1 / 21

Material Requirement Planning (MRP)

Material Requirement Planning (MRP). Chapter 16 Feb 9, 2006. Material Requirement Planning (MRP). ______________________________________ ______________________________________ Key Outputs of MRP Calculate demand for component items

augustus
Download Presentation

Material Requirement Planning (MRP)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Material Requirement Planning (MRP) Chapter 16 Feb 9, 2006

  2. Material Requirement Planning (MRP) • ______________________________________ • ______________________________________ Key Outputs of MRP • Calculate demand for component items • Determine requirements for subassemblies, components, and raw material • Determine when they are needed • Generate work orders and purchase order • Consider lead time

  3. When to use MRP • ___________________________________ • ___________________________________ • ___________________________________ • ___________________________________ Dependent / Independent Demand?

  4. Demand Characteristics Demand Characteristics for Finished Products and Their Components Dependent demand Independent demand 100 x 1 = 100 tabletops 100 tables 100 x 4 = 400 table legs 400 – 300 – 200 – 100 – Discrete demand Continuous demand 400 – 300 – 200 – 100 – No. of tables No. of tables 1 2 3 4 5 Week M T W Th F M T W Th F

  5. Material Requirements Planning (MRP) Work orders Purchase orders Rescheduling notices MRP Input & Output

  6. Product Structure Record Clip Assembly (1) Rivets (2) Pressboard (1) Level 0 Clipboard Level 1 Top Clip (1) Bottom Clip (1) Pivot (1) Spring (1) Level 2 Major Inputs to MRP Process:1. Bill of Material • Product structure file • Determines which component items need to be scheduled

  7. Major Inputs to MRP Process:2. Master Production Schedule(MPS) • Drives MRP process with a schedule of finished products • Quantities represent production not demand • Quantities may consist of a combination of customer orders & demand forecasts • Quantities represent what needs to be produced, not what can be produced • Example PERIOD MPS ITEM 1 2 3 4 5 Clipboard 85 95 120 100 100 Lapdesk 0 50 0 50 0 Lapboard 75 120 47 20 17 Pencil Case 125 125 125 125 125

  8. Major Inputs to MRP Process:3. Inventory Record • _________________________________________________ • Contains an extensive amount of information on every item that is produced, ordered, or inventoried in the system • _________________________________________________ DESCRIPTION INVENTORY POLICY Item Pressboard Lead time 1 Item no. 734 Annual demand 5000 Item type Purch Holding cost 1 Product/sales class Comp Ordering/setup cost 50 Value class B Safety stock 0 Buyer/planner RSR Reorder point 39 Vendor/drawing 07142 EOQ 316 Phantom code N Minimum order qty 100 Unit price/cost 1.25 Maximum order qty 500 Pegging Y Multiple order qty LLC 1 Policy code 3

  9. MRP Processes – 4 Basic Steps • Exploding the bill of material • ___________________________________ • Netting out inventory • ___________________________________ • ___________________________________ • Lot sizing rule – How many units • ___________________________________ • ___________________________________ • ___________________________________ • Time-phasing requirements • ___________________________________

  10. Lot Sizing Rule Comparison • The FOQ rule ___________ _______________________ • The POQ rule ___________ _______________________ _______________________ _______________________ • The L4L rule ___________ _______________________ _______________________ _______________________

  11. MRP Matrix Gross Requirement • Derived from planned order releases of the parent • Actual / estimated demand, in case of final product Schedule Receipts • Items on order • Scheduled to arrive in the future time period Projected on hand • Current inventory, or anticipated inventory at the end of period Inventory on-hand at end of period t - 1 Scheduled / planned receipts in period t Gross requirements in period t Projected on-hand Inventory at end of period t = + -

  12. MRP Matrix Net requirements • Actual quantity to produce based on projected on hand and on-order quantity Planned Order Receipts • Quantity, when orders need to be received • Consider lot sizing rule: Planned Order Release • When order need to be placed to receive on time • Consider lead time

  13. ITEM NAME OR NO. PERIOD LOT SIZE LT 1 2 3 4 5 MRP Matrix (You can download the template from our class webpage)

  14. ITEM: CLIPBOARD LLC: 0 PERIOD LOT SIZE: L4L LT: 1 1 2 3 4 5 Gross Requirements 85 95 120 100 100 Scheduled Receipts 175 Projected on Hand 25 Net Requirements Planned Order Receipts Planned Order Releases Example MRP Matrix

  15. A LT=3 C(3) LT=4 D(2) LT=2 MRP Example 1 Given the following information, determine when orders should be released for A, C, and D and the size of those orders

  16. B LT=2 D(3) LT=2 A LT=3 C(3) LT=4 D(2) LT=2 MRP Example 2 Given the following information, determine when orders should be released for A, B, C, and D and the size of those orders.

  17. Evolution of MRP • MRP (material requirements planning) was the precursor to ERP • Primarily a production planning and control system • MRP evolved to MRP II (manufacturing resource planning) • ERP (Enterprise Resource Planning) and ERP II continue to extend the links through all business processes

  18. Enterprise Resource Planning (ERP)An Overview • Organizes and manages a company’s business processes by sharing information across functional areas • Connects with supply-chain and customer management applications • ERP in the nutshell* • Client server software • Integrates majority of business processes • Processes majority of transactions • Enterprise wide database • Real time data access * adapted from e-courseware, MIT Sloan

  19. ERP Modules [Figure 12.1 Organizational Data Flow]

  20. Finance & Accounting Sales & Marketing Production & Materials Management Human Resources ERP Modules[Figure 12.2 ERP’s Central Database] ERP Data Repository

  21. ERP Implementation Process • First step is to analyze business processes • Which processes have the biggest impact on customer relations? • Which process would benefit the most from integration? • Which processes should be standardized? • Use of Internet portals can aid implementation

More Related