An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HBD R&D at the WIS Boris Khachaturov, Alexander Kozlov, Ilia Ravinovich and Itzhak Tserruya Weizmann Institute, Israel • Mini Workshop on PHENIX upgrade plans, BNL Aug. 5-6, 2002 Itzhak Tserruya PHENIX Upgrade mini-Workshop

  2. Outline • The HBD concept • Goals of the R&D programme at the WI • Set-up and Status • Plans Itzhak Tserruya PHENIX Upgrade mini-Workshop

  3. HBD in PHENIX HBD HBD • Compensate magnetic • field with inner coil • (B=0 for r 50-60cm) • Compact HBD in the • inner region • Specifications • * Electron efficiency 90% • * Modest  rejection ~ 200 • * Double hit recognition 90% Itzhak Tserruya PHENIX Upgrade mini-Workshop

  4. Concept: • Windowless Cherenkov detector • Radiator and detector gas: CF4 • Large bandwidth and large Npe • Transmissive CsI photocathode • No photon feedback Detector Configuration Itzhak Tserruya PHENIX Upgrade mini-Workshop

  5. CsI photocathode QE The most attractive option: • Transmissive photocathode • Relatively high quantum efficiency Very large bandwidth: 6 – 11.5 eV Very large N0 940: 40 pe in a 50cm radiator Itzhak Tserruya PHENIX Upgrade mini-Workshop

  6. Novel Concept: • Windowless Cherenkov detector • Radiator and detector gas: CF4 • Large bandwidth and large Npe • Transmissive CsI photocathode • No photon feedback • No ring image as in RICH or in • proximity focus  blob image • Low granularity • Detector element: multi - GEM • High gain Detector Configuration Itzhak Tserruya PHENIX Upgrade mini-Workshop

  7. Detector configuration: granularity • Pads • Shape: hexagonal • Dimension: app. size of the blob (R=1.8cm) • 2000 pads to cover central arm acceptance • Threshold: defined by background Itzhak Tserruya PHENIX Upgrade mini-Workshop

  8. Main Goals of the R&D Programme • Demonstrate concept validity * Response to electrons and hadrons (Npe per electron and per mip) * CF4 scintillation * Demonstrate e-efficiency and double hit recognition. Itzhak Tserruya PHENIX Upgrade mini-Workshop

  9. CF4 radiator gas / Alternative C4F10 ? • CF4 scintillation parameters: • Peak at 163nm • 100-200 photons/MeV and dE/dx = 7keV/cm • 20-30% CsI Q.E.. • Results: • 0.007 ph/(MIP cm2) • 250 MIPs in one PHENIX arm • 10 cm2 size of the blob • Signal / noise > 10! • Shades reduce noise by a factor of 3 • Timing ? • CF4 scintillation is not a killing factor Itzhak Tserruya PHENIX Upgrade mini-Workshop

  10. Main Goals of the R&D Programme • Demonstrate concept validity * Response to electrons and hadrons (Npe per electron and per mip) * CF4 scintillation * Demonstrate e-efficiency and double hit recognition. • Generic Detector R&D * CsI / CF4 bandwidth * Gain in GEM * Aging of CsI and GEM in CF4 * Optimize Detector configuration: 3 GEM or 2GEM + MWPC? * dE/dx in CF4 • Monte Carlo simulations Itzhak Tserruya PHENIX Upgrade mini-Workshop

  11. Cosmic ray signals in Ar/CO2 Ar/CO2 70-30 • VGEM = 450 V • E d = 2.0 kV cm –1 • E t = 4.0 kV cm –1 • E i = 4.5 kV cm –1 S. Bachman et al. NIM 438A (1999) 376 S. Bachman et al. NIM 438A (1999) 376 S. Bachman et al. NIM 438A (1999) 376 Gain: 4 x 104 Mounting & working with GEM Itzhak Tserruya PHENIX Upgrade mini-Workshop

  12. CF4 + GEM + CsI work! Itzhak Tserruya PHENIX Upgrade mini-Workshop

  13. Setup: from the original sketch (end 2001)… Set up: • Detector: double GEM (10x10cm2) + PCB • Cosmic trigger: 3 layer plastic scintillators + Cherenkov counter (in near future) Electric scheme • Two HV power supplies for more flexibility • Cathode readout Cherenkov counter for high momentum muons (~min-1) Itzhak Tserruya PHENIX Upgrade mini-Workshop

  14. Setup: …to a more elaborated sketch (1.2002) … • Design almost complete • Manufacturing and order underway Itzhak Tserruya PHENIX Upgrade mini-Workshop

  15. Setup: … to the full design (2.2002) … Cherenkov cosmic ray trigger Cherenkov light reflected by 16 mirrors, in a pyramid arrangement, onto 4 large PM Mini HBD: CF4 radiator tank + Multi –Gem detector box Scintillators Itzhak Tserruya PHENIX Upgrade mini-Workshop

  16. Setup: … to real life (7.28.02) Cherenkov cosmic ray trigger Cherenkov light reflected by 16 mirrors in a pyramid arrangement onto 4 large PM Mini HBD: CF4 radiator tank + Multi –Gem detector box Scintillators Itzhak Tserruya PHENIX Upgrade mini-Workshop

  17. The mirror support Itzhak Tserruya PHENIX Upgrade mini-Workshop

  18. The mirrors mounted Itzhak Tserruya PHENIX Upgrade mini-Workshop

  19. Status & plans: • Basic equipment to work with GEM is ready: • UV source, x-ray and alpha sources • Electronics, gas system, monochromator • Double GEM detector is working at the WIS in Ar/CO2 • Gain 4.5·104 achieved and is consistent with measured at CERN • CsI photocathodes routinely produced with reproducible results • Moving to CF4 within the next weeks. • Cosmic ray trigger • Procurement of parts and components completed (only CF4 radiator tank is missing) • Setting-up underway • Mini HBD • Procurement of parts and components almost completed (only CF4 radiator tank is missing) • Multi-GEM box ready. • Simulations • Optimize shade configuration to absorb scintillation • Granularity Itzhak Tserruya PHENIX Upgrade mini-Workshop