E.I. CONSTRUCTION AND DEVELOPMENT CORP. #2247 ALEXANDER ST. COR MARCONI & FORD STS., BRGY. SAN ISIDRO, MAKATI CITY TEL. NOS. 843-55-14/ 845-36-34; TELEFAX NO. 844-18. PROJECT PRESENTATION.
E N D
E.I. CONSTRUCTION AND DEVELOPMENT CORP. #2247 ALEXANDER ST. COR MARCONI & FORD STS., BRGY. SAN ISIDRO, MAKATI CITY TEL. NOS. 843-55-14/ 845-36-34; TELEFAX NO. 844-18 PROJECT PRESENTATION SEN. GIL J. PUYAT AVE. PEDESTRIAN OVERPASS PROJECT – RCBC SIDE (along Sen. Gil J. Puyat Avenue) City of Makati
Location Map This Site
Outline • Project Scope of Work • Project Methodology • Work Schedule / Work Sequence • Safety & Traffic Plan / Site Set-up
Scope of Work • Structural Works - Structural Framing for overpass (Bridge) - Column & Pedestal - Stairs • Civil and Architectural Works - Bored Piles - Pile Cap Foundation - Escalator Pit - Supply and Installation of Aluminum Composite Panel 4mm thk - Supply and Installation of Tempered Glass Railings 12mm thk
Methodology Work Plan & Schedule Construction of Sen. Gil J. Puyat Pedestrian Overpass Project - RCBC SIDE PROJECT TITLE Sen. Gil J. Puyat Ave., Makati City PROJECT LOCATION 9 Months TIMELINES OF COMPLETION
Project Methodology BEFORE CONSTRUCTION • Conduct Pre-Construction site inspection to validate existing utilities. • Securing of necessary permits, As Built Drawings of the existing underground utilities. • Coordination with concern agencies prior to start of work. • Preparation and installation of required Project ID and signage. • Preparation of traffic management plan/Project Safety plan • Necessary Traffic signs and warning barricades shall be provided. • All personnel that will be deployed to site shall undergo safety orientation.
Project Methodology BORED PILING PROCEDURE Excavation of Pile Shaft Cleaning of Pile Shaft Preparation and Installation of Reinforcing Bars Pouring of Concrete
Project Methodology • BRIDGE ERECTION PROCEDURE & SEQUENCE • Mobilization of the erection crew with the necessary equipment. • Prepare and install all necessary power lines from the nearest point of the power supply to the assembly area. (Gen. Set) • Match marking and proper storage of members and component parts of the structure to ensure proper assembly and positioning when final assembly commences. • Before mobilization start, all elevation and alignment of existing steel pedestal should be check by QA/QC to ensure correctness, and should provide crane access prior for proper erection. Crane ways must be free of all obstruction. • Delivery and installation of column pedestal at B. • Delivery and installation of temporary support along Center Island of the main road. • Provide protection for the delivered materials to keep from dirt and rust. Protection must be level to ensure straightness of the materials.
Project Methodology • BRIDGE ERECTION PROCEDURE & SEQUENCE • Mobilization of the erection crew with the necessary equipment. (cont.) • Splicing of main beams and platform at site warning devices of segment 1 and segment 2. • Provide safety barricade, signage and early warning devices to warn incoming vehicles and pedestrians. • Provide traffic personnel to man traffic along the area of erection. • Delivery and installation of temporary support along the center island on the road. • Provide safety net for fall protection of workers and safety for small tools that may injure workers working below.
Proposed Traffic Plan/Scheme • Traffic management will be strictly observed and put into practice during the construction period. • Proper barricades, lightings, sufficient traffic warning signs and information's as well as the flagmen must be placed on sites to properly warn and guide the public for their safety. • All site activities shall be well coordinated to TAPI/MACEA. • Working area will be properly enclosed with (board-up and bollards) with appropriate signs put in place. • Flagmen or traffic crews will be provided if necessary The Following are the Schematic Diagram of the Proposed Traffic Flow wherein the construction are being implemented.
