1 / 17

The Who’s Final Production Presentation “Better than the last one”

This final production of top-notch pinball machinery showcases improved features like double dovetail and trademarked logos. With resources including vertical machining center and various tools, the process plan details wooden and aluminum base manufacturing. The fixture, dubbed "The Pinball Wizard," estimates work content and total hours. The status of materials, tooling, and fixtures is outlined, with costs and licensing considerations provided. For any inquiries or clarifications, feel free to ask!

beatrizm
Download Presentation

The Who’s Final Production Presentation “Better than the last one”

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Who’s Final Production Presentation“Better than the last one” Paul Freund Mark Radio Chad Swanson

  2. Previous Prototype • Single Dovetail • Solid Base • 2.5” x 4.5” • Oval Wood Base

  3. Final Product • Double Dovetail • Box Tubing for Base • 3” x 5” • Rectangular Wood Base • “Trademarked” Logo

  4. Haas Vertical Machining Center Router Cut-off Saw Fixtures ¾” Dovetail Cutter ¾” Spot Drill ¾” Flat End-mill 3/8” Flat End-mill 6” Face-mill Resources and Tooling

  5. Wood Base • Walnut • 4 ½” x 6 ½” x ¾” • Rectangular groove cut in to house Al base • Routed Edges • Natural Walnut Stain

  6. Wood Base Process Plan

  7. The Aluminum Base • 3” x 5” x 1/8” Al Box Tubing • 4 “male” dovetail ends cut into top • Bead blasted

  8. Aluminum Base Process Plan

  9. The Top • 3” x 5” x 3/8” • Double Dovetail • Bead Blasted • Field Feature • “Trademarked” Logo • Alternate Oval Logo

  10. Top Process Plan

  11. Top Process Plan (con’t)

  12. The Fixture: The Pinball Wizard

  13. Estimated Work Content (Time)50 Pieces • Dovetail Top ~ 3 Hours • Dovetail Base ~ 5 Hours • Machine Field ~ 5 Hours • Bead Blast ~ 5 Hours • Wood Bases ~ 3.5 Hours • Miscellaneous Filing ~ 2 Hours • Assembly ~ 1.5 Hours • TOTAL HOURS ESTIMATED ~ 25

  14. Status of Materials, Tooling, & Fixtures • Materials • All Aluminum arrived 11/14/2001 • Have 10 Wood Bases, 2-Day Lead Time for more • All tooling currently on hand, may need extra dovetail cutters • Either fixture modifications or new fixture to be machined for Aluminum bases

  15. Gantt Chart

  16. Costs • 3 x ½” Aluminum Stock—32’ = $181.54 • 3 x 5 Al Tubing = $182.88 • Shipping = $20.00 • Wooden Base = $75.00 • Miscellaneous = $75.00 • Machining/Resource Costs = $450.00 • Licensing = $350.00 • Personalization TOTAL = $1334.42 or $26.69/unit ($19.69/unit without licensing)

  17. QUESTIONS??????