1 / 11

TFTR D&D ALARA PLAN FY00 thru FY02

TFTR D&D ALARA PLAN FY00 thru FY02. December 3, 1999 Presented By: James H. Chrzanowski. TFTR D&D ALARA PLAN. This presentation will review for the ALARA committee those D&D activities being planned for the three year plan, including: Assumptions made in determining dose estimates

aulani
Download Presentation

TFTR D&D ALARA PLAN FY00 thru FY02

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TFTR D&D ALARA PLANFY00 thru FY02 December 3, 1999 Presented By: James H. Chrzanowski

  2. TFTR D&D ALARA PLAN • This presentation will review for the ALARA committee those D&D activities being planned for the three year plan, including: • Assumptions made in determining dose estimates • General task descriptions • Estimated personnel exposure for each D&D task • Controls which will be used • The safety and protection of the work force will be the primary concern during the D&D Removals • Integrated Safety Management (ISM)

  3. TFTR D&D ALARA PLAN • The TFTR D&D Project Mission is to: • Surgically remove items which can be re-used within the DOE complex • Remove Tritium contaminated and activated systems for disposal • Clear the Test Cell of hardware except for the Neutral Beams and their sources • Reclassify the D-site complex as a non-nuclear facility as defined in DOE Order 420.1 (“Facility Safety”) • Provide data on the D&D of a large magnetic fusion facility

  4. TFTR D&D ALARA PLAN • How dose estimates were developed: • Dose rates based upon surveys performed this Summer and Fall. • Man-hours were based upon estimates developed by engineering for the D&D Project • Estimates were conservative • No credit was taken for the use of shielding, even though shielding will be used wherever possible • Activities whose estimated dose were less < 1.0 mrem were discounted from totals

  5. TFTR D&D ALARA PLAN • SURVEY DATA • - Top of umbrella structure • 0.8-1.0 mrem/hr. • - Midplane adjacent to TF coil • 5.0 mrem/hr. • - At edge of 102-ft. elevation • 0.8 mrem/hr. • - Vacuum Vessel on contact • 25-35 mrem/hr. • - At yellow fence • 0.16 mrem/hr.

  6. TFTR D&D ALARA PLAN Sample Dose Estimating Table Man-hours to complete task Dose-Rate/Hour Primavera Activity No.

  7. TFTR D&D ALARA PLAN • Steps Taken to Minimize Exposure • Experienced personnel will be used for critical tasks such as vacuum interface/line breaks • Lead shielding will be used whenever possible • Disassembly sequence • Special tools • Pre-job Briefings • Post-job Briefings

  8. TFTR D&D ALARA PLAN • Contamination Issues • Personnel shall wear protective clothing/equipment as determined by Health Physics • Elephant trunks, gloveboxes, etc. shall be used to contain airborne contamination • Each procedure requires HP to survey/smear area prior to starting work to determine working condition

  9. TFTR D&D ALARA PLAN • FY BREAKDOWN • FY00 -Area preparation, initial diagnostic removals, Tokamak removals on top of umbrella structure • Minimal expected personnel dose • FY01- Majority of Diagnostic line breaks, pump duct removals, vacuum vessel entry, start of contaminated basement vacuum line removals, prep and concrete fill VV • Highest expected personnel dose • FY02 – Umbrella structure removal, Diamond cutting of VV and close vessel work • Reasonably high personnel dose

  10. TFTR D&D ALARA PLAN • PROJECTED DOSE SUMMARY • (Conservative estimates)R1 • FY00 …………………. 4.1 Rem • FY01 …………………. 13.9 Rem • FY02 …………………. 6.6 Rem • D&D Projected Total= 24.6 Rem

  11. TFTR D&D ALARA PLAN • ESTIMATED DOSE COMPARISON • D&D Project……………………….. 24.6 Rem • 1996 TFTR Outage (requested) ….. 13.7 Rem • 1996 TFTR Outage (actual) ………. 5.05 Rem • (internal & external values)

More Related