1 / 23

NSLS – II ASAC Review

NSLS – II ASAC Review. Conventional Facilities Briefing Marty Fallier Director for Conventional Facilities National Synchrotron Light Source – II Project October 10, 2006. Outline. Conventional Facilities Scope Facility Overview Facility Program WBS Tunnel Design & Access

beau-cherry
Download Presentation

NSLS – II ASAC Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NSLS – II ASAC Review Conventional Facilities Briefing Marty Fallier Director for Conventional Facilities National Synchrotron Light Source – II Project October 10, 2006

  2. Outline • Conventional Facilities Scope • Facility Overview • Facility Program • WBS • Tunnel Design & Access • Differential Settlement • Vibration Mitigation • Utility Support • Temperature Stability • Control Room • Schedule

  3. NSLS II Facility Overview

  4. Site Plan NSLS Conf. Center Service Bldg Typ 4 CLOB CFN Future JPsi RF-LINAC AREA Future Guest House LOB Typ 4 Ring Bldg Loading Underpass

  5. Building Program

  6. Conventional Facilities WBS

  7. Floor Plan – CLOB 1st

  8. Floor Plan - CLOB 2nd

  9. Floor Plan – CLOB 3rd

  10. Tunnel Design • Roof and wall thicknesses generally driven by shielding criteria except inner wall in area of berm (just structural) • Outer wall (ratchet wall) is HD concrete • During T-I will study whether precast or poured in place provides best balance of technical and cost performance • Tunnel floor thickness driven primarily by vibration criteria • During T-I will do modeling to arrive at optimal thickness and section shape • Rigidly connected to exp. floor to create monolithic floor • Penetrations from above for power and cooling water • Penetrations from sidewall for HVAC Supply and Return

  11. Tunnel Design - Ring Building Section

  12. Tunnel Access • Egress for life safety achieved by exits at each service building location • Large shielded doors for equipment access provided at Service buildings for tunnel entry • Mandoors and labyrinth provided at each Service building • Vehicle ramp to roll-up door at 2nd floor of each Service Bldg provides equipment access to electrical mezzanine at top of tunnel • RF & LINAC areas integrated with CLOB structure have similar access as Service Bldgs

  13. Service Bldgs

  14. Differential Settlement • Measures to reduce potential for differential settlement include: • Thorough geotechnical analysis of site to identify problem areas • Minimize footprint over disturbed areas • Set finished floor elevation for maximum cut and minimum fill • Early site preparation contract for maximum time to cut, fill, compact and observe settlement prior to building contract. • Monolithic slab design for tunnel and experimental floor • High slab stiffness, Tunnel 36”; Experimental Floor 18” • Building loads isolated from tunnel and experimental floor slab • Access corridor isolated from experimental floor slab

  15. Vibration Mitigation • Measures to be implemented in conventional design include: • “Monolithic” slab for accelerator and experimental floor • Slab thickness and section changes based on vibration modeling results during Title I • Possible use of polymer admixtures for enhanced damping characteristics • Isolation of bldg structure from tunnel and slab • Inertial bases and isolation of machinery • Low flow velocity design for ducts and piping • Limited use of duct and piping isolation to avoid conversion & transmission of low frequency vibration • Commissioning of equipment and systems to include alignment, balancing & vibration measurement

  16. Utility Support • Utilities run underground in center of ring and distributed to five service bldgs (one in CLOB RF/LINAC area) • Minimizes pipe runs and pipe size in bldg proper • Minimizes potential noise and vibration impacts • Mechanical Utilities include: • Chilled water from expansion of Central CHW plant • Tower water from process cooling water tower • Potable water, compressed air, sanitary etc. • Electrical Utilities distributed via substation and load center at each services bldg

  17. Utility Support

  18. Utility Distribution

  19. Temperature stability • Key temperature stability requirement is tunnel air @ +/- 0.1C at a given location with respect to time. • Requires high resolution industrial grade instruments and controls with excellent repeatability. • Control scheme using programmable controllers and reheat with temperature reset capability • Space temp setpoint of 85 F is nominally equivalent to process cooling water supply setpoint to minimize temperature gradients • Should be readily achievable provided loads to accelerator components are relatively steady-state

  20. Tunnel Temperature Control

  21. Tunnel Air Distribution

  22. Control Room • The Accelerator Control Room is located on the second floor of the CLOB above the LINAC-RF area • Provides ready access to Tunnel, RF & LINAC areas and electrical mezzanine • Computer room is adjacent to control room and control room operators meeting room • Additional study is required to identify optimal cable routing which may indicate computer room may be more advantageously located on 1st or 3rd floor

  23. Schedule • Conventional Facilities Schedule has been coordinated with Accelerator requirements. • Construction sequencing will enable • Availability of Ring Bldg for LINAC, booster and storage ring installation to begin – June 2011 • LINAC & Booster can be sooner if required • Control/Computer room availability in CLOB - August 2011 • Conventional Construction complete - October 2011

More Related