1 / 6

Settlement Options for Switchable Generation Resources RCWG 8/31/2016

Settlement Options for Switchable Generation Resources RCWG 8/31/2016. Agenda Emergency Settlement options Project next steps. Emergency Settlement Options. Option 1 – Optional Switch Non-ERCOT Control Area releases the SWGR.

atownsend
Download Presentation

Settlement Options for Switchable Generation Resources RCWG 8/31/2016

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Settlement Options for Switchable Generation Resources RCWG 8/31/2016

  2. Agenda • Emergency Settlement options • Project next steps

  3. Emergency Settlement Options Option 1 – Optional Switch • Non-ERCOT Control Area releases the SWGR. • SWGR QSE will have the decision if SWGR will move from non-ERCOT Control Area into ERCOT. • ERCOT will ask for SWGR to switch for an Emergency Condition. • Resource may be RUC committed • Settlement based on current Protocols • Option 2 – Required Switch • ERCOT will ask for SWGR to switch for an Emergency Condition. • Non-ERCOT Control Area releases the SWGR. SWGR will be required to switch to ERCOT if physically capable. • Potential for additional settlement treatment

  4. Alternatives for Emergency Settlement Option 2 There are multiple alternatives on how to financially settle the SWGR during suspended switching operation intervals. • A = Make whole to the resource cost + penalty from contractual obligations + penalty from market obligations • B = A + lost opportunity cost • C = B - RUC Clawback Objective: Compile list of potential items in each of the following categories and bring to WMS for discussion: • Make whole to resource cost • Using Generic or verifiable cost • No claw-back charge • Penalties from contractual obligations • Capacity availability penalties etc. • Penalties from market obligations • Capacity availability penalties etc. • Lost opportunity cost • Market based revenue potential from non-ERCOT Control Area minus ERCOT market revenue

  5. Project next steps Project timeline: • Working groups under ROS (PLWG, OWG) have discussed and not had any comments, consider no additional assignments to ROS at this time • Working groups under WMS (QMWG, CMWG, RCWG) assigned various topics, groups will report back to WMS on progress • September 7th – WMS meeting • Workshop will be scheduled if requested • Submit comments to David Thompson • David.Thompson@ERCOT.com

  6. Questions

More Related