Governing Board Meeting December 12, 2013. C-4 Canal Bank Improvements Belen Phase 2 Flood Protection Berm & Wall. John Mitnik, P.E. Engineering & Construction Bureau Chief. C-4 Canal Bank Improvements Belen Phase 2 Flood Protection Berm & Wall. Bid Summary.
E N D
Governing Board Meeting December 12, 2013 C-4 Canal Bank ImprovementsBelen Phase 2Flood Protection Berm & Wall John Mitnik, P.E. Engineering & Construction Bureau Chief
C-4 Canal Bank Improvements Belen Phase 2 Flood Protection Berm & Wall
Bid Summary • RFB Advertised: October 15, 2013 • Bid Opening: November 15, 2013 • Number of Bids received: 8 • Bid Range: $1,120,000 – 2,223,000 • Engineer’s Estimate: $1,429,549 to $1,580,028
Resolution • A Resolution of the Governing Board of the South Florida Water Management District to authorize entering into a 358 day contract with Arbor Tree & Land, Inc., the lowest responsive and responsible bidder, for C-4 Canal Bank Improvements Belen Phase 2, Flood Protection Berm & Wall Project, in an amount of $1,360,250.00, for which $1,110,892.00 in ad valorem funds are budgeted in FY14 Engineering & Construction Bureau's capital improvement program and the remainder is subject to the Governing Board approval of the FY15 budget; providing an effective date.