GE Telecommunications Base Wiruca, Nicaragua

GE Telecommunications Base Wiruca, Nicaragua. Team 7: Section 12 Ricky Schaffer Mike Stanowski Adriana Philip Submitted to Dr. Colledge. Table of Contents. Project Background Ideas and Analysis Design Specifications Cost Analysis Social Implications Summary. Recognizing the Need.

barny
Download Presentation

GE Telecommunications Base Wiruca, Nicaragua

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GE Telecommunications BaseWiruca, Nicaragua Team 7: Section 12 Ricky Schaffer Mike Stanowski Adriana Philip Submitted to Dr. Colledge

  2. Table of Contents • Project Background • Ideas and Analysis • Design Specifications • Cost Analysis • Social Implications • Summary

  3. Recognizing the Need • Provide a reliable means of cell phone service to small villages such as Wiruca, Nicaragua.

  4. Defining The Problem • To find an inexpensive and environmentally friendly way of supplying power to a telecommunication system.

  5. Gantt Chart

  6. Background Information Wiruca, Nicaragua • 48 families • All are coffee growers • Earnings $100/mth/house • Disposable income of $10/mth/house • No electricity • No cell phone service, but have cell phones for use when traveling • If power were available, they would power: TV, radio, lights, fan • Current cell phone tower/system costs: $300,000-$500,000 per tower/equipment and $90,000 for the energy system to power it (solar system producing 30 kW/hr/day. (32 solar panels – each 200 W and 24 volts) • Other nearby communities recently put in a solar system for $17,000 for 200 people. • Diesel fuel is $1/liter

  7. Background Information (cont’d) • Security guard protecting each cell phone tower installation 24 hours each day. • The current protection building for the equipment is built by a subcontractor which the telecommunication firm employs. • Rated for hurricane and earthquake conditions in the country. • The community pays 1.7 Cordobas/hr for the first 25 kW-hr. They pay x Cordobas for the second 25 kW-hr. They pay y Cordobas for the third 25 kW-hr, and so on. • The generators currently employed are located inside the building for security and weather reasons. • The area is mountainous – used for growing coffee. There are micro-hydro systems located in surrounding communities. • The communities and the university are VERY interested in establishing businesses around the power generation systems. • If power lines are run from the power generation system – there MAY be regulatory concerns. Many efforts are taken to install similar systems, and if they produce less than 13.v kVolts, there are USUALLY no problems from regulators. • CLARO is the cell phone service provider.

  8. Sodium Metal Halide Battery • Lasts about 15 years (around 2500 cycles) • Temperature Range: -40⁰ C to 55 ⁰ C • It takes 7.5 hours at 150 amps to recharge the sodium metal halide battery once it has discharged (used) 80% of its energy capacity. • Temperature – 270C-350C (inside the case) • Voltage – 1.8-3.4V • Current- 20-100A • Cell power – 100-200W • Resistance (initial) – 7-10mΩ • Pressure- 1-2 atmospheres

  9. Possible Design Solutions • Required • NaMx Battery • Power Generator • Alternative Energy • Geothermal • Wind • Solar • Micro-hydro

  10. Screening Matrix

  11. Criteria

  12. Weighted Matrix

  13. Final Decision • Solar and Wind combination. • Provides most feasible option with minimum cost and maximum output.

  14. Wind Energy Specifications • Skystream Turbine (GE subsidiary) • Rated Capacity: 2.4 kW • Weight: 170 lb (77 kg) • Rotor Diameter: 12 ft (3.72 m) • Direction of Rotation: Clockwise looking upwind • Blades: 3-Fiberglass reinforced composite • Rated Speed: 50 - 325 rpm • Maximum Tip Speed: 216.5 ft/s (66 m/s) • Survival Wind Speed: 140 mph (63 m/s) • Cost: $6,212 x 3 = $18,636

  15. Solar Energy Specifications • Electrical Parameters-Optimal Power output: 225 watts-Power output tolerances: +/- 3%-Module Efficiency: 13.8%-Power Output: 38 W -Voltage at Pmax (Vmpp): 29.5 Volts-Current at Pmax (Impp): 7.63 Amps -Operating Conditions-Operating temperature: - 40 to + 90C-Max. wind load: 50 psf-Max. snow load: 113 psf-Mechanical Characteristics-Dimensions (L x W x D): 65" x 39" x 2" (1650 x 990 x 50 mm)-Weight: 43.7 lbs (19.8 kg) • Cost: $516.90 x 38= $19,976.81 + Labor

  16. Solar Panel Angle Calculations

  17. Generator Specifications • GE Product • Running Watts (W)-7000 (LP) • Surge Watts (W)-10500 (LP) • Operation-Fully Automatic • Voltage (V) 120 • Amps-58.3/29.1 (LP) • Cost: $2289

  18. Supplying the Battery With the 84 watts per square meter • Insulation • Internal Insulation (thermal and electrical) to maintain necessary internal temperature • Generator to supply needed power

  19. Additional Loads • Lighting • Three 30W Halogen CFL Bulbs • Total: 90W • GE Product • Cost: 8 x $9.31 = $74.48

  20. Hut Specifications • Houses generator and battery • Cement Walls • Fire resistant • Capable of handling various weather conditions • Cost of cement: ((15 ft x 15 ft)x2)=450sqft x $2 = $900 + (4x(15ftx8ft) x $2=$960 + (4( .5 ft x 15ft x 8ft) x $2= $480 • Total Cost = $2340 • Security • Barbed Wire Fence: $1.50 per foot • Total Fencing: 100 ft (25 ft sides around the hut) • Total Cost = $150 • Total Hut Construction Costs: $2490 + Labor

  21. Estimated Total Startup Cost • Wind System, Solar System, Generator, Lights, and Hut Construction • $43,466.29 + Labor

  22. Prototype

  23. Schematic of Telecom Base Station

  24. Time Value of Money • Diesel Power is a constant flow of cost of $1/liter. • Rate of inflation is currently 1.7% • Alternative energy is a one time large cost and some small additional maintenance costs • Diesel Power is becoming more and more expensive as alternative energy becomes less and less expensive

  25. Social Implications • Widespread use of cell phones would allow residents of Wiruca better access to areas around them for trading purposes • Eventually could move Nicaragua out of developing status and increase global competitiveness • Would increase global communication

  26. Summary • Green telecom station in Wiruca, Nicaragua. • Best option: Solar-Wind Hybrid • Estimated Total Startup Cost: $43,466.29

  27. References • http://portsmouthrienergy.com/A2.pdf • http://www.bonanza.com/booths/magnet4less/items/1_2KW_Max_Hybrid_Wind_Turbine_Generator_24V__Controller • http://www.solarhome.org/solarpanelsbywatt.aspx • http://solarelectricityhandbook.com/solar-angle-calculator.html • http://www.1000bulbs.com/product/56637/FC30-29392.html • http://www.docstoc.com/docs/9121223/GE-PowerPoint-Template • http://www.solarhome.org/yinglisolaryl225p-29b225watt20voltsolarpanel.aspx • http://www.pasturemanagement.com/electricfencing.htm • http://www.magnet4less.com/product_info.php?products_id=643 • http://www.homestandbygeneratorsystems.com/products/aircooled/7kW-Automatic-HGS-040315GEC-0/