An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status of BepiColombo Harri Laakso ESA/ESTEC, Code SRE-OS, Noordwijk, The Netherlands 1 H. Laakso, SERENA - HEWG meeting, Mykonos, Greece, 8-11 June 2009

  2. Launcher: Ariane 5 Launch date: 21-Jul-2014 MOI date: 21-May-2020 (5.8 year cruise to Mercury by electric propulsion) Backup: 06-Aug-2015  31-Oct-2021 (6.2 years) Launch strategy: Direct escape 1-year Earth-to-Earth transfer Earth, 2 Venus, 4 Mercury flybys/gravity assists Gravity capture into Mercury orbit / Final Mercury orbit adjustment by chemical propulsion Science operations: 1 year nominal plus 1 year extended Mission Design Overview

  3. Summary of IPDR Results

  4. MPO Payload Resources - Mass * excl. 1.5 kg MIXS base plate; ** excl. thermal straps (S/C) Experiment unit interconnection harness (ca. 6 kg) not included

  5. MPO Payload Resources - Power Operational scenarios under study by SOC; re-allocation pending further assessment Limitation to 100 W baseline for perihelion or certain mission phases

  6. MPO Payload EID-B Status EID B Issue 1 with configuration control to come by summer / early autumn this year !!

  7. Open P/L procurement issues: Solutions to be addressed without delay Firm up and finalise P/L experiment interface definition for H/W phase: Partly achieved, but still missing elements Consolidation to be addressed without delay P/L accommodation and local interfaces to be confirmed and detailed: Ongoing activity, as part of PDR with minor adjustments only H/W phase comes upon us, and requires significant more attention to detailed work and close interaction and reporting In view of the above and the observed IPDR results: Please stop “nice-to-have” optimisation dreams Keep momentum and intensify P/L work Adopt the “Yes We Can” attitude – also we got to get out of a crisis ! MPO Payload Priorities

  8. The Critical Equipment Review was held between September-December 2008 Critical technological elements were reviewed Highly useful exercise and confirmed many technologies that are not considered critical any more Some remained open and were further studied in spring 2009, such as solar arrays, antenna pointing mechanism and wave guide The CER board met on 18 December 2008 Recommended to start the PDR activity Recommended that Collocation Meeting should be organized only after the test results on the solar array are available Gave critical notes on the mass traceability and maturity of technology for solar array, antenna pointing mechanism and waveguides Critical Equipment Review - 2008

  9. The PDR Kick-Off was held on 10 March The CER Board provided guidance to the review team and recommendations on work by the Prime before collocation The SPC Tracking Committee follows the PDR and advises the SPC Major items were: Overall mass budget with increasing trend remains a major concern (10% margin!) S/W and AOCS complexity and development schedule AIV (accessibility of equipment, schedule) Solar Array Contamination risk by thruster plumes Collocation meeting with Astrium on 4 – 7 May The PDR Board meeting on 29 May PDR Activities and Issues

  10. Preliminary draft recommendations of the PDR board are not yet public The PDR Board recognized significant development accomplished during the past 12 months The board believes strongly that BepiColombo will fly Solar arrays are adequate for the Mercury environment and are currently tested for at 200 C for 10 000 hrs at 230 C for 5 000 hrs The results confirmed the expectations of solar cell aging The PDR Board will reconvene in September to discuss the remaining key issues, such as mass and solar array Final PDR meeting in November is for closing the RIDs and AIs The BepiColombo CaC needs to be confirmed after the summer in order to issue the SPC paper in September for the SPC meeting on 2 October 2009 PDR Results

  11. Manufacturing of STM is in final stage at JAXA, test preparations on-going Tests on EM are on-going On-board S/W requirements review completed Launcher coupled load analysis confirmed acceptable notching profile Characterization tests of thermal hardware and solar cells are on-going Issue: Solar array appears to have too little margin to cover UV degradation, temperature uncertainties and modified cosine law. Addition of one solar cell string is under consideration (MMO height increase of 16 cm) MMO Status