An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. National Town Hall Meeting on Demand Response and Smart Grid 9 Mark Gaines Director Customer Programs SDG&E and SoCalGas

  2. Application Summary Smart Meters to be installed 1.2 million electric meters 900,000 gas meters Cost/Benefits Cost = $576 million Benefits = $724 million 55% from operational improvements 45% from demand response benefits Demand Response Proposal C/I customers > 20 kW – CPP default rate C/I customers < 20 kW – Peak Time Rebate (PTR) 57,000 Thermostats for small C/I Res customers - PTR California Southern California Gas Company San Diego Gas & Electric SDG&E’s Smart Meter Program

  3. SDG&E’s Smart Meter Program Implementation Status • Meter installation: • 40,000 installed to date • 200,000 expected by year end • Full deployment by 5/1/2011 • DR Rates: • 1,750 C/I customers > 200 kW • Defaulted to CPP in May 2008 • 75% chose to stay on CPP • 20,000 C/I customers > 20 kW • Will be defaulted to CPP in 2011 • 1.2 million PTR customers will be eligible in 2011 • $.75/kWh rebate w/o automated controls • $1.25/kWh rebate w automated controls World Famous Sea World

  4. SDG&E Smart Meter Program World Famous San Diego Wild Animal Park Challenges: • Rate Challenges: • Communicating CPP for > 200 kW • 1 year bill protection between CPP and TOU • On-line rate comparison available • Averaged 1 hour for Account Executives to explain rate to customers • CPP for > 20 kW C/I customers (20,000 customers w/o Account Executives) • Rate design will be simpler (lower CPP rate) • 12 month data available before CPP rate offered • 1 year bill protection between CPP and TOU

  5. SDG&E Smart Meter Program Challenges: • IT System Challenges: • Highly complex “spider web” of new systems and system integrations • Data collection • Billing • Data reporting • Rate comparison • Bill presentation • Some implementation delayed • Additional delays possible Gaslamp District

