1 / 71

Santi Ch aroenpornpattana , Ph.D. Assistant Professor & Director

Construction Planning and Scheduling Construction Management Training Program For Technical Departments by AIT Extension & PRMP, Government Of Punjab. Santi Ch aroenpornpattana , Ph.D. Assistant Professor & Director Construction Engineering & Management Program

beata
Download Presentation

Santi Ch aroenpornpattana , Ph.D. Assistant Professor & Director

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Construction Planning and SchedulingConstruction Management Training Program For Technical Departments by AIT Extension & PRMP, Government Of Punjab SantiCharoenpornpattana, Ph.D. Assistant Professor & Director Construction Engineering & Management Program King Mongkut’s University of Technology Thonburi AIT Conference Center 18th August 2009

  2. Planning and Scheduling Santi Charoenpornpattana, Ph.D. @2009

  3. Three basic objectives of construction project management Cost Time Performance Santi Charoenpornpattana, Ph.D. @2009

  4. What is “Planning” ? • General: “the function of selecting organization’s objectives and establishing the policies, procedures, and programs necessary for achieving them. • Project management context: “establishing an predetermined course of action within a forecasted environment” Santi Charoenpornpattana, Ph.D. @2009

  5. Planning & Control / Time & Cost Time Cost Scheduling Cost Planning Planning Schedule Control Cost Control Control SantiCharoenpornpattana, Ph.D. @2009

  6. Planning & Control / Time & Cost Tools Time Cost Bar Chart/ CPM Estimation/ Cost Planning Planning Bar Chart/CPM/ S-Curve Earned Value Control Santi Charoenpornpattana, Ph.D. @2009

  7. What is “Scheduling” • “the function of arranging and sequencing the planned activities in order to achieving the objectives” • Questions to be answered: • What is the total duration of the project? • What are the start and finish dates for the activities? • Can a project activity be delayed? How long? Santi Charoenpornpattana, Ph.D. @2009

  8. Real life example • It’s now 8.30 am. • You want to know the earliest time you can finish personal task for the lecture today: • Take a bath (5 min) • Dress up (5 min) • Boil water for tea (10 min) • Food reheat (5 min) • Eat breakfast (10 min) • Having tea (5 min) • Walk to lecture room (5 min) • Can you be on time for the class? If not, what should I do? • What is the earliest time you could reach the class? • How much free time do you have before the class? • Can I have any break after each task? Santi Charoenpornpattana, Ph.D. @2009

  9. Planning Process 1 2 5 DESCRIP OF WORK “HOW” OBJECTIVES LOGICAL SEQUENCE AND RESOURCE REQUIREMENTS 7 PROJECT ORGANIZATION BUDGET MANPOWER 4 SCHEDULE “WHO” 3 WORK PLAN “WHAT” SCOPE OF WORK 6 PROJECT OBJECTIVES “HOW MUCH” “WHO DOES WHAT” “WHEN” WORK PACKAGE DESCRIPTION WORK BREAKDOWN STRUCTURE PROJECT BASE PLAN WORK SCHEDULE Source: lecture note Dr. ChotchaiCharoenngam,  CE70.21 Integrated Project Planning and Control School of Engineering and Technology, AIT - 2008 SantiCharoenpornpattana, Ph.D. @2009

  10. Typical Scheduling techniques • Bar Chart • Network Diagram Santi Charoenpornpattana, Ph.D. @2009

  11. Categorizing scheduling techniques Santi Charoenpornpattana, Ph.D. @2009

  12. Bar Chart Santi Charoenpornpattana, Ph.D. @2009

  13. Barchart • Henry L. Gantt, World War I -1917 • Classic technique & Well known Pro: • Easy, Very effective communication tool • Very popular for representation of simpler schedules • Understandable to all level of management Con: • Can be complex when have >100 activities • Key shortcoming: No dependencies captured • Most effective as reporting format rather than representation Santi Charoenpornpattana, Ph.D. @2009

  14. Bar Chart – construction phase ACTIVITIES Foundation Structural Architectural M & E Landscape TIME jan mar may feb april june july dec Santi Charoenpornpattana, Ph.D. @2009