Site Set-up Week 1 to 2
Site Set-up Week 3 to 4
Site Set-up Week 5 onwards
Site Set-up Activity: Launching of Bridge Frame Time: 11PM to 4AM Location: Buendia Westbound corner Ayala Ave. (infront of The Columns) TRAFFIC SCHEME: Buendia Westbound corner Ayala Ave. closed Divert traffic flow of vehicles traveling along Buendia westbound. Right turn to Zuellig then left turn to Malugay then right turn to Ayala Ave. extension then left turn to Yakal and left turn to Pasong Tamo and right turn to Buendia or from Malugay right turn to Ayala Ave. Extension and take U-turn slot and right turn to Buendia Ave. Vehicles coming from Ayala Ave. goin to Buendia westbound should take left turn to Buendia. Traffic advisory and directional signages will be installed in all strategic locations. Traffic enforcers will be deployed. Subject to approval of concerned LGU’s.
Site Set-up Activity: Launching of Bridge Frame Time: 11PM to 4AM Location: Buendia Westbound corner Ayala Ave. (infront of The Columns)
Site Set-up Activity: Launching of Bridge Frame Time: 11PM to 4AM Location: Buendia Eastbound corner Ayala Ave. (infront of RCBC Plaza) TRAFFIC SCHEME: Buendia Eastbound corner Ayala Ave. closed Divert traffic flow of vehicles traveling along Buendia going east then left turn to Salcedo then left turn to Geronimo and right turn to Buendia Ave. Vehicles coming from Ayala Ave. north bound going to Buendia Eastbound take right turn to Salcedo then left turn to Geronimo and right turn to Buendia Ave. Traffic advisory and directional signages will be installed in all strategic locations. Traffic enforcers will be deployed. Subject to approval of concerned LGU’s.
Site Set-up Activity: Launching of Bridge Frame Time: 11PM to 4AM Location: Buendia Eastbound corner Ayala Ave. (infront of RCBC Plaza)
PROPOSED AYALA-BUENDIA OVERPASS ALONG SEN. GIL PUYAT AVENUE THE COLUMNS SIDE RCBC PLAZA SIDE FROM EDSA TO TAFT AVE. FROM TAFT AVE. TO EDSA
WEEK 1 TO 2 DRILLING WORKS EQUIPMENT AND MATERIALS MOBILIZATION REBAR WORKS CONCRETING WORKS DISPOSAL OF EXCAVATED SOIL PILE TESTING THE COLUMNS SIDE RCBC PLAZA SIDE
WEEK 3 TO 4 TRANSFER EQUIPMENT AND MATERIALS MOBILIZATION CONSTRUCTION OF PILE CAP FOUNDATION AT THE COLUMNS SIDE DRILLING WORKS CONSTRUCTION OF ESCALATOR PIT AND STAIR FOOTINGS DISPOSAL OF EXCAVATED SOIL REBAR WORKS
WEEK 5 ONWARDS CONSTRUCTION OF PILE CAP FOUNDATION AT RCBC SIDE CONSTRUCTION OF ESCALATOR PIT AND STAIR FOOTINGS
WEEK 5 ONWARDS ERECTION OF COLUMNS ON BOTH ENDS COMPLETION OF TEMPORARY SUPPORT THE COLUMNS SIDE RCBC PLAZA SIDE
LAUNCHING OF BRIDGE FRAME INSTALLATION OF 1ST AND 2ND SEGMENT INSTALLATION OF 3RD SEGMENT THE COLUMNS SIDE RCBC PLAZA SIDE 1ST SEGMENT 2ND SEGMENT 3RD SEGMENT
CONSTRUCTION OF CONCRETE STAIRS THE COLUMNS SIDE RCBC PLAZA SIDE ARCHITECTURAL WORKS MECHANICAL, ELECTRICAL, PLUMBING & MISCELLANEOUS WORKS
PROPOSED AYALA-BUENDIA OVERPASS THE COLUMNS SIDE RCBC PLAZA SIDE FROM EDSA TO TAFT AVE. FROM TAFT AVE. TO EDSA