  6. f i g u r a t i o n N 1 5 : M e t e r , C o n AMI I I 1 6 : M e t e r I n s t a l l S e r v i c e O r d e r s AMI Installation MDMA g n i l i l Head - End Vendor B I 1 7 : B u l k M e t e r I n s t a l l U p d a t e r o f s d a MV 90 ( Itron ) e R r e t e IDS M Scheduler I 1 9 : 3 P a r t y S a m p l e M e t e r T e s t D a t a Customer Information System ( CISCO ) r d M e t e AMI Technology Vendor r R M I 2 0 : M a n u f a c e t u r e r M e t e r T e s t D a t a e a s t d e e t r s u o R R & e A S N a r e d t g s e n M l i I l i n B t : a 0 e r t r 5 o a I f v D s a l d r a e D e m ODS a R t o a t a r e s t t u e a C M D Trouble : : 7 g 1 4 n 5 i I l I l i B Call & ? : a Hand - Held n 7 I 4 o I I 2 i N t Outage 1 X : a 6 I F a l M 2 i e l e I : t e 2 r r l Meter Reads a n : R 5 d e e Info a t ? d D O o s S A s W t 4 e s i X - o e u t r I s I r n : R t v s k i n Mainframe Messaging a 2 MRMS e a c s I Portal M e e t O : t C r g a r r U l a d r l e u e P : e e o Scheduler d v d u D i r t p 9 g s n i e t p s i N ( AMI Customer M f a 4 d c I o e R t M t U n t I e t e 7 a o l e i r o I f a a t : t / : i I i c 8 Online Presentment m 5 e p o C 4 a n 4 S t M I s s a e t : , h ? I i : y i 1 o r a I p I 42 : Meter Read Request I & Bill Analysis ) s n M n 8 3 I 1 O n v : I I I c : N e f 0 u 9 6 c I f b h N t I : R 2 : : I 43 : Meter Routes a V I i - r N e l l N 1 a l i : o r e C Mobile N r M C : 1 R 3 g s t n y d M 4 M m I r : e o e 1 u I i M : c f I 44 : Meter Reads & Interval Data a 1 t : e e z n e I a a o t 5 l o : e t 3 l M e t a t e e D : d s e r r e M t e e : Workforce Mgmt Meter Inventory t e i s C R u r M m e r Demand R I 45 : Meter Read Request R c e O t o D E M r e m f o C t e I e e o e E Outage Filter R S f a n n e E s t I r n - 3 e n S o p i Management a t m e r d e e 3 t l v t p Response ( n a 9 t C t n SORT ( MDSI ) i A , y I 46 : Meter Reads & Interval Data r d i r t e a 9 e a a t o n e m a o g t r O y s s e : t c u d n n B : R r , c r e s c y n e s u d ( SAP ) t s i t a s c l s d C l CRM ( SAP ) c o C t / f e n s e R l f n T P , e i t e R & t u D W u o R c / u n o s r t e h r r i R s e r e D m R e a o s e f s Geo Facility E b g t e t s C i f R r S e o s v e f o i s e D c m a B o s t t l r n o e R u q p & k t a t e o o r m i a c w e t e l l i a N e m u m e M n I t q l o i A Mgmt System GFMS e e P n d n ? n o a : i t l n n I 3 1 r s e s e s H n e u s s n u t o y e , t g n n & r s / u W i ) e , s i r r s s g t p s n e s t c ( Enghouse ) R t a B s A e s t c m E Q E o i I R c E e c e I o t l e Interface ( MMI ) t o n u n n I I o l i p N n N n e c q r n i f b i 1 AMI 1 e t s t a f e r n t 9 y n R e b i i I 18 : Meter i l 5 o n l 2 1 D r n r o e o o l r : y g i : g i a e g : : N t l s R d a g e n n l t u r s m y O M r i m D e e y C c Receipt Data C r R s s o d s t f g Data Collection / A s t a l n R U u e u i e e e I / i U a a t F r t c v i s s s I e l q t 4 n e i R 1 - t : s d Outage l o t E u t t t r k i u R a O e r r a e e o o o O v y a n i v X d d e w R t i , g l d , e g n b t Head - end t q e e m m : u i s e o y i Work e e F 6 s N e t , l n t - AMI Installation e e l M I e N D s M k b t t e s r r r r s I A o S X t R e w a : Orders t 3 u t s e P System ( s ) 2 i n I N g Vendor I , 4 I 1 e t M a : c . M M A e e t t e r e : r R 4 & e 2 a N e d I t s w , o r k D a t a & A l a r I 2 5 : O u t a g e V e r i f i c a t i o n R e q u e s t m s Outage , e t c . ) V e r i f i c a t i o n R e s p o n s e I 2 6 : O u t a g e Management Meter Data Management System ( MDMS ) l o I 27 : Restoration Verification Request r t s n System ( OMS ) t l I 28 : Restoration Verification Response o P u F c s R m e R e t r s y D m S d e n t s : n o y i X X t a S a a m g 0 X ) r n i o e l 4 s f b n n a I I o n I p M E s I I I e s N A N d & s 3 R 3 n 1 e d a d 0 & e e 2 : d s a 3 m I S n a I t W : d e a : 3 : e s e e D 3 w 0 D g a a / 4 d n 1 t R V V i I R i e R h 0 l N o D : a a e s : a i P a i r R r ( n t t L r r r e D r e g a e t Meter t t r i o A e a S a t A k r o t t i u u e D i a R t e b w s D e a M t n a a l D e M - a u r t o l I M d l Reads & l v t s b M a e r r : a i t : t M k u a M e : o 2 v e a 8 i 2 t n n l r 1 e e Interval Demand 3 1 t M I e I t N t N t e e I n I : r r 7 I Data ? 3 Response I Weather Data Service Control ( Itron ) r Geo Facility t e e M l a Applications t u Network r i V : LSGIS 3 MDMA 1 ATDI N X I Mgmt System GFMS Engineering Data ( EDW ) Meter t n o i P mapping kWickview r ( Enghouse ) e t e M Reads & l a u Meter Read t r i V : 4 1 N I Interval d a o L Data Mart Data Customer Data ( CDW ) X I 29 : AMI Network AMI Data Warehouse Installation Details Technology IN 7 : AMI Vendor GFMSmdt Network Asset Existing SDG & E Systems LEGEND Meter Data Management System Existing Integration or Planned outside of the AMI Project Planning and Engineering System Meter Asset Management Wave 1 – Meter Installation Support Application Development and Integration ( March , 2007 – July , 2008 ) CIS System or Integration AMI Solution Architecture – Phase 0 System Meter / DR Data Comm . Wave 2 – Billing & Remaining AMI Functionality Application Development and Integration ( January , 2008 Removed at Full AMI { estimate } – January , 2009 ) Deployment Mobile Workforce Management X Outage Management Updated : 12 / 27 / 06 Interface taken off the scope as the result of Phase 0 analysis . Version : Draft 0 . 11 GIS System Future Considerations ? Customer Portals Pending interface , needs verification from business process workshop and final business case decisions . Data Warehouse SDG&E Smart Meter Program Challenges: • IT System Challenges:

  7. SDG&E Smart Meter Program Lessons learned to date: • Need 1 person to develop optimal rate design • Objective: Send proper price signals • Need 2 people to develop optimal marketing campaign • Objective: Educate/communicate with res and non-res customers • Need 1000+ people to develop IT systems • Objective: Just make it work! World Famous Torrey Pines Golf Course

  8. Questions?