1 / 14

Fiscal Year 2019 TransNet Audit Schedule B Guide

This guide details the preparation of TransNet's Fiscal & Compliance (AUP) Audit Schedule B for FY 2019. Learn how to set up, populate, and ensure accuracy between Schedule B and Schedule A.

awentia
Download Presentation

Fiscal Year 2019 TransNet Audit Schedule B Guide

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Fiscal Year 2019TransNet Fiscal & Compliance (AUP) Audit Schedule B Preparation

  2. Schedule B vs. Schedule A • Schedule B is not identical to Schedule A • Report TransNet Extension activity only • No Beginning Balance Column • No Adjustments Column • No TI Section • No Non-TransNet Section • No GASB 31 Section • Includes Completed Project totals by Program

  3. Set Up the FY 2019 Schedule Change dates for the current audit year Ensure MPO IDs & Project Numbers on Schedule B are in same order as Schedule A

  4. Set Up the FY 2019 Schedule Ensure ending balance (before adding FY19 activity) ties to Schedule A beginning balance

  5. Set Up the FY 2019 Schedule ***This is Schedule A*** GASB 31 is not on Schedule B But is on Schedule A Must tie to Schedule B FY18 Ending Balance

  6. Populate your Schedule Now that you’ve set up your Schedule, begin populating the report • Do not automatically pull in prior year cumulative data • Each cell with prior year data should reflect all information: =80000+15000+25000 • Provides audit trail that all reviewing parties can follow • Add current year data to formula • Enter amounts from Schedule A Adjustment column

  7. Adjustment Activity • No ‘Adjustment’ column in Schedule B • Using Schedule A Adjustment column: • Determine if adjustment is a Revenue or Expenditure (may have both in one adjustment) • If Revenue, then increase/decrease ‘Funds Received’ in Schedule B • If Expenditure, increase/decrease ‘Project Expenditures’ in Schedule B

  8. Adjustment Activity • No ‘Adjustment’ column in Schedule B • Using Schedule A Adjustment column: • Notes to Schedule A should provide guidance to determine if adjustment to Revenue or Expenditure (if Note is not clear, then modify the Note) • May also be adjustment to Interest Income • For Pooled Interest, adjustment to project should always be increase to Revenue

  9. Reminders • Active CIPs/MPO IDs • Do not report in Schedule A if all zeroes • Okay to keep on Excel spreadsheet, just ‘Hide’ row; • No need for Footnote • Detail of all active projects are to be reported in Schedule B, even if not showing in Schedule A • Cells that must match between Schedules A and B: • Ending balance at 6/30/19 for each CIP; • Ending balance at 6/30/19 for each MPO; • Ending balance at 6/30/19 for each Program; and • Total Cumulative TransNet

  10. Reminders • MPO IDs & Project Numbers should be reported in same order on Schedules A & B • Footnotes are generally not required • Check with Auditors for unusual situations that may require a one-time Footnote

  11. Schedule B sample This last column must match Schedule A’s ending balance as of 06/30/2019

  12. Completed Projects • Completed Projects are shown in Schedule B to provide a complete picture of cumulative activity • The Completed Projects section is listed by Program and includes the net of all projects within the Program type • Use the same order as Schedule A • Location is below “Subtotal Cumulative TransNet Extension” and before “Total Cumulative TransNet Extension” ***Do not include TransNet I activity in this section***

  13. Completed Projects Completed projects populated here.

  14. Thank you

More Related