GLAST LAT Tracker Delta Manufacturer Readiness Review for Tray Assembly and Test at G&A

GLAST LAT Tracker Delta Manufacturer Readiness Review for Tray Assembly and Test at G&A. Luca Latronico INFN-Pisa luca.latronico@pi.infn.it. Relevant Documents. LAT-PS-01801 Integration of TMCM and SSD Ladders onto Tracker Trays

aya
Download Presentation

GLAST LAT Tracker Delta Manufacturer Readiness Review for Tray Assembly and Test at G&A

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GLAST LAT Tracker Delta Manufacturer Readiness Review for Tray Assembly and Test at G&A Luca Latronico INFN-Pisa luca.latronico@pi.infn.it

  2. Relevant Documents LAT-PS-01801 Integration of TMCM and SSD Ladders onto Tracker Trays released – MRB on wire-bonds encapsulation removal requires sigantures approval LAT-PS-03534 Single Tray Electrical Test Plan released Production company: G&A Engineering, Carsoli-Oricola (AQ)

  3. INFN provides G&A with tray panels, TMCMs, ladders, (and their relative locations on the tray) + Nusil adhesives Alignment jig (WS-B1) provides: TMCM planarity Pitch adapter planarity Bonding pads alignment (HV and shield pads) Dry assembly test to check TMCM connectors clearance Adhesive distribution (WS-B2) Assembly of TMCM onto tray (WS-B3) Metrology (WS-B4) Wire bonding (WS-B5) Electrical tests (WS-B6) Current production rate ramping up: need to match CC pocket and MCM connector depth extra screening on TMCM pitch adapter (missing connections on signal strips and HV lines – PA debondings) alignment jig Assembly and test flow-chart WS-A Material receiving and inspection WS-B TMCM Integration

  4. Ladder test (WS-C1) Tray Z positioning under CMM (WS-C2) 50m wrt nominal position Ladder positioning on the bridges (WS-C3) Alignment from bridge itself used as reference and excellent alignment of SSD inside ladder (~2 mm RMS) Glue deposition (WS-C4) 19 spots of siliconic glue/SSD 4 spots conductive glue + 1 unbroken line across ladders Ladder assembly (WS-C5) Ladder metrology (WS-C6) Ladder height 0.250.1 mm Ladders relative parallelism of 0.1 mm Wire bonding (WS-C6) Destructive pull tests on coupons (>5g each) Visual inspection Functional test by INFN with tray inside box LAT-PS-03534 DRB and shipping to INFN Ladder assembly tools Assembly and test flow-chart WS-C Ladders integration WS-D Final disposition

  5. Availability of components and tools • Bare panel trays after TVAC test in Roma2 • 27 trays available – planned supply is 4trays/day • SSD Ladders from G&A and Mipot • ~1400 ladders available - 400 more from G&A (200 to test, 200 being built) – 900 will be built from Mipot asap • MCM from SLAC through quick functional verification at INFN-Pisa • Currently 38+32 • Could match 14 trays (26 TMCMs) from first lot of 38 because of connector stick-out issue • 6 TMCMs sent back to SLAC for PA debondings • Nusil at G&A for ~3/4 of tray production • G&A tools • TMCM alignment tools: 5 • Ladder integration tools (tray alignment + ladder bridges): 6 • CMM: 2 (1 for alignments, 1 for metrology) • Glue dispenser: 2 • wire-bonder: 2 • 2 working shifts per day to grant production rate of 4 trays/day • EGSE for functional tests • 1 full EGSE system installed at G&A and operated by INFN

  6. Data exchange with INFN-Pisa • From INFN to GA: • List of subparts (ladders and TMCM) from INFN-Pisa • From GA to INFN: • List of subparts with G&A reference SNs (neede for tray box) • Progress of assembly (weekly) • Quality Assurance • Rely on G&A certified QA program for internal activity • Handle major NCR notified from G&A (MARECO) with Pisa system

  7. Tower 0 tray production • 14 complete trays assembled (27 TMCMs and SSD Ladder planes) • 23 Si layers were within specs • 4 Si layers had short for problems related to bias circuit delamination • All went through thermal tests • 4 Si layers (bottom side of heavy trays) had many disconnected channels because of CTE mismatch impact on wire-bond encapsulation  MRB on wire-bond encapsulation • 23 SSD layers operated successfully up to now

  8. y x L02 L02 L03 L01 silicon #1 silicon #2 silicon #3 silicon #4 Pin 1 Pin 3 L11 L13 L12 MCM side L23 L21 L22 Pin 2 Pin 4 L31 L33 L32 Metrology of ladders alignment Metrology: with a CMM with interchangeable mechanical-optical heads, the positions of 12 “C” markers, 3 for each ladders, and the positions of the MCM alignment pins are measured on both sides of the tray.

  9. Results – ladders alignment

  10. Functional test results – leakge current 079MID front: 1.67 uA @ 150 V 079MID back: 1.85 uA @ 150 V 050MID front: 2.02 uA @ 150 V 050MID back: 1.77 uA @ 150 V

  11. Functional test results – trigger rates vs threshold 079MID back 079MID front 050MID front 050MID back

  12. Functional tests results – bad channels • Total number of bad channels well within specs (16 max) • High reliability of PA screening test on TMCM • High yield of wire-bonding

  13. Conclusions • Assembly and test procedures well tuned and tested on EM trays and tower 0 • G&A moving rapidly to planned production rate • High yield of assembly so far • > 100 ladders glued and wire-bonded with no failures and well within specs • Tower A production well within specs • Leakage current • Noise and thresholds performance • Bad channels