduled for delivery by Sept.1, 2012

  8. Progress - Top-off Safety • Work of task force establishing engineered safeguards which will prevent the top-off accident continues • Preliminary safety review by external independent committee conducted 3/7-8, 2012. Committee endorsed overall strategy and commented on the quality of the work. A number of suggestions were made which the task force will follow-up. • Final safety review planned for Fall, 2012

  9. Progress - Top-off Radiological Incident Analysis • Radiological analysis of the top-off injection accidents have been completed • Full injected beam loss at front end inside SR results in <500 mrem/h (injection rate15 nC/s)on experimental floor; at least one interlocked PPS required to prevent this accident scenario. • Full injected beam conveyed down to FOE results in dose rate at experimental floor ~300 rem/hr (15 nC/s); redundant interlocked PPS required to prevent this injection accident scenario. • Top-off interlock strategies have been recommended to the top-off task force • The results are published as a scientific paper (Nucl.Instr.and Meth., A648 (2011) 15-21)

  10. Progress - Construction Safety • Contractor(s) performing better than industry average • Torcon – improved performance • EWH – perfect record thus far, exceeding all goals • Ring Building Construction complete only PL’s remain • Many programmatic enhancements, best practices; & Lessons Learned (LL) • Increased use and detail of PHA’s (LL) • Increased communications – daily ESH planning mtgs; weekly ESH Mgmt mtgs; monthly ESH group mtgs, schedule and coordination mtgs with ESH. (LL) • On site medical provider – NYS licensed EMT’s • Drug screening, pre-employment and post-incident/cause • Construction safety assessment program – contractor and NSLS-II (LL) • Modified Safety Incentive – workers receive 90%, 2 mos period (LL) • Torcon – $ 490,608.20 (available $ 908,470,52) 53.97% (Initial program TC lost 100% due to 1 DART) • EWH - $159,372.92 (available $159.372.92) 98.75%

  11. Construction Manpower Peak 243 • Manpower was expected to exceed 300, however peaked at 243 in late FY10: • Torcon finished ring building in Feb 2012 will go down to <50 for punch list • EWH is ramping up however overall manpower will decrease from peak in 8/10 • Decrease in manpower equates to less risk exposure

  12. Progress-Transition from Construction • Laboratory Beneficial Occupancy Readiness Review (BORE) process is being used • Officially turns over sections of facility to allow machine installation • Specific NSLS-II BORE Plan in place that; • Defines scope • Establishes schedule • Identifies resources • PSD BORE Coordinator Assigned • Ring building BORE’s start Feb 2011 and finished February 2012 total of 8 phases to match construction phases • LOB BORE’s to start June/July 2012 and finish in Dec 2012 Project Lessons Learned passed to Lab

  13. Ring Building BORE Status

  14. Occupied Areas/Construction Areas

  15. Progress - Authorization Basis • Phased Commissioning strategy agreed to; • Safety Assessment Documents (SAD) and Accelerator Safety Envelopes (ASE) are modular: • Preliminary SAD (for CD-3) – approved by DOE 2008 • Linac Commissioning SAD/ASE - complete • Booster Commissioning SAD/ASE – complete pending approval • Storage Ring Commissioning SAD/ASE – in process • Includes project beam lines • Accelerator Routine Operations SAD/ASE • Initial planning ongoing to conduct injection from Booster into P-2 prior to SR being complete will require shielding and fault study analysis and may require mods to Booster SAD/ASE and/or a USI and ARR phasing strategy

  16. Recommendations from 2/11 PAC “Establish the charter for the initial task of the ARR Team to cover not just the Linac, but also the complete facility, to the extent that available information allows” Complete Team selected for all ARR’s through routine operations Team includes internal and external ESH and Accelerator operations experts

