280 likes | 452 Views
Ayodeji Adeyemi Rhett Bouquet David Brasset Andrew Judice. Globalplex International Dock Port of South Louisiana Reserve, Louisiana. Introduction. Project Brief and Design Criteria Alternative Designs and Selection Permits Public Participation Health and Safety Construction Schedule
E N D
AyodejiAdeyemi Rhett Bouquet David Brasset Andrew Judice Globalplex International DockPort of South LouisianaReserve, Louisiana
Introduction • Project Brief and Design Criteria • Alternative Designs and Selection • Permits • Public Participation • Health and Safety • Construction Schedule • Construction Cost Estimate • Plans
Design Criteria The Project Outline Project Brief General Cargo Dock Port of South Louisiana Between River Miles 138 &139 St. John the Baptist Parish Reserve, Louisiana • Panamax Vessel with 65,000 dwt • General Cargo Design Load of 1000 psf • HS20-44 Truck Loading • Maximum Current of 4.5 Knots
Permits • Government Agencies • US Army Corps of Engineers • Levee Board • US Coast Guard • Riverboat Pilots • LADOTD • St. John the Baptist Parish
Permits Process • Efficient method • Thorough method • Letters of no objection Time • Six – eight months
Permits Elevated Roadway Structure LADOTD Project Permit Crossing LADOTD Right of Way
Public Participation Public input for the Preliminary Design Informing the public of temporary changes Informing the public of progress Suggestions of the public
Health and Safety Safety is part of the design process OSHA – Where do their regulations come from? OSHA – Structural requirements OSHA – Safety equipment and actions The power of OSHA
Cost Estimation: What is it? • Educated approximation of final cost. • Done at a point when: • A basic idea of material quantities is known • Before all of the final details have been worked out • Why is it important? • Prevents a waste of the engineer’s time and the clients money. • A worthwhile cost estimate • Total material cost • Total labor cost • Additional costs • GRAND TOTAL (Sum total material and labor)
Cost Estimation: The Components • Roadway Bridge • Abutment • Cast in Place Concrete • Compacted Fill • Piles • Levee Crossing • Cast-in-Place Concrete • Compacted Fill • Slope Paving • Roadway Deck • Precast Concrete Deck Slabs • Deck Framing (Girders & Diaphragms) • Painting • Roadway Bents • Piles • 6” Bracing • 8” Bracing • Structural Steel • Painting • T-Head Platform • Platform Deck &Framing • Timber Curb • Bollards • Cast-in-Place Concrete Deck • Finishing Concrete Deck • Structural Steel (Beams) • Piles and Pipe Bracing • 42”φ x .500” Pipe Piles • 12” φ Horizontal Bracing • 12” φ Vertical Bracing • Fender Connection to Pile • Painting • Fender System • Mooring Dolphins • Walkway Bents • Walkway Spans
Plans • Proposed General Arrangement • Shows Position of Roadway, Dock, and Dolphins • Selected Elevations Were Highlighted • Soil Borings are Indicated
Plans • Proposed Roadway Plan and Profile • Shows Elevation of Road at Start of Ramp, Highway Crossing, Levee Crossing. • Locations of the piles and the spread footings. • The road way is 12ft wide. • The span length is 1019 ft.
Plans • Sample Bent • A general view of the bent • 12ft wide, 10in thick concrete deck • W36X135 steel girder . • The pile used is a 24in diameter and run -50ft deep from it tip into the ground
Conclusions • T-Head Platform dock was chosen as the general cargo dock. • Importance of permit acquisition • Construction time of approximately 13 months. • The total project cost was estimated to be around $9.25 Million