  15. Bar Chart – whole development Santi Charoenpornpattana, Ph.D. @2009

  16. Hierarchy of Bar Charts Santi Charoenpornpattana, Ph.D. @2009

  17. Network Diagram Santi Charoenpornpattana, Ph.D. @2009

  18. Network Diagram • Shows not only timing but also interrelations and dependencies of the activities • Logical sequencebehind the activities are important • Two main types of network diagram • CPM (Critical Path Method) • PERT (Program Evaluation Review Technique) Activity 1 Activity 2 Activity 3 E C A B D Activity 4 Activity 5 Santi Charoenpornpattana, Ph.D. @2009

  19. CPM • Standard scheduling technique in construction industry • Logical sequence is the key • Embedded in all commercial scheduling software (MS Project, Primavera Project Planner, etc) • Very effective for control purpose • Specified in the contract of almost all medium to large scale projects as a rule especially for the processes of change order and dispute resolution Santi Charoenpornpattana, Ph.D. @2009

  20. Two ways of representing CPM • Arrow diagramming • Precedence diagramming Formwork procurement Formwork & Concrete Erecting steel Laying out footings Excavating footings Mobilizing 1 2 3 4 5 6 Steel procurement Formwork procurement Mobilizing Laying out footings Excavating footings Formwork & concrete Erecting steel Steel procurement Santi Charoenpornpattana, Ph.D. @2009

  21. Steps in CPM scheduling Identifying activities Assigning logical interrelationships between activities Assigning duration for activities Calculation Santi Charoenpornpattana, Ph.D. @2009

  22. 1. Identifying activities • Breaking down project’s work into smaller elements • Work Breakdown Structure (WBS) Santi Charoenpornpattana, Ph.D. @2009

  23. Templates Santi Charoenpornpattana, Ph.D. @2009

  24. Example 1 WBS of house construction Santi Charoenpornpattana, Ph.D. @2009

  25. Example 2 WBS of large scale building construction Santi Charoenpornpattana, Ph.D. @2009

  26. Numbering Santi Charoenpornpattana, Ph.D. @2009

  27. How many level ? • Until the manageable level • Until there is no important constraints between sub-activities • For small to medium construction work, 4-5 levels would be appropriate • For large-scale project, multiple-linked WBS are used. (Master WBS, GC WBS, SC WBS, etc.) Each is done by different party. Santi Charoenpornpattana, Ph.D. @2009

  28. 2. Logical interrelationships • Time-sequence relationships among the various activities • Mandatory – technical constraint • Foundation before structure • Excavation beforebackfilling • Discretionary – management constraint • Resource limitation • Organization policy/procedure • External – external constraint • Seasonal condition • Law and regulations Santi Charoenpornpattana, Ph.D. @2009

  29. Example 3 D Arrow diagram B A dummy arrow F 1 2 5 6 C E 4 Precedence diagram B D F A C E Santi Charoenpornpattana, Ph.D. @2009

  30. Quiz Santi Charoenpornpattana, Ph.D. @2009

  31. Answer Found Struc Floor Rough Excav Finishing Base Rafter Roof Wall Clean Landscape Santi Charoenpornpattana, Ph.D. @2009

  32. Arrow vs Precedence diagramming Santi Charoenpornpattana, Ph.D. @2009

  33. Arrow vs Precedence diagramming Santi Charoenpornpattana, Ph.D. @2009

  34. 3. Duration • Amount of time assigned to complete a particular activity • How to determine? • Historical information • Information from subcontractor • Handbook • Duration = Work Quantity Crew production rate Santi Charoenpornpattana, Ph.D. @2009

  35. 4. Calculation • Forward & Backward calculation • The questions: • What is the total duration of the project? • What are the start and finish dates for the activities? • Can a project activity be delayed? How long? Santi Charoenpornpattana, Ph.D. @2009

  36. Notations Early start Early finish Activity description j i Duration Total float Late start Late finish Activity Description Early start Early finish Duration Late start Late finish Total float Santi Charoenpornpattana, Ph.D. @2009

