Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore. STRAWMAN Presented FERC Little Rock technical conference. White Paper DRAFT ATTACHMENT K Presented FERC Atlanta technical conference. Solicited additional feedback prior to summit.
E N D
Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore
STRAWMAN Presented FERC Little Rock technical conference. White Paper DRAFT ATTACHMENT K Presented FERC Atlanta technical conference. Solicited additional feedback prior to summit. FERC Order 890 Attachment KOVERVIEW
Base Case Model Critical Energy Infrastructure Information (CEII) Confidential Information Planning Criteria Construction Plan FERC Order 890 Attachment KDefinitions
Comment - Confidential Information Definition too broad Cleco Response Cleco disagrees. Consistent with FERC’s model of Protective Order & confidentiality provisions of OATT. Comment - Construction Plan What is construction plan limited to 5 years Cleco Response Five year time frame came from Cleco’s budgeting dept. Cleco agrees that a plan should exist to include proposed projects up to 10 years. FERC Order 890 Attachment KDefinition Comments
Comment -Base Case Model Specify time period Indicate changes & discrepancies in SPP & SERC models Stakeholders should have input into SPP & SERC Cleco Response MMWG set model time frame Cleco submits data for Cleco’s CA Data same for Cleco in both SPP & SERC Stakeholders need to participate through SPP & SERC process not Cleco. FERC Order 890 Attachment KDefinition Comments
Model Development including input by stakeholders. 10 year plan (Construction Plan 1-5, Proposed Plan 6 - 10). Coordinated regional planning with adjacent transmission owners. FERC Order 890 Attachment KPlanning Process
Comment - Input into planning criteria. Cleco response. Planning criteria is industry accepted. Comment - Coordinated regional planning with adjacent transmission owners. Cleco response. Agree. Only adjacent systems are monitored. Change Attach K to transmission owners. FERC Order 890 Attachment KPlanning Process Comments
Stakeholders may request formation of committee. Open & welcome input from stakeholders. Post calendar of events on OASIS as well as email exploder to keep stakeholders up to date on planning process as well as allow comments and input. Affected systems FERC Order 890 Attachment KCoordination
Comment - Summit is to inform stakeholders rather than solicit input & no follow up. Cleco Response - Section 5.1 clearly states stakeholders may comment and provide input. Flow chart shows posting pre & post summit. Comment – Company & affiliates can’t hold more than one seat on stakeholder committee Cleco Response – Cleco agrees and language will be changed. FERC Order 890 Attachment KCoordination Comments
Comment – Stakeholder may request any issue related to transmission planning be considered by committee. Cleco Response – Cleco agrees and language will be changed. FERC Order 890 Attachment KCoordination Comments
Willing to share all information, but must protect confidential information including CEII. Require requester to sign confidentiality agreement. FERC Order 890 Attachment KOpenness
Comment – Signing a confidentiality agreement is too excessive. Cleco Response – consistent with OATT and we are referring ONLY to confidential information. Non confidential information does not apply. FERC Order 890 Attachment KOpenness Comments
Cleco will allow stakeholder to request base case power flow models, planning criteria, as well as assumptions for verification and validation of studies provided appropriate confidentiality agreements are in place. Post construction plan on OASIS. FERC Order 890 Attachment K Transparency
Comment - Stakeholder should be allowed to download information directly rather than make a request. Cleco response – White paper does not specify downloading, only process to obtain information. Cleco is evaluating technical options including eRoom or FTP server FERC Order 890 Attachment K Transparency Comments
Firm PTP reservations will be modeled during active timeframe of TSR, unless it qualifies for rollover rights (5 years or more). Network customers (native load & non-native load) submit a 10 year load forecast & DNR’s. FERC Order 890 Attachment K Information Exchange
All stakeholders are treated comparably whether network, Point to Point, or pre 888. Models and supporting data are available for replication & duplication of results. FERC Order 890 Attachment K Comparability
Any party may dispute planning process by providing written notice of such dispute. Representatives of each party shall negotiate to resolve dispute within 10 business days Executive management of each party (30 days) Hire an external mutually agreed upon mediator File section 206 complaint with commission FERC Order 890 Attachment K Dispute Resolution
Comment – Should not apply to pre 888 agreements. Cleco response – Agree, it is an OATT attachment. Comment – Who is independent regional planning authority? Cleco response – SPP FERC Order 890 Attachment K Dispute Resolution Comments
Cleco participates in SPP & SERC (Entergy) model development processes. Coordinate with affected systems Joint planning meetings w/ Entergy (SERC) & SPP. Voting member of SPP TWG. FERC Order 890 Attachment K Regional Participation
Separate queue on OASIS for TSR & generator interconnection. Study annually three (3) highest priorities as established by stakeholders (previously 1) FERC Order 890 Attachment K Economic Planning Studies
Comment– May be impracticable to submit data at time of economic study request. Cleco response – Disagree. Execute study, scope & details must be included. Comment – Confidentially of data. Cleco response – Agree. Language will be added for confidential information. FERC Order 890 Attachment K Economic Planning Studies Comments
Comment – Cost of studies above 3 will be assigned to requesting parties. Cleco response – Agree. Language will be modified. Comment – Requesting parties be billed as study cost are incurred rather than prepayment. Cleco response – Draft language to be consistent with OATT for study cost payments. FERC Order 890 Attachment K Economic Planning Studies Comments
Reliability Upgrades – LPSC rate base for planning criteria violations. Economic Upgrades Cost allocated to beneficiary. FERC Order 890 Attachment K Cost Allocation
Comment – Stakeholders should have input into Planning criteria. Cleco response – Cleco’s planning criteria is in accordance with NERC reliability standards & SPP criteria. Comment – Clarity is needed is defining an economic study. Cleco response – Disagree. Clearly stated that if Cleco’s planning criteria is not violated which is reliability, then it is an economic upgrade. FERC Order 890 Attachment K Cost Allocation Comments
Cleco will recover cost for three economic studies annually through existing rate structure. Requestor will pay for any additional studies. FERC Order 890 Attachment K Recovery of Planning Cost
Comment – Parties should not be exposed to TP’s cost exceeding estimate. Cleco’s response – Disagree. OATT requires TC’s to pay for studies. FERC Order 890 Attachment K Recovery of Planning Cost Comments