Title Slide. MONTHLY STATUS REPORT– May 2013 LOS ALAMITOS UNIFIED SCHOOL DISTRICT Los Alamitos High School Track Modernization Project May 21, 2013 Los Alamitos, California. ACTIVITY SUMMARY. General Site Conditions Mobilization of Site Complete Initial Surveying Complete
E N D
Title Slide MONTHLY STATUS REPORT– May 2013 LOS ALAMITOS UNIFIED SCHOOL DISTRICT Los Alamitos High School Track Modernization Project May 21, 2013 Los Alamitos, California
ACTIVITY SUMMARY • General Site Conditions • Mobilization of Site Complete • Initial Surveying Complete • Storm-water Pollution Prevention Plan Implemented • Demolition Complete • Soil Extraction Complete • Grading and Compaction 90% Complete • Concrete Retaining Curb at Parking Lot 95% Complete Executive Summary • ON TIME AND ON BUDGET
ACTIVITY SUMMARY • Track – Start of Construction Progress 21 Track – After First Day of Construction Track Prior to Construction
ACTIVITY SUMMARY • Demolition • Complete Progress 21 Dust Mitigation Typical Equipment on Project
ACTIVITY SUMMARY • Storm-water Pollution Prevention • On-Going Progress 21 Hay Tubes at Perimeter of Site Crushed Rock at Entry – Dust Mitigation
ACTIVITY SUMMARY • Site Leveling • 90% Complete Progress 21 Laser Leveler on Blade Laser Leveling Equipment
ACTIVITY SUMMARY • Concrete Curb at Parking Lot • 95% Complete Progress 21 Formwork for New Concrete Curb Curb at Parking Lot Saw-Cut
ACTIVITY SUMMARY • Soil Excavation/Compaction • 90% Complete Progress 21 Current “Track” Current “Track”
SCHEDULE • General Site Conditions • Begin Electrical and Timing Conduit Installation • Begin Main Drain Tie-In • Begin Installation of Site Curbing • Begin Installation of Trench Drains • Begin Installation of Fence Posts Schedule