  37. Forward pass 0 3 3 7 A B 2 3 1 3 TF 4 TF LF LS LS LF EF = ES + D B A 3 3 0 4 3 7 LS LS LF LF TF TF ES EF EF ES Santi Charoenpornpattana, Ph.D. @2009

  38. Backward pass 0 3 3 7 A B 2 3 1 3 TF 4 TF LF is assigned or obtained 3 1 3 7 B A 3 3 0 4 3 7 LS = LF - D TF = LF – D – ES 3 0 7 3 0 0 EF ES EF ES Santi Charoenpornpattana, Ph.D. @2009

  39. What is “Float” • Float or slack of activity is a measure of flexibility, or inherent surplus time in the activity’s scheduling • It indicates how long the activity can be delayed or extended without having effect on completion of the whole (or part) project Santi Charoenpornpattana, Ph.D. @2009

  40. Example analysis B 4 8 C 2 4 2 4 CRITICAL PATH 2 4 4 8 0 0 A F 2 10 0 8 2 2 D E 3 5 0 8 2 3 2 10 1 2 0 0 5 6 6 8 3 3 Santi Charoenpornpattana, Ph.D. @2009

  41. What the “critical path” can tell? • The path is critical ! • No delay is allowed in the path • Management must take special care on all activities along the critical path • Acceleration of the critical activities can shorten total project duration • Who cause delay ! Santi Charoenpornpattana, Ph.D. @2009

  42. Quiz Santi Charoenpornpattana, Ph.D. @2009

  43. B A A B A B B A EF EF EF EF EF EF EF EF ES ES ES ES ES ES ES ES D D D D D D D D LS LS LS LS LS LS LS LS LF LF LF LF LF LF LF LF Logical relationships • Four logical relationships: 2. Start-to-Start (SS) 1. Finish-to-Start (FS) Can start B only when A started Can start B only when A finished 4. Start-to-Finish (SF) 3. Finish-to-Finish (FF) Can finish B only when A finished Can finish B only when A started Santi Charoenpornpattana, Ph.D. @2009

  44. B B A A A B A B EF EF EF EF EF EF EF EF ES ES ES ES ES ES ES ES D D D D D D D D LS LS LS LS LS LS LS LS LF LF LF LF LF LF LF LF Lag • Waiting duration before beginning of the subsequent action 2 7 3 5 Santi Charoenpornpattana, Ph.D. @2009

  45. 0 3 4 5 6 7 8 1 2 6 2 6 4 4 2 Excav Excav 2 Conc Conc 2 Excav 1 Conc 1 Use of SF SS FF and Lag • Excavation takes 6 days • Concrete takes 6 days • Concrete can be started after excavation is already started for 2 days • Concrete can be finished after excavation is already finished for 2 days Excavation Concrete 2 2 Santi Charoenpornpattana, Ph.D. @2009

  46. F H G I E D C B J A K EF EF EF EF EF EF EF EF EF EF EF ES ES ES ES ES ES ES ES ES ES ES 6 0 2 0 6 2 3 4 2 3 4 LS LS LS LS LS LS LS LS LS LS LS LF LF LF LF LF LF LF LF LF LF LF Calculation of PDM 1 3 1 2 Santi Charoenpornpattana, Ph.D. @2009

  47. E A I B C H D J G F K 2 2 0 0 3 6 2 4 6 3 4 Calculation of PDM 1 3 1 2 Santi Charoenpornpattana, Ph.D. @2009

  48. F C I G 8 4 15 12 12 6 0 4 6 4 4 3 5 8 1 14 14 17 5 9 Calculation of PDM B D 3 6 0 4 3 2 1 0 4 3 6 3 E H J K 9 15 17 17 4 9 15 17 2 6 2 0 A 0 0 0 7 9 15 17 9 15 17 17 0 0 1 2 Santi Charoenpornpattana, Ph.D. @2009

  49. Quiz Santi Charoenpornpattana, Ph.D. @2009

  50. Float Santi Charoenpornpattana, Ph.D. @2009

More Related