  17. Progress – ARR Process • ARR Phasing approach adopted* • Linac - Complete • Booster • SR • Final Ops • ARR Coordinator assigned (LL) from BORE’s • Web page established to give team early access to documentation. • Coordination meeting with team in Sept at ASO mtg • Follow up conference calls preceded ARR • ARR preceded by an internal Instrument Readiness Review established to verify readiness; IRR will also be used for beam line commissioning • *May need to add additional phase to support Pentant 2 injection

  18. Progress - Linac Commissioning • Linac Authorization Basis Documentation (SAD & ASE) complete and approved by BHSO • Commissioning Plan - complete • Injection Building occupancy 8/12/11 • Equipment Installation - complete • Necessary SOP’s - complete • Training/qualification - complete • Instrument Readiness Review - compete • ARR – complete – no new prestarts identified • All ARR pre-starts- complete • Linac Commissioning start week of 3/26 • Sequence for Booster and SR underway Dec 7, 2011 Jan 11,2012

  19. Project Injury Summary (since 2/11) • Operations: • Cut chin • Construction: • Fractured foot • Dislocated knee (Job Shopper)

  20. NSLS-II Construction Injury • On Sep 22, 2011, a painter with Keller Painting [a subcontractor to Torcon] was injured • The painter and his partner were moving a box containing a cover to an electrical cabinet (approximately 100 pounds) so that they could complete painting steel columns • They had successfully moved one box and were in the process of moving a second box when the box slipped out of the hands of the painter and landed on the instep of his foot • He was taken to the on-site EMT and then to a local hospital for further evaluation • An X-Ray revealed that one of the metatarsal bones in his foot was broken • The painter was wearing appropriate ANSI approved safety shoes Causes: The box slipped from the painters hand, apparently as a result of paint residue on his cotton gloves Corrective Actions: All trades should ensure that when manually moving pieces of material, their gloves are clean and adequate for the task Two boxes containing electrical panel covers

  21. Injury NSLS-II Job Shopper Injury • On January 13, 2012, a job shopper (sub-contractor to the project) working on technical equipment installation was injured. • The job shopper was descending a flight of “ratchet wall” stairs in Pentant 3 at the end of his work shift (approximately 3:00 pm). • When he was about at the 8th or 9th step from the bottom, he lost his footing and started to fall. • He had been holding the handrail, and tried to catch himself before reaching the bottom. • When he landed at the bottom of the stairway his left knee locked up and hyperextended, causing his knee to dislocate. • Job Shopper was wearing area based PPE (hard hat, safety glasses and safety shoes), the safety shoes were in good condition. • His co-workers transported him to the OMC, where he was given pain medication and transported to mather hospital. • Subsequent time lost classifies this as a DART and he will require corrective surgery. Analysis/Causes: Stairs were in good condition, dry well lit and constructed of slip resistant materials, handrails are on both sides. Stairs are fully compliant with OSHA stds. The job shopper was not carrying any materials/equipment and he was in good physical condition. He was leaving for the day on a Friday for the weekend. A likely contributor is that the worker may have been distracted and or descending the stairs in a hurry in order to leave for the day. Corrective Actions: Workers were reminded of keeping their head in the game at all times and paying attention to their surroundings, even while doing routine tasks (i.e. descending stairs) Hoey/ Stiegler; 1/13/12

  22. Project Safety Record (March 12) *Includes Shopppers

  23. Risk Analysis & Management

  24. Issues • Coordination of construction contractors (Torcon & EWH) with installation activities • End of construction mind set risks • Increase in number of beam lines (and BL procurements and reviews) • Commissioning/install activities (documentation, ARR’s, job shoppers, etc.) • Need to analyze shielding & fault conditions and get buy in on booster injection into pentant 2, may require AB modifications & extra ARR phase

  25. Summary • ESH Program is well defined and documented • ESH Staff is well qualified and in place • Performance metrics are trending positively • Early deficiencies in construction safety program implementation have been addressed and processes are in place to move forward safely with minimum risk • On track with authorization basis process including BORE, SAD’s and ASE’s for Booster & SR • Program is continually improving & incorporating Lessons Learned

More Related