An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. status of the machines over X-mas standby period, services required and plans for rapid start-up OP Group Meeting KH

  2. cooling circuits • cooling circuits require 200-300 kW heat load in order not to freeze • circuits of the equipment must not be separated from the main cooling circuit • for the temperature surveillance (BE/OP/TI) alarms must be available KH

  3. cooling circuits - IEFC 19/10/12

  4. cooling circuits - IEFC 19/10/12 • CV will intensify the rounds during the closure especially if the weather is cold. • On Monday January 7th , CV will restart : • PS : FDED-00032 PS Magnet • POPS: FTEB-00046 • POPS will be fully operational on Tuesday. S.Deleval – IEFC 19/10/12

  5. 6. February 2012: a good example • Extremely cold and windyweather • All the primary circuits were running with a reducedload. • Large amount of problems on drinkable and fire hydrant circuits but the primary circuits hadwellresisted • POPS start up wasdelayedbecause the filling circuit wasfrozen → corrective workacheived. IEFC 19 October 2012 S.Deleval – IEFC 19/10/12

  6. proton machines, status • Linac2 (see EDMS 1235164): • source pulsing, beam on source beam stopper • most converters on • RF off • vacuum maintained • PSB: • some TT2 converters on • all other converters off • RF off • vacuum maintained • PS: • converters off • RF off • vacuum maintained • SPS: • power converters off • RF power amplifiers on (dampers, TWC800, TWC200, IOT prototype in BB3) • vacuum maintained • cooling stays on KH

  7. proton machines, services • * EN/CV and EN/EL provide always piquet service • ‘best effort’ service during working hours, but somebody must be reachable • piquets which are not required (magnets, kickers, LL RF, … do not appear) • magnets: in case of water leaks best effort • OP: TI plus support from beam operators plus supervisor KH

  8. ion machines, status • Linac3 (see EDMS 1235164): • source pulsing, beam on source beam stopper • most converters on • RF off • vacuum maintained • LEIR: • all converters off • RF off • magnetic cycle prepared in case of re-start • vacuum maintained KH

  9. ion machines, services • * EN/CV and EN/EL provide always piquet service • ‘best effort’ service during working hours, but somebody must be reachable • piquets which are not required (magnets, kickers, LL RF, … do not appear) • magnets: in case of water leaks best effort KH

  10. other services • GS: • roads cleared • fire brigade informed • lifts • DSO coverage • references: • Linacs: EDMS 1235164 KH

  11. 2013 start-up beam to be given downstream as soon as ready beam parameters to be confirmed well before X-